Nova Scotia Power to Install High Voltage Electrical Lines on New Tower Across Straight of Canso

Nova Scotia Power

December 14, 2017

Nova Scotia Power is in the final construction phase of a project that will see six new transmission towers carrying high voltage electrical lines across the Strait of Canso, which will improve service reliability by providing an important back-up power connection between Cape Breton and the mainland.

“As area residents will know, we’ve been building new transmission towers across the Strait of Canso since February, with site clearing and tower construction now complete,” said Tom Flewwelling, Senior Project Engineer with Nova Scotia Power. “One of the final pieces of work is to install high voltage electrical lines on the new towers that will create two separate circuits across the Strait. This separation will establish an alternative power connection between Cape Breton and mainland Nova Scotia, improving service reliability for our customers in the event of a significant outage.”

Installing the electrical lines on the six new transmission towers requires a significant coordinated effort by a number of personnel and different types of equipment to pull and tension the lines to the appropriate height across water, land, a railway and roadways. As always, safety is our top priority and the daily work schedule is weather dependent. Navigational lights that were on the older towers are also in the process of being moved to the new, higher towers.

In order to safely allow the electrical line installation across the Strait, marine traffic may be restricted and delays should be expected in the area of Georges Bay and the Canso Causeway locks. Vessels intending to travel through this area should contact the onsite standby vessel or the Canso Lock, and proceed with caution through the area.

“We really appreciate the community’s patience as we’ve progressed from pouring concrete pads earlier this year to the more recent and very visible tower assembly,” said Flewwelling. “Building the tallest transmission towers in Atlantic Canada is no small feat, and we are proud to be working with a number of very skilled and safety-oriented local contractors and businesses to complete this important reliability project for Nova Scotians.”

The new Strait of Canso transmission towers will also support the addition of renewable energy from Newfoundland and Labrador through the Maritime Link, which will enable Nova Scotia Power to achieve a requirement to generate electricity from 40 per cent renewable energy in 2020. In 2016, 28 per cent of Nova Scotia’s electricity came from renewable sources, including eight per cent from hydro and tidal generation.

https://www.nspower.ca/en/home/newsroom/news-releases/nova-scotia-power-set-to-install-high-voltage-elec.aspx

Related Articles


Latest Articles

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    February 6, 2026 The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual Read More…

  • 3D Printing: Inside Lighting’s Next Revolution

    February 5, 2026 While 3D printing in mass production was once a dream, advancements in the technology have moved it more into the mainstream. The technique, which is also referred to as additive manufacturing, has rapidly evolved from a niche prototyping tool into a transformative production method for many sectors, including the lighting industry. As Read More…

  • Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    February 5, 2026 In an era of extreme weather, aging infrastructure, and ever‑rising energy demands, many facility managers are rethinking their relationship with the grid. Microgrids offer a way to take control and operate autonomously when necessary. A microgrid is more than just backup, when designed properly, it becomes a platform for resiliency, efficiency, and Read More…

  • ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    February 5, 2026 Understanding NEMA Ratings for Electrical Enclosures NEMA Ratings are an essential classification system used across North America to define the environmental and mechanical protection provided by electrical enclosures. Developed by the National Electrical Manufacturers Association (NEMA), these ratings help engineers, installers, and specifiers identify the appropriate enclosure type for industrial, commercial, and outdoor Read More…


Changing Scene

  • Lighting What’s Next: Stanpro Celebrates 65 Years

    Lighting What’s Next: Stanpro Celebrates 65 Years

    February 6, 2026 “We didn’t get here by standing still. For 65 years, we’ve shaped how we think, how we design, and what responsibility means,” the company said in a LinkedIn post. “Today, that thinking takes a new form. Not to change who we are, but to express our evolution more clearly. This is Stanpro, Read More…

  • Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    February 6, 2026 Efforts to support the creation of new affordable housing and reduce chronic homelessness are on track, but there is still lots of work to do, according to David Hickey, the minister responsible for the New Brunswick Housing Corporation. New data indicates progress has been made on three key government priorities related to Read More…

  • BJ Electric is now Bernie’s Electric Supplies Ltd

    BJ Electric is now Bernie’s Electric Supplies Ltd

    February 6, 2026 BJ Electric has announced the company has rebranded as Bernie’s Electric Supplies Ltd, a nod to their founder. “BJ Electric Supplies is now Bernie’s Electric Supplies—in honor of our founder, Bernard Joseph Thompson, and the values that have guided the company for nearly 50 years. As we grow and evolve, this name Read More…

  • The Government of Canada Introduces the Build Canada Homes Act

    The Government of Canada Introduces the Build Canada Homes Act

    February 6, 2026 The Government of Canada has introduced the Build Canada Homes Act, legislation that will establish Build Canada Homes as a Crown corporation whose mandate will be dedicated to building affordable housing in communities across the country. As Canada’s affordable housing builder, this legislation will equip Build Canada Homes with the necessary tools to Read More…