Survey Documents Cost to Contractors of Payment Delays

Prompt Payment

June 20, 2018

Although slow payments are part of business as usual within the commercial construction industry, they are more pervasive and more costly than expected, according to results of a survey of U.S. construction subcontractors. This has cost consequences for the entire industry.

Subcontractors perform most construction activities, but slow payment cycles can hamper these small businesses from meeting payment obligations, such as payroll and material purchases. The cash flow cycle results in significant financing costs as well as liens placed against properties to ensure payment, notes Contract Simply, an automated workflow solutions provider that conducted the survey in partnership with Building Connected.

The purpose of the survey was to better understand how slow payments affect development project costs, risks and project completion. It distributed the survey to 1,300 contractors representing a wide diversity of construction trades. The survey’s findings indicate that slow payments in the industry result in US$40 billion in superfluous costs annually.
The survey results also revealed that

• 41% of subcontractors wait between 30 and 60 days for payment

• an additional 46% of those surveyed wait 60 to 90 day, confirming a PWC Working Capital report that engineering and construction sectors in the U.S. suffer from over 50 days sales outstanding (DSO).

• 83% of the contractors surveyed have been forced to file a lien due to slow payment, with a majority reporting having used business savings or a line of credit to float payments to others. For 75% of the contractors, this means incremental costs in the form of finance fees and administrative time averaging 3.3% of the total project costs, which equates to $40 billion for the industry as a whole.

• more than 70% of respondents indicated that if construction lenders and borrowers were to offer net 30 payments, they would collectively be willing to provide US$21 billion in discounts.

Since many contractors build financing fees into proposals, faster payments could avoid costly and time-consuming liens and lower project costs. Paying promptly also enables developers and builders to attract and retain the best subcontractors in a competitive labour market.

The study makes four recommendations for expediting payments:

• implement digital solutions to track and expedite payments and cut days from invoice processing

• offer e-payments options

• collect lien releases digitally with payments to eliminate friction

• automate invoice approval workflows with daily reminders

Find out more: https://cdn2.hubspot.net/hubfs/2886905/Contract Simply Construction Payments Report 2018 Final.pdf

Related Articles


Latest Articles


Changing Scene

  • Delta Transformers Appoints New Representative in Ontario

    Delta Transformers Appoints New Representative in Ontario

    October 8, 2026 Delta Transformers, a Canadian manufacturer of dry-type transformers, is pleased to announce the appointment of Spectrum Power Systems as their new representative in Ontario, Canada, effective October 1st, 2026. For over 27 years Spectrum Power Systems has been representing leading electrical manufacturers throughout Ontario. The company has a strong presence in the… Read More…

  • Former Electrical Contractor Principal Arrested Following ESA Referral to Police

    Former Electrical Contractor Principal Arrested Following ESA Referral to Police

    October 8, 2026 Arrest follows ESA licence revocation, $70,000 in previous fines and new electrical safety charges   Peel Regional Police recently arrested Rahyl Hassan, principal of former Licensed Electrical Contractor, Strak Holdings Inc., following an investigation in which the Electrical Safety Authority (ESA) cooperated with police.  ESA referred concerns about potential criminal activity to Peel… Read More…

  • Federal Government Announces $2 billion Investment to Deliver One Million Home Retrofits Across Canada

    Federal Government Announces $2 billion Investment to Deliver One Million Home Retrofits Across Canada

    October 8, 2026 The federal government has announced a $2 billion investment to deliver one million home retrofits across Canada. These energy-efficient retrofits will lower heating costs for Canadians and reduce emissions. First, they are launching a new National Heat Pump Rebate to help up to 820,000 households make the switch to more efficient electric heat pumps: Heat pumps… Read More…

  • FCM and the Government of Canada Announce $66.3 M in 162 Energy Efficient Housing Projects

    FCM and the Government of Canada Announce $66.3 M in 162 Energy Efficient Housing Projects

    September 8, 2026 Funding supports homeowners and affordable housing providers in reducing energy costs and improving quality of life, while adding jobs to communities coast-to-coast  The Government of Canada and the Federation of Canadian Municipalities (FCM) today announced that $66.3 million in funding has been approved for 162 energy efficiency projects across the country. The… Read More…