Temporary Generators Installed at Pukatawagan

EIN Manitoba Hydro Logo

August 19, 2022

After just over a month of planning, transportation, and installation work, Manitoba Hydro energized two large industrial generators to bring power back to the community of Pukatawagan. This will allow residents to return home while the utility works to replace 77 fire-damaged poles on the power line feeding the community.

“A lot of people worked really hard to make this happen,” said Cyril Patterson, Manitoba Hydro’s Director of Rural Operations. “There’s lots left to do out there, but we’re happy community members can go home while we finish the job.”

The wildfire that threatened Pukatawagan (also known as Mathias Colomb Cree Nation), forced the evacuation of approximately 2,000 residents and damaged the power line feeding it, but left the rail line into the community intact. This allowed Manitoba Hydro to ship in two large generators to temporarily restore power. The two 1,500 kW generators, which are far too large to be flown in, are being continuously monitored and refueled while crews work to repair Pukatawagan’s normal power supply.

“Being in our Treaty Six territory is the comfort of home…we feel settled,” said Lorna Bighetty, Mathias Colomb Cree Nation Chief.

“Installing the generators means that essential services — such as health, water and sewer, service to our homes, access to the outside world through internet services and other media — are available again. We will rest at night and rise in the morning knowing that our families are safe.”

To complete repairs, crews will get to work setting poles in and around steep cliffs, marsh, and rock — a difficult task complicated by access issues. Many of the materials required to restore power, including poles, spools of power lines, insulators, guy wires, specialized vehicles, transformers, fuel, etc., arrived in the community on the same train as the generators. The train was 27 cars long.

“There are, literally, a lot of moving parts here,” Patterson said. “The generators came via rail from Alberta into The Pas, where we attached more cars to that train with additional materials and fuel. Once it all got to Pukatawagan, we installed environmental protection around the generator sites, then unloaded, fueled, and installed the generators so people could come home. Now we’ll use helicopters to fly equipment and crews to the fire-damaged areas and fix those lines.”

Manitoba Hydro continues to provide regular updates to the leadership of Mathias Colomb Cree Nation as well as other agencies such as Indigenous Services Canada, Manitoba Wildfire Service, and the Canadian Red Cross. The generators will be in place until repairs to the power line are completed.

Source

Related Articles


Latest Articles


Changing Scene

  • CAF-FCA Welcomes Federal Apprenticeship Investments, Urges Focus on Implementation

    CAF-FCA Welcomes Federal Apprenticeship Investments, Urges Focus on Implementation

    May 1, 2026 CAF-FCA welcomes the federal government’s strong focus on skilled trades in the 2026 Spring Economic Update, including new investments in apprenticeship pathways, financial supports, and employer incentives. These measures reflect long standing priorities advanced by employers and partners across the country. The Canadian Apprenticeship Forum (CAF-FCA) welcomes the Government of Canada’s renewed Read More…

  • ECABC Announces 2026 Hall of Fame Inductees

    ECABC Announces 2026 Hall of Fame Inductees

    April 30, 2026 ECABC is proud to announce that Bill Strain and Rob Tate will be inducted into the ECABC Electrical Hall of Fame this June. Bill and Rob have devoted their careers to the electrical contracting industry in British Columbia. Induction into the Electrical Hall of Fame is the highest honour the Association can Read More…

  • Nexans Initiates Copper Mark Recertification for Montreal Site

    Nexans Initiates Copper Mark Recertification for Montreal Site

    April 27, 2026 Nexans Canada Inc. has initiated the Copper Mark recertification process for its site located at 460 Durocher Avenue in Montreal. As part of this process, an independent external assessment of the site is scheduled for April 22–24, 2026. Copper Mark is an independent assurance framework designed to assess the responsible practices of industrial sites against recognized Read More…

  • Fort Frances Memorial Sports Centre Adding Solar as Part of GICB Program

    Fort Frances Memorial Sports Centre Adding Solar as Part of GICB Program

    April 27, 2026 The Fort Frances Memorial Sports Centre will generate solar energy following an investment of $589,762 from the federal government through the Green and Inclusive Community Buildings (GICB) program. This funding will reduce greenhouse gas emissions and annual electricity costs for the facility. A rooftop solar generation system will convert solar energy into Read More…