Secondary Network Arc Flash Case Study

Arcflash

Aug 18, 2019

By Tony Oruga

Network crews were working in an electrical room tasked to install an 800 A disconnect for a temporary service on the network secondary. The 3-spot network was energized at 480 V on the secondary (34.5 kV on the primary) and all three network protectors were closed and serving load. Each network protector installed was a 3000 A, 480 V Eaton CM52 unit equipped with an Arcflash Reduction Maintenance SystemE (ARMS). Prior to performing their work, crews enabled the ARMS function on all three units in the spot. This put all three network protectors in a “hair-trigger” mode, ready to clear any current condition that exceeded 2.5x the nameplate rating.

As part of standard utility work, all procedures were followed in accordance with their specific utility standard practices. The workers had the specified PPE for those specific work conditions. However, as in any work environment, unforeseen events still occur and crews are trained to deal with less than ideal circumstances. During this particular install, the worker lost positive control of the wrench he was using to install 500 kcmil cable to an energized copper bus. This resulted in the wrench hitting the unistrut, which created a path to ground between the unistrut and the live network secondary. The calculated available fault current at the collector bus is 101.2 kA assuming 25 kA symmetrical available fault current on the 34.5 kV primary bus with balanced contribution.

Because the ARMS protection system was enabled as a part of standard working procedure, each CM52 unit interrupted in approximately 1.9 cycles once the 7500 A threshold was met. According to crew reports, the ARMS device activated and cleared the fault before the worker noticed they had made contact with the energized bus. See Figure 1 for a depiction of the network arrangement.

[PLEASE INSERT EIN-34-WhitePaper-2.jpg HERE]

This technology has been proven with substantial test data to support its capability; however, this is the first report of the ARMS system being called to action during a network arc flash event involving real world circumstances that prevented severe injury or possible death to the worker. The purpose of this white paper is to share this event with others and help create a safer environment through technology for those working in these applications.

System characteristics

• Utility: Austin Energy
• Location: Austin, TX
• Network size: 3-spot network
• Transformer size: 2000 kVA delta-wye; 7% impedance
• Primary system voltage: 34.5 kV
• Secondary voltage: 480 V
• Network protector size: 3000 A; 480 V
• Network protector type: Eaton CM52
• Available incident energy: approximately 200 cal/cm2 (without ARMS considered) based on system analysis
• Available fault current on 480 V secondary: 101.2 kA (3 x 33.7 kA for parallel contribution)
• CM52 ARMS total clear: 1.9 cycles on average
• CM52 ARMS activation: at 2.5 x 3000 A (nameplate rating) = 7500 A

Go here for additional network protector ARMS technical information.

Tony Oruga is a product and sales manager for Eaton. This article was first published online: https://www.eaton.com/content/dam/eaton/products/utility-and-grid-solutions/network-protector-solutions/secondary-network-arc-flash-case-study-wp024002en.pdf

 

Related Articles


Latest Articles

  • Regulations Amending the Products Containing Mercury Regulations – A Call to Consultation

    Regulations Amending the Products Containing Mercury Regulations – A Call to Consultation

    January 29, 2023 By Line Goyette Under the Canadian Environmental Protection Act, 1999, the Canadian government is proposing the Regulations amending the products containing mercury. Consultation is open until March 9, 2023. The Products Containing Mercury Regulations (the Regulations), which were published on November 19, 2014, and came into force on November 8, 2015, prohibit the manufacture and import of products containing mercury… Read More…

  • A Career with Purpose – Apprentices Building Canada’s Reduced Carbon Future

    A Career with Purpose – Apprentices Building Canada’s Reduced Carbon Future

    January 27, 2023 By Yoana Turnin, Project Manager, EHRC In 2021, Canada joined 120+ other countries in committing to achieving net-zero emissions by year 2050 in an effort to “avert the worst impacts of climate change.” In a few words, that means either reducing or offsetting the economy’s greenhouse gas emissions through electrification, energy efficiency… Read More…

  • Challenges, Opportunity, and Labour Demand in the Construction Industry

    Challenges, Opportunity, and Labour Demand in the Construction Industry

    January 27, 2023 By Blake Marchand There is some uncertainty in the overall market right now, relating to inflation, interest rates, even global events like the war in Ukraine has an impact. These factors will have an impact on the construction industry, which may have an impact on broader opportunities for electrical contractors. Although, anecdotally… Read More…

  • First Retrofit Financed by the Canada Infrastructure Bank Receives IREE Certification

    First Retrofit Financed by the Canada Infrastructure Bank Receives IREE Certification

    January 27, 2023 The Canada Green Building Council (CAGBC) and the Canada Infrastructure Bank (CIB) have announced Dream’s 366 Bay St. redevelopment in Toronto is the first retrofit project financed by the CIB to achieve Investor Ready Energy Efficiency (IREE) certification. IREE certification is part of the CIB’s Building Retrofits Initiative and is administered through… Read More…


Changing Scene

  • Rexel Canada Aquires Lineman’s Testing Labratories of Canada

    Rexel Canada Aquires Lineman’s Testing Labratories of Canada

    Janaury 29, 2023 Rexel Canada aquires Lineman’s Testing Laboratories of Canada Ltd (LTL), a leading provider of high-voltage electrical services and products to the utility and industrial markets based in Toronto, ON and Edmonton, AB. The acquisition, which closed today, will provide Rexel Canada with enhanced opportunities in an attractive and value-added market. The acquisition… Read More…

  • Bartle & Gibson Announces Milwaukee Tool Zones at Three Locations

    Bartle & Gibson Announces Milwaukee Tool Zones at Three Locations

    Janaury 29, 2023 Bartle & Gibson Co. Ltd. announced the addition of three Milwaukee Tool Zones. The Zones include two Milwaukee Tool Red Zones, one at their Calgary North location and one at their Port Coquitlam location, and one Milwaukee Tool Lighting Zone at their Edmonton North location. These Milwaukee Tool Zones are a one-stop… Read More…

  • Electricity Canada and Smart Grid Innovation Network Canada Enter Collaborative Agreement

    Electricity Canada and Smart Grid Innovation Network Canada Enter Collaborative Agreement

    January 27, 2023 Electricity Canada and Smart Grid Innovation Network Canada have entered into a collaborative agreement to share knowledge and create a climate of cooperation that initiates a new direction for both organizations to better serve the professional needs of the members, industry, and community. This agreement will increase collaboration to benefit industry in… Read More…

  • Government of Canada Launches New Intake Model for Zero-Emission Vehicles Infrastructure Funding

    Government of Canada Launches New Intake Model for Zero-Emission Vehicles Infrastructure Funding

    January 27, 2023 The Government of Canada is now accepting applications from not-for-profit organizations, public institutions and governments to locally deliver federal funding from the Zero Emission Vehicle Infrastructure Program (ZEVIP). Applications will be accepted throughout 2023 and 2024. This is yet another step the government is taking to make electric vehicle (EV) charging more accessible for… Read More…