Guide to the Canadian Electrical Code, Part I — Instalment 40

Bill Burr

 

Aug 13, 2018

By William (Bill) Burr

The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook** but will hopefully provide some help in navigating, while reading the code.

The 24th Edition of the CE-C, Part I, (C22.1-18)* is now available from CSA Group. This discussion of Section 78 — Marine Wharves, Docking Facilities, Fixed and Floating Piers, and Boathouses is based on the new edition.

Rule 80-000 notes that this is a supplementary or amendatory section of the code and applies only to the installation of impressed current cathodic protection systems. Appendix B and the CEC Handbook have additional information and descriptions of cathodic protection.

Rule 80-002 provides wiring methods for DC wiring and includes:

  • conformance to Section 12, except for below ground burial of not less than 450mm or 200mm in raceway or with mechanical protection
  • conformance to Section 18 and Section 20 in hazardous areas

Where DC wiring is installed underground below a Section 20 (Annex J20) Class I hazardous area, it may be buried to a depth not less than 450 mm or 200mm in raceway, providing the wiring is in threaded rigid conduit and sealed in accordance with rules 18-104 or 18-154, where it emerges from the ground.

Rule 80-004 requires that DC cathodic protection wiring be a minimum No. 12 AWG, except for instrumentation and reference electrode leads, and be selected in accordance with rule 12-102 (3) with regard to location and conditions of use.

Rule 80-006 specifies that splices, taps and connections made in conductors underground or exposed to the weather must be

  • made by welding, by a positive compression tool, by crimping and soldering, or by means of a copper, bronze, or brass cable connector
  • sealed against moisture by taping or other method as effective as the original insulation
  • connected to piping by thermit welding, or by a clamp of the same material as the piping or anodic to it
  • connected to a tank or other structure with a welded stud, thermit welding or other permanent means
  • sealed against moisture by the application of a material resistant to any corrosive environment

Rule 80-008 requires that the cathodic protection system rectifier be provided with a dedicated circuit in accordance with the requirements of Section 12.

Rule 80-010 outlines that each rectifier unit of a cathodic protection system have a separate disconnecting means installed

  • readily accessible
  • within sight of, and
  • within 15 m of the unit, or
  • integral to the rectifier and equipped with barriers or other suitable means to protect service personnel from live parts on the line side
  • rendered inaccessible to unauthorized persons by a lockable cover
  • labelled in a conspicuous, legible, and permanent manner identifying it as the disconnecting means for a cathodic protection system

Rule 80-012 requires that where the available operating voltage is more than 50V

  • the voltage difference between exposed points of the protected system, or
  • any point in the vicinity of the anodes, and any point 1m away on the earth’s surface, not exceed 10V.

Rule 80-014 requires that the following warning signs and drawings be provided:

  • a marking warning on tanks, pipes and structures that the cathodic protection system not be disconnected unless the power source is turned off
  • a sign, in a conspicuous location adjacent to the disconnecting means of electrical apparatus connected to the cathodically protected structures, advising that the cathodic protection be turned off and a temporary cathodic protection bypass conductor, appropriately sized for maximum available current, be installed before equipment or piping is replaced or modified
  • in a non-hazardous location, a sign advising that the use of a temporary cathodic protection bypass conductor, appropriately sized for maximum available current, may be used as an alternative to turning off the cathodic protection when replacing or modifying the protected equipment
  • a drawing, placed inside or near the rectifier cabinet, showing the location, polarity and anodes of underground cathodic protection wiring
  • a notice, placed in a conspicuous location adjacent to the entranceway of a storage or process container, advising that the cathodic protection system must be turned off before entering the container

In the next instalment, we will be discussing Section 84 – Interconnection of Electric Power Production Sources.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting; billburr@gmail.com

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

**Note the CEC Handbook is also published by CSA.

 

Related Articles


Latest Articles

  • Electrical Permit Requirements for Alarm System and Voice, Data, Video Installations

    Electrical Permit Requirements for Alarm System and Voice, Data, Video Installations

    January 19, 2026 Other than the exceptions listed below, electrical permits and inspections are required for all electrical work involved in the installation of intrusion and similar alarm systems in all structures. Electrical permits and inspections ensure that low -voltage systems are installed safely and in compliance with Code requirements. A permit and inspections must Read More…

  • The Role of Lighting in the AI-Powered Home

    The Role of Lighting in the AI-Powered Home

    January 14, 2026 Elizabeth Parks, President and CMO of Parks Associates, joins Derek Richardson, Founder and CEO of Deako, for a wide-ranging conversation on how lighting is becoming a core layer of the intelligent home. The discussion explores how Deako’s plug-and-play lighting approach is removing long-standing barriers to adoption by simplifying installation, reducing costs, and Read More…

  • What Canada’s Lighting Pulse Means for Contractors and Plant Buyers in 2026

    What Canada’s Lighting Pulse Means for Contractors and Plant Buyers in 2026

    January 14, 2025 By John Kerr From the ground, many contractors and plant teams are experiencing the same thing: jobs are there, but they are smaller, more price‑sensitive, and slower to release compared to past years. The Canadian Pulse of Lighting confirms that impression and offers some clear signals about how contractors and plant electrical Read More…

  • Guide to the Canadian Electrical Code, Part 1 – 26th Edition[i] – A Road Map: Section 54

    Guide to the Canadian Electrical Code, Part 1 – 26th Edition[i] – A Road Map: Section 54

    January 12, 2026 By Bill Burr The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the Read More…


Changing Scene

  • Leviton Canada Partners with The Titan Group to Strengthen Midwest Presence

    Leviton Canada Partners with The Titan Group to Strengthen Midwest Presence

    January 19, 2026 Leviton Canada is proud to announce its partnership with The Titan Group, who will now represent Leviton’s Residential and Commercial & Industrial product lines across the Midwest provinces, effective January 1, 2026. “We’re excited to begin our partnership with Titan,” said Bill Tischner, Western Sales Director. “Their industry expertise, commitment to service, Read More…

  • Hammond Power Solutions Appoints Xavier Biot as Vice President, Strategic Accounts

    Hammond Power Solutions Appoints Xavier Biot as Vice President, Strategic Accounts

    January 19, 2026 Hammond Power Solutions is pleased to announce the appointment of Xavier Biot as Vice President, Strategic Accounts. In this role, he will lead HPS’s strategic account teams. He will partner with customers to align transformer and power quality solutions with evolving electrification, sustainability, and operational needs. His focus will be on helping Read More…

  • Hammond Manufacturing Expands to Western Canada

    Hammond Manufacturing Expands to Western Canada

    January 13, 2026 Hammond Manufacturing have announced that they are opening a new distribution facility in the Southeast of Calgary, Alberta. The new facility includes over 50,000 sq ft of warehouse space. “This addition will better serve our customers in Western Canada and stock volume and larger products to ensure our distributors have an improve stock Read More…

  • ABB Chosen to Supply Technology for BC Ferries’ New Major Vessels

    ABB Chosen to Supply Technology for BC Ferries’ New Major Vessels

    January 12, 2026 ABB will supply a complete package of power, propulsion and control technology for four new double-ended passenger and car ferries operated by British Columbia Ferry Services (BC Ferries). One of the largest ferry operators in the world, BC Ferries provides year-round vehicle and passenger service on 25 routes to 47 terminals, carrying Read More…