Temporary Generators Installed at Pukatawagan

EIN Manitoba Hydro Logo

August 19, 2022

After just over a month of planning, transportation, and installation work, Manitoba Hydro energized two large industrial generators to bring power back to the community of Pukatawagan. This will allow residents to return home while the utility works to replace 77 fire-damaged poles on the power line feeding the community.

“A lot of people worked really hard to make this happen,” said Cyril Patterson, Manitoba Hydro’s Director of Rural Operations. “There’s lots left to do out there, but we’re happy community members can go home while we finish the job.”

The wildfire that threatened Pukatawagan (also known as Mathias Colomb Cree Nation), forced the evacuation of approximately 2,000 residents and damaged the power line feeding it, but left the rail line into the community intact. This allowed Manitoba Hydro to ship in two large generators to temporarily restore power. The two 1,500 kW generators, which are far too large to be flown in, are being continuously monitored and refueled while crews work to repair Pukatawagan’s normal power supply.

“Being in our Treaty Six territory is the comfort of home…we feel settled,” said Lorna Bighetty, Mathias Colomb Cree Nation Chief.

“Installing the generators means that essential services — such as health, water and sewer, service to our homes, access to the outside world through internet services and other media — are available again. We will rest at night and rise in the morning knowing that our families are safe.”

To complete repairs, crews will get to work setting poles in and around steep cliffs, marsh, and rock — a difficult task complicated by access issues. Many of the materials required to restore power, including poles, spools of power lines, insulators, guy wires, specialized vehicles, transformers, fuel, etc., arrived in the community on the same train as the generators. The train was 27 cars long.

“There are, literally, a lot of moving parts here,” Patterson said. “The generators came via rail from Alberta into The Pas, where we attached more cars to that train with additional materials and fuel. Once it all got to Pukatawagan, we installed environmental protection around the generator sites, then unloaded, fueled, and installed the generators so people could come home. Now we’ll use helicopters to fly equipment and crews to the fire-damaged areas and fix those lines.”

Manitoba Hydro continues to provide regular updates to the leadership of Mathias Colomb Cree Nation as well as other agencies such as Indigenous Services Canada, Manitoba Wildfire Service, and the Canadian Red Cross. The generators will be in place until repairs to the power line are completed.

Source

Related Articles


Latest Articles


Changing Scene

  • Cascadia Sales Representing Eaton in BC

    Cascadia Sales Representing Eaton in BC

    May 21, 2026 Cascadia Sales are thrilled to announce that effective May 11, 2026, they will officially be representing an expanded portfolio of Eaton brands across British Columbia. “Adding Crouse-Hinds, B-Line, Bussmann, and Cooper Power series to our lineup allows us to provide even more comprehensive electrical solutions to our BC partners,” the company said Read More…

  • Nedco Opens New Kelowna Branch

    Nedco Opens New Kelowna Branch

    May 21, 2026 In a recent announcement from Nedco, the company celebrated the Grand Opening of the new Kelowna branch on Friday, May 8, 2026. Nedco invited attendees to explore the new 11,000 sq. ft. facility designed to conveniently serve Okanagan customers. The tour of the new facility took place from 11:00 AM to 2:00 Read More…

  • Leviton Canada Partners with NRG INTENSI‑T Inc. to Strengthen the Presence of Lighting Controls in the Quebec Region

    Leviton Canada Partners with NRG INTENSI‑T Inc. to Strengthen the Presence of Lighting Controls in the Quebec Region

    May 21, 2026 Leviton Canada is proud to announce its partnership with NRG INTENSI-T Inc., who will now represent Leviton’s Lighting Controls product line throughout the Quebec region, effective May 1, 2026. This new partnership reflects Leviton’s commitment to strengthening its lighting controls presence in Quebec through experienced, market-focused representation. With deep regional knowledge, an Read More…

  • Mac’s II Agencies Expands ABB Partnership into UPS Solutions

    Mac’s II Agencies Expands ABB Partnership into UPS Solutions

    May 21, 2026 As demand increases for resilient, always-on power for commercial, industrial, and mission-critical environments, Mac’s II Agencies is strengthening its Power Quality portfolio with ABB systems engineered for diverse conditions. With a broad range of sizes and configurations available, engineers, contractors, and end users can specify power backup and protection solutions with continued confidence, backed Read More…