Survey Documents Cost to Contractors of Payment Delays

Prompt Payment

June 20, 2018

Although slow payments are part of business as usual within the commercial construction industry, they are more pervasive and more costly than expected, according to results of a survey of U.S. construction subcontractors. This has cost consequences for the entire industry.

Subcontractors perform most construction activities, but slow payment cycles can hamper these small businesses from meeting payment obligations, such as payroll and material purchases. The cash flow cycle results in significant financing costs as well as liens placed against properties to ensure payment, notes Contract Simply, an automated workflow solutions provider that conducted the survey in partnership with Building Connected.

The purpose of the survey was to better understand how slow payments affect development project costs, risks and project completion. It distributed the survey to 1,300 contractors representing a wide diversity of construction trades. The survey’s findings indicate that slow payments in the industry result in US$40 billion in superfluous costs annually.
The survey results also revealed that

• 41% of subcontractors wait between 30 and 60 days for payment

• an additional 46% of those surveyed wait 60 to 90 day, confirming a PWC Working Capital report that engineering and construction sectors in the U.S. suffer from over 50 days sales outstanding (DSO).

• 83% of the contractors surveyed have been forced to file a lien due to slow payment, with a majority reporting having used business savings or a line of credit to float payments to others. For 75% of the contractors, this means incremental costs in the form of finance fees and administrative time averaging 3.3% of the total project costs, which equates to $40 billion for the industry as a whole.

• more than 70% of respondents indicated that if construction lenders and borrowers were to offer net 30 payments, they would collectively be willing to provide US$21 billion in discounts.

Since many contractors build financing fees into proposals, faster payments could avoid costly and time-consuming liens and lower project costs. Paying promptly also enables developers and builders to attract and retain the best subcontractors in a competitive labour market.

The study makes four recommendations for expediting payments:

• implement digital solutions to track and expedite payments and cut days from invoice processing

• offer e-payments options

• collect lien releases digitally with payments to eliminate friction

• automate invoice approval workflows with daily reminders

Find out more: https://cdn2.hubspot.net/hubfs/2886905/Contract Simply Construction Payments Report 2018 Final.pdf

Related Articles


Latest Articles


Changing Scene

  • Nexans Initiates Copper Mark Recertification for Montreal Site

    Nexans Initiates Copper Mark Recertification for Montreal Site

    April 27, 2026 Nexans Canada Inc. has initiated the Copper Mark recertification process for its site located at 460 Durocher Avenue in Montreal. As part of this process, an independent external assessment of the site is scheduled for April 22–24, 2026. Copper Mark is an independent assurance framework designed to assess the responsible practices of industrial sites against recognized Read More…

  • Fort Frances Memorial Sports Centre Adding Solar as Part of GICB Program

    Fort Frances Memorial Sports Centre Adding Solar as Part of GICB Program

    April 27, 2026 The Fort Frances Memorial Sports Centre will generate solar energy following an investment of $589,762 from the federal government through the Green and Inclusive Community Buildings (GICB) program. This funding will reduce greenhouse gas emissions and annual electricity costs for the facility. A rooftop solar generation system will convert solar energy into Read More…

  • IDEAL Electrical Announces $1M Donation and Partnership with Habitat for Humanity

    IDEAL Electrical Announces $1M Donation and Partnership with Habitat for Humanity

    April 27, 2026 In 2026, IDEAL Electrical will support four global Habitat for Humanity activations across Greater Toronto, Greater Chicago, the United Kingdom and Los Angeles/Southern California. These efforts will bring together IDEAL employees, electricians and apprentices, industry partners and electrical influencers to contribute more than 500 volunteer hours, $100K in materials and invaluable electrical skills Read More…

  • Ontario Investing $300 Million to Build and Upgrade Local Sport and Recreation Facilities

    Ontario Investing $300 Million to Build and Upgrade Local Sport and Recreation Facilities

    April 20, 2026 The Ontario government is investing an additional $300 million in the Community Sport and Recreation Infrastructure Fund (CSRIF) to build and upgrade sport and recreation facilities across the province. Announced as part of the 2026 Ontario Budget: A Plan to Protect Ontario, this brings total government funding for the program to $500 million, Read More…