CanGBC Case Study: AMPED Sports Lab & Ice Complex

CanGBC

May 16, 2021

High performance focus earns Ottawa arena its Zero Carbon certification

AMPED Sports Lab and Ice Complex (AMPED) is a recreational and health facility located in Ottawa, Ontario. The facility caters to Canada’s hockey obsessed culture, with facilities designed to help athletes reach their optimum performance.

This focus on high performance goes beyond the athletes AMPED serves to the facility itself. Thanks to an energy overhaul led by Modern Niagara Group Inc., AMPED is the first Zero Carbon Building – Performance certified arena under the Canada Green Building Council’s Zero Carbon Building Standard Program.

Building for life

As a multi-disciplinary contractor, Modern Niagara specializes in mechanical, electrical, building controls and building services. Over the past 20 years, Modern Niagara has focused on analyzing, developing, and implementing energy conservation measures for all types of buildings. As a contractor and CaGBC member, Modern Niagara is conscious of the impact of buildings on carbon emissions – and the role buildings must play in helping Canada meet its climate targets.

The Modern Niagara team saw AMPED as a challenge. Arenas are traditionally one of the most energy intensive buildings – particularly when operating during the warmer summer months. Addressing energy upgrades by transitioning away from fossil fuels to earn Zero Carbon Building – Performance certification gave Modern Niagara the opportunity to push the envelope and set a new standard for these specialized building types.

“Recognizing that every building is unique, the path to a zero carbon building is also unique. If a hockey and sports-dedicated facility in a city where temperatures vary by over 40 degrees can become zero carbon, imagine the possibilities for other buildings across Canada and around the world,” said Brad McAninch, CEO, Modern Niagara Group Inc.

Amped

 

 

 

 

 

 

Moving beyond fossil fuels

The AMPED facility caters to elite athletic training, as well as recovery and treatment of injuries or chronic problems. It houses a physiotherapy clinic, a gym and a 120’ by 65’ ice rink – a perfect size for skills development and custom training for hockey players of all ages.

To earn the ZCB-Performance certification, Modern Niagara took an aggressive path and targeted all mechanical systems that consumed natural gas, and consequently emitted carbon into the atmosphere – including the ice rink dehumidifier, the hot water heater, and the rooftop air handling units.

All fossil fuel consumption related to building energy use was eliminated on-site and converted to electric-based alternatives. To achieve their goal, custom-designed and built rooftop units (RTUs) were manufactured with heat pumps and electric heat backup instead of the traditional direct expansion (DX) coil and gas-fired burner. The ice arena dehumidification system was also retrofitted with a unique, custom-built liquid dessicant air-conditioned unit, equipped with refrigeration DX system reheat. These custom units helped to drastically reduce greenhouse gas (GHG) emissions, while also providing the highest possible efficiency.

To better manage building performance, including the ice-making process, a robust automation and metering system was installed. Used in combination with a real-time analytics software package, it optimizes building and process control and performance, enhances maintenance services, and assists in the continuous commissioning of the facility in order to ensure energy savings persist.

The Chiller system that is used to make ice for the rink also had an energy optimization automation system installed to ensure run times and sequencing are automatically adjusted to drive efficiencies. Heat reclaim from the Ammonia-based chiller was considered however the return on investment was excessive for the low amount of high-temperature heat available.

Lighting systems were retrofitted to high-efficiency LED, and to provide clean electricity a 136 kW solar photovoltaic array was installed.

Amped Solar

 

 

 

 

 

 

 

A first for ice arenas everywhere

Modern Niagara’s approach to sustainability led them to the Zero Carbon Building Standard. As an organization, they saw ZCB-Performance certification as a way to demonstrate the importance of GHG reductions while improving energy efficiency. The project targeted a 20 per cent improvement in energy efficiency and a 70 per cent reduction in carbon emissions. While the approach can lead to slightly higher utility operating cost today, the project was able to reduce exposure to rising carbon prices, and significantly reduce climate impacts—a key factor for the Modern Niagara team.

“Other types of certifications tend to focus only on energy efficiency, but do not adequately capture the cost to the environment,” said McAninch. “The Zero Carbon Building Standard helps us meaningfully contribute to our sustainability goals and reduces our impact on the environment, which is important to our organization and staff. We expect this project will increase tenant satisfaction and provide unique education opportunities around zero carbon buildings.”

Project Owner: AMPED Sports Lab & Ice Complex

LEED / Sustainability Consultant: Modern Niagara Engineering

Mechanical Engineer: Modern Niagara Engineering

Electrical Engineer: Paragon Engineering Services

Commissioning Authority: Modern Niagara Engineering

CaGBC members involved: Modern Niagara

Related Articles


Latest Articles


Changing Scene

  • Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    May 26, 2025 Siemens will invest CAD $150 million over five years to establish a Global AI Manufacturing Technologies Research and Development (R&D) Center for Battery Production in Canada. The new R&D center, located initially at Siemens Canada’s head office in Oakville, as well as in Toronto and Kitchener-Waterloo, Ontario, will focus on developing cutting-edge AI manufacturing technologies with an initial emphasis… Read More…

  • Honda Postponing Ontario EV Supply Chain Investment by Two Years

    Honda Postponing Ontario EV Supply Chain Investment by Two Years

    May 26, 2025 Honda is postponing its plan to invest in a comprehensive EV supply chain in Ontario. The CBC reported that the investment is being push back by two years. “Due to the recent slowdown of the EV market, Honda Motor has announced an approximate two-year postponement of the comprehensive value chain investment project in Canada…. Read More…

  • Serge Leblanc Named Sonepar Canada Interim President

    Serge Leblanc Named Sonepar Canada Interim President

    May 26, 2025 George McClean, former President of Sonepar Canada, has decided to leave Sonepar for an opportunity outside of the electrical industry. Serge Leblanc, current President of Lumen Canada, has been appointed interim President of Sonepar Canada. Leblanc will manage both responsibilities until a successor is named.  Leblanc joined Lumen in 1997 and has… Read More…

  • Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    May 26, 2025 On Monday, May 26, the Ontario Building and Construction Tradeswomen (OBCT), will host its first-ever Advocacy Day at Queen’s Park. Tradeswomen from across the province will gather to meet with Members of Provincial Parliament, including Minister of Labour David Piccini, to advocate for progress in the skilled trades for tradeswomen. OBCT’s top priorities include:… Read More…