Temporary Generators Installed at Pukatawagan

EIN Manitoba Hydro Logo

August 19, 2022

After just over a month of planning, transportation, and installation work, Manitoba Hydro energized two large industrial generators to bring power back to the community of Pukatawagan. This will allow residents to return home while the utility works to replace 77 fire-damaged poles on the power line feeding the community.

“A lot of people worked really hard to make this happen,” said Cyril Patterson, Manitoba Hydro’s Director of Rural Operations. “There’s lots left to do out there, but we’re happy community members can go home while we finish the job.”

The wildfire that threatened Pukatawagan (also known as Mathias Colomb Cree Nation), forced the evacuation of approximately 2,000 residents and damaged the power line feeding it, but left the rail line into the community intact. This allowed Manitoba Hydro to ship in two large generators to temporarily restore power. The two 1,500 kW generators, which are far too large to be flown in, are being continuously monitored and refueled while crews work to repair Pukatawagan’s normal power supply.

“Being in our Treaty Six territory is the comfort of home…we feel settled,” said Lorna Bighetty, Mathias Colomb Cree Nation Chief.

“Installing the generators means that essential services — such as health, water and sewer, service to our homes, access to the outside world through internet services and other media — are available again. We will rest at night and rise in the morning knowing that our families are safe.”

To complete repairs, crews will get to work setting poles in and around steep cliffs, marsh, and rock — a difficult task complicated by access issues. Many of the materials required to restore power, including poles, spools of power lines, insulators, guy wires, specialized vehicles, transformers, fuel, etc., arrived in the community on the same train as the generators. The train was 27 cars long.

“There are, literally, a lot of moving parts here,” Patterson said. “The generators came via rail from Alberta into The Pas, where we attached more cars to that train with additional materials and fuel. Once it all got to Pukatawagan, we installed environmental protection around the generator sites, then unloaded, fueled, and installed the generators so people could come home. Now we’ll use helicopters to fly equipment and crews to the fire-damaged areas and fix those lines.”

Manitoba Hydro continues to provide regular updates to the leadership of Mathias Colomb Cree Nation as well as other agencies such as Indigenous Services Canada, Manitoba Wildfire Service, and the Canadian Red Cross. The generators will be in place until repairs to the power line are completed.

Source

Related Articles


Latest Articles


Changing Scene

  • Delta Transformers Appoints New Representative in Ontario

    Delta Transformers Appoints New Representative in Ontario

    October 8, 2026 Delta Transformers, a Canadian manufacturer of dry-type transformers, is pleased to announce the appointment of Spectrum Power Systems as their new representative in Ontario, Canada, effective October 1st, 2026. For over 27 years Spectrum Power Systems has been representing leading electrical manufacturers throughout Ontario. The company has a strong presence in the… Read More…

  • Former Electrical Contractor Principal Arrested Following ESA Referral to Police

    Former Electrical Contractor Principal Arrested Following ESA Referral to Police

    October 8, 2026 Arrest follows ESA licence revocation, $70,000 in previous fines and new electrical safety charges   Peel Regional Police recently arrested Rahyl Hassan, principal of former Licensed Electrical Contractor, Strak Holdings Inc., following an investigation in which the Electrical Safety Authority (ESA) cooperated with police.  ESA referred concerns about potential criminal activity to Peel… Read More…

  • Federal Government Announces $2 billion Investment to Deliver One Million Home Retrofits Across Canada

    Federal Government Announces $2 billion Investment to Deliver One Million Home Retrofits Across Canada

    October 8, 2026 The federal government has announced a $2 billion investment to deliver one million home retrofits across Canada. These energy-efficient retrofits will lower heating costs for Canadians and reduce emissions. First, they are launching a new National Heat Pump Rebate to help up to 820,000 households make the switch to more efficient electric heat pumps: Heat pumps… Read More…

  • FCM and the Government of Canada Announce $66.3 M in 162 Energy Efficient Housing Projects

    FCM and the Government of Canada Announce $66.3 M in 162 Energy Efficient Housing Projects

    September 8, 2026 Funding supports homeowners and affordable housing providers in reducing energy costs and improving quality of life, while adding jobs to communities coast-to-coast  The Government of Canada and the Federation of Canadian Municipalities (FCM) today announced that $66.3 million in funding has been approved for 162 energy efficiency projects across the country. The… Read More…