Temporary Generators Installed at Pukatawagan

EIN Manitoba Hydro Logo

August 19, 2022

After just over a month of planning, transportation, and installation work, Manitoba Hydro energized two large industrial generators to bring power back to the community of Pukatawagan. This will allow residents to return home while the utility works to replace 77 fire-damaged poles on the power line feeding the community.

“A lot of people worked really hard to make this happen,” said Cyril Patterson, Manitoba Hydro’s Director of Rural Operations. “There’s lots left to do out there, but we’re happy community members can go home while we finish the job.”

The wildfire that threatened Pukatawagan (also known as Mathias Colomb Cree Nation), forced the evacuation of approximately 2,000 residents and damaged the power line feeding it, but left the rail line into the community intact. This allowed Manitoba Hydro to ship in two large generators to temporarily restore power. The two 1,500 kW generators, which are far too large to be flown in, are being continuously monitored and refueled while crews work to repair Pukatawagan’s normal power supply.

“Being in our Treaty Six territory is the comfort of home…we feel settled,” said Lorna Bighetty, Mathias Colomb Cree Nation Chief.

“Installing the generators means that essential services — such as health, water and sewer, service to our homes, access to the outside world through internet services and other media — are available again. We will rest at night and rise in the morning knowing that our families are safe.”

To complete repairs, crews will get to work setting poles in and around steep cliffs, marsh, and rock — a difficult task complicated by access issues. Many of the materials required to restore power, including poles, spools of power lines, insulators, guy wires, specialized vehicles, transformers, fuel, etc., arrived in the community on the same train as the generators. The train was 27 cars long.

“There are, literally, a lot of moving parts here,” Patterson said. “The generators came via rail from Alberta into The Pas, where we attached more cars to that train with additional materials and fuel. Once it all got to Pukatawagan, we installed environmental protection around the generator sites, then unloaded, fueled, and installed the generators so people could come home. Now we’ll use helicopters to fly equipment and crews to the fire-damaged areas and fix those lines.”

Manitoba Hydro continues to provide regular updates to the leadership of Mathias Colomb Cree Nation as well as other agencies such as Indigenous Services Canada, Manitoba Wildfire Service, and the Canadian Red Cross. The generators will be in place until repairs to the power line are completed.

Source

Related Articles


Latest Articles


Changing Scene

  • BC Hydro Making it Easier and More Affordable to Connect New Homes

    BC Hydro Making it Easier and More Affordable to Connect New Homes

    July 24, 2025 BC Hydro is supporting the construction of new housing developments in growing communities by advancing changes to streamline upgrades and reducing the cost of new customer connections to BC Hydro’s electricity grid. “As communities across B.C. grow, so does the need for essential housing. We are committed to ensuring we’re ready to… Read More…

  • Mitrex Sets Record with Largest BIPV Solar Panel Mural at SunRise Residential in Edmonton

    Mitrex Sets Record with Largest BIPV Solar Panel Mural at SunRise Residential in Edmonton

    July 22, 2025 Building-Integrated Photovoltaics (BIPV) manufacturer, Mitrex proudly announces that its transformative SunRise Residential project in Edmonton, Alberta, has earned the Guinness World Record for the largest solar panel mural globally. This landmark project showcases Mitrex’s innovative BIPV solar panels, blending cutting-edge solar technology with vibrant cultural artistry to redefine sustainable architecture. Sustainable Architecture with BIPV Spanning over 30,000 square feet, the Mitrex eFacade PRO plus… Read More…

  • Nexans Unveils a Cable Made with 100% Recycled Materials

    Nexans Unveils a Cable Made with 100% Recycled Materials

    July 24, 2025 Nexans has reached a major milestone in its sustainability journey by developing a prototype cable made entirely from recycled materials — a first in the company’s history. This innovation combines technical performance, industrial feasibility, and a drastically reduced environmental footprint, marking a decisive step forward in circular economy. A cross-continental success story… Read More…

  • EFC Welcomes New Manufacturer Member: MGM Transformers

    EFC Welcomes New Manufacturer Member: MGM Transformers

    July 24, 2025 Since 1974, MGM Transformers has produced tough and trusted transformers designed to get the job done right. As a leading manufacturer, the company employs a highly experienced and dedicated engineering team that excels in custom designs. MGM Transformers is committed to excellent quality and service, offering industry-leading lead times and exceptional customer service. MGM Transformers specializes… Read More…