Meeting National Building Code of Canada Requirements

Building Code Requirements

 

Pierre McDonald

For an electrical installation, meeting the minimum code requirements is not achieved simply by following the installation requirements of the Canadian Electrical Code Part 1 (CE Code). While electricians might believe that they are responsible just for that part of the installation that meets the CE Code, it might be shocking (no pun intended) to learn that they must also meet certain requirements of the National Building Code of Canada (NBCC). 

Here’s an example: for residential construction, the vapour barrier is an important part of the NBCC requirements, yet it is the electrician who is charged with installing vapour hats around all exterior wall and ceiling outlets. This is a very small example of requirements outside of the CE Code that should be understood by electrical tradespeople.

The CE Code includes an Appendix G, which is an informative appendix that lists requirements related to installations that are not governed by Rules of the CE Code, but are required by the NBCC. CE Code rules that are referenced to the NBCC will have the words “See Appendix G” in brackets associated with them. These references only cover those rules that are part of the fire protection requirements contained within the NBCC so you will not find the reference to the vapour barrier requirement mentioned above. (FYI, see NBCC 9.25.3 for Air Barrier Systems and 9.25.4 for Vapour Barriers.)

The application of Appendix G is stated as follows. It should be noted that the appendix is based on the 2015 edition CE Code and the 2010 edition NBCC:

• G2.1 – The intent of this Appendix is to advise Canadian Electrical Code, Part I users of performance requirements for electrically connected fire-protective equipment required by the National Building Code of Canada.

• G2.2 – Special fire protection requirements, such as use of thermal insulation, fire spread, flame spread requirements for electrical wiring and cables, flame-spread requirements for combustible raceways, and construction of electrical equipment vaults are covered by this Code (e.g., Rules 2-126, 2-128, 2-130, 2-132, 26-354, etc.).

• G2.3 – Provincial and municipal building codes may deviate from the National Building Code of Canada, and users of this list should also check those codes.

Looking into a few examples as to how this appendix will assist, we can begin with the CE Code Rules 2-128 Fire Spread, 2-130 Flame spread requirements for electrical wiring and cables, and 2-132 Flame spread requirements for totally enclosed non-metallic raceways. All mandate that they meet some requirements within the NBCC. While there are also Appendix B notes to these rules, the Appendix G notes refers the reader to several sections, articles and sentences within the NBCC. For example, Rule 2-128, refers the reader to:

• 3.1.9.1.(1) and (2), Fire stopping of service penetrations through fire-rated assemblies of fire separations

• 3.1.9.3., Penetration of fire-rated assemblies or fire separations by wires, cables, boxes, and raceways

• 3.1.13.4., Flame-spread rating for combustible light diffusers and lenses 

• 9.10.9.6., Electrical wiring and boxes and penetrating a fire separation

Rule 2-130 references:

• 3.1.4.3.(1), Wires and cables in combustible buildings

• 3.1.5.18.(1), Wires and cables in noncombustible buildings

• 3.1.5.18.(2) and (3), Wires and cables within plenums of noncombustible buildings or wiring and cables that extend from plenums

• 3.4.4.4.(1)(b), Restrictions on wiring and raceways penetrating an exit enclosure

• 3.6.4.3.(1), Equipment and wiring within plenums

And Rule 2-132 references

• 3.1.5.20., Combustible raceways in noncombustible buildings

• 3.1.5.20.(2), Combustible raceways within plenums of noncombustible buildings

In a nutshell, these references point the code user to requirements that could affect the installation or at least provide additional information for the installation. Details of these references should be fully investigated and understood by the electrical installer to ensure compliance with the CE Code rules. These references include:

• Fire stop requirements that are subjected to the fire test method in CAN/ULC-S115 – Fire Tests for Fire stop Systems
• Requirements for wiring, cables, conduit, outlet boxes and similar equipment that are allowed to penetrate a fire rated assembly under certain conditions
• Information regarding flame spread ratings of combustible light diffusers and lenses, as well as limits on the installation of these products
• Information regarding the FT rating of wires and cables, including optical fibre cables as well as installation requirements in combustible and non-combustible installations

Section 32 and certain rules within Section 32 also have substantial references in Appendix G to the sections, articles and sentences within the NBCC. This stands to reason as Section 32 “applies to the installation of electrical local fire alarm systems, permanently connected carbon monoxide alarms, and fire pumps required by the National Building Code of Canada.” While the rules in Section 32 cover conductors, wiring methods, equipment bonding, electrical supervision, circuitry and over current devices for power supplies, and smoke alarms and carbon monoxide alarms in residential occupancies, the substantial requirements for installating fire alarm systems exists within the NBCC. It is the NBCC which mandates when a fire alarm system must be installed, zoning and annunciation of fire alarm systems, elevator emergency recall (alternate floor recall for elevators), visual signal devices in a fire alarm system, and the mandatory use of CAN/ULC-S524 – Installation of Fire Alarm Systems as per 3.2.4.5, to mention just a few.

The same holds true regarding the rules for Fire Pumps, 32-200 to 32-212. It is the actual reference within Appendix G to the NBCC sentence 3.2.5.18. that mandates the use of NFPA 20 standard – Installation of Stationary Pumps for Fire Protection.In fact, Section 32 has 53 references to requirements in the NBCC. 

For some electrical installers this might not mean too much, while for others these requirements must be clearly laid out. This informative Appendix G first appeared in the 1998 edition CE Code and has provided references to those installers who must understand these requirements to fulfill contractual obligations. I have simplified the NBCC requirements to illustrate a few of the requirements associated with the NBCC that could affect the electrical Installer. It is clear that not all requirements regarding electrical installations are written in the CE Code and can easily be found. Using all the tools available, including the Appendix G references, will provide those answers.


 

Pierre McDonald, CET, is Senior Regulatory Affairs Representative/Répresentant Principal, Affaires Réglementaires, Underwriters Laboratories of Canada Inc. Based in St. Albert, AB, Pierre has been a member of the Canadian Electrical Code Part 1 technical committee as well as several subcommittees including serving as Chair of Sections 6 and 76 and as a member representing regulators on several other CSA committees. Pierre is still active with code development and interpretation.

Other articles by Pierre McDonald:

2015 CE Code: Changes on “Approved Electrical Equipment” 

Code and Public Safety 

Section 62: Fixed Electric Heating Systems 

Now Available: CAN/ULC Standard on Electric Utility Workplace Electrical Safety

Establishing When the CE Code Becomes Mandatory
 

UL Code Link 

CAN/ULC-S576-14, Standard for Mass Notification System Equipment and Accessories 

Canadian CE Code Changes: Section 20 and More 

Conductor Ampacities and Their Temperature Rating 

Codes and Standards – Provincial Legislation and the Administrative Requirements of the CE Code 

Changes to Section 12 Wiring Methods 

Section 4 Conductors — Changes from the Canadian Electrical Code’s 2009, 21st Edition to the 2012, 22nd Edition 

Related Articles


Latest Articles

  • Code Question on Section 24 – Patient Care Areas

    Code Question on Section 24 – Patient Care Areas

    July 14, 2025 The rules for the installation of panelboards, circuits, and bonding in Patient Care Area depends on whether the area is designated as either, Basic Care, Intermediate Care or Critical Care. How are these areas defined? Read more on Section 24 — Health care areas Read More…

  • Ontario’s Institutional Component Drives Non-Residential Construction Intentions in May 2025

    Ontario’s Institutional Component Drives Non-Residential Construction Intentions in May 2025

    July 14, 2025 In May, the total value of building permits issued in Canada rose by $1.4 billion (+12.0%) to reach $13.1 billion. The increase in construction intentions was driven by Ontario’s institutional component (+$1.3 billion). On a constant dollar basis (2023=100), the total value of building permits issued in May increased 11.8% from the previous month and was… Read More…

  • Plan Group Partners in Construction of UHN Surgical Tower at Toronto Western Hospital

    Plan Group Partners in Construction of UHN Surgical Tower at Toronto Western Hospital

    July 14, 2025 Plan Group is proud to be a partner in the construction of the UHN Surgical Tower at Toronto Western Hospital. Plan Group will provide work on the project in: Mechanical: Plumbing, HVAC, Controls, Medical GasElectrical: Lighting & Controls, Power Distribution, Emergency Generators, UPSTechnology: Structured Cabling, AV Systems including Digital Signage and IPTV UHN’s 15-storey Surgical… Read More…

  • How Canada Can Equip Workers for a Low-Carbon Future

    How Canada Can Equip Workers for a Low-Carbon Future

    July 14, 2025 The Canadian economy is shifting towards low-carbon industries, and the workforce is shifting with it. New roles are emerging, traditional ones are evolving and the demand for skilled workers is growing fast — particularly in light of the ambitious nation-building agenda the federal government has set out. In the federal Speech from… Read More…


Changing Scene

  • OEL Apprentice Success Project Available Until March 2026

    OEL Apprentice Success Project Available Until March 2026

    July 14, 2025 With renewed funding by Ontario’s Skills Development Fund, the OEL Apprentice Success Project is now available for another year until March 2026. The project is part of OEL’s Employer Engagement Program (EEP) consisting of wage, training, and equipment subsidies for apprentices. These funding opportunities are available to OEL Members and non-Members. For… Read More…

  • EB Horsman Unveils New Mural at Campbell River Branch

    EB Horsman Unveils New Mural at Campbell River Branch

    July 14, 2025 EB Horsman & Son are thrilled to unveil a new mural at their Campbell River branch, painted by the talented Kwakwaka’wakw artist, Adam Lewis. “This stunning piece celebrates Indigenous heritage and our community spirit,” said EB Horsman on LinkedIn. “As we mark 125 years of serving Western Canada and 55 years in… Read More…

  • Glenco Electric Celebrate New Red Seal Team Members

    Glenco Electric Celebrate New Red Seal Team Members

    July 14, 2025 “The Red Seal Journeyman designation is the highest recognition in the trades, and we’re proud to have seen so many of our team members earn it under our watch,” said Glenco Electric on LinkedIn. “At Glenco, we’re big on mentorship and promoting from within. When you combine that with driven, hard-working professionals,… Read More…

  • Canada and Ontario Investing to Improve Energy Efficiency in Province’s Agri-Food Industry

    Canada and Ontario Investing to Improve Energy Efficiency in Province’s Agri-Food Industry

    July 14, 2025 The governments of Canada and Ontario are investing up to $3 million and launching the third intake of the Agricultural Stewardship Initiative (ASI) to help farmers implement projects to improve the energy efficiency of their farming operations. To support the province’s plan to protect Ontario, this funding will help local agriculture, agri-food… Read More…