Nova Scotia Power to Install High Voltage Electrical Lines on New Tower Across Straight of Canso

Nova Scotia Power

December 14, 2017

Nova Scotia Power is in the final construction phase of a project that will see six new transmission towers carrying high voltage electrical lines across the Strait of Canso, which will improve service reliability by providing an important back-up power connection between Cape Breton and the mainland.

“As area residents will know, we’ve been building new transmission towers across the Strait of Canso since February, with site clearing and tower construction now complete,” said Tom Flewwelling, Senior Project Engineer with Nova Scotia Power. “One of the final pieces of work is to install high voltage electrical lines on the new towers that will create two separate circuits across the Strait. This separation will establish an alternative power connection between Cape Breton and mainland Nova Scotia, improving service reliability for our customers in the event of a significant outage.”

Installing the electrical lines on the six new transmission towers requires a significant coordinated effort by a number of personnel and different types of equipment to pull and tension the lines to the appropriate height across water, land, a railway and roadways. As always, safety is our top priority and the daily work schedule is weather dependent. Navigational lights that were on the older towers are also in the process of being moved to the new, higher towers.

In order to safely allow the electrical line installation across the Strait, marine traffic may be restricted and delays should be expected in the area of Georges Bay and the Canso Causeway locks. Vessels intending to travel through this area should contact the onsite standby vessel or the Canso Lock, and proceed with caution through the area.

“We really appreciate the community’s patience as we’ve progressed from pouring concrete pads earlier this year to the more recent and very visible tower assembly,” said Flewwelling. “Building the tallest transmission towers in Atlantic Canada is no small feat, and we are proud to be working with a number of very skilled and safety-oriented local contractors and businesses to complete this important reliability project for Nova Scotians.”

The new Strait of Canso transmission towers will also support the addition of renewable energy from Newfoundland and Labrador through the Maritime Link, which will enable Nova Scotia Power to achieve a requirement to generate electricity from 40 per cent renewable energy in 2020. In 2016, 28 per cent of Nova Scotia’s electricity came from renewable sources, including eight per cent from hydro and tidal generation.

https://www.nspower.ca/en/home/newsroom/news-releases/nova-scotia-power-set-to-install-high-voltage-elec.aspx

Related Articles


Latest Articles


Changing Scene

  • CAF-FCA Welcomes Federal Apprenticeship Investments, Urges Focus on Implementation

    CAF-FCA Welcomes Federal Apprenticeship Investments, Urges Focus on Implementation

    May 1, 2026 CAF-FCA welcomes the federal government’s strong focus on skilled trades in the 2026 Spring Economic Update, including new investments in apprenticeship pathways, financial supports, and employer incentives. These measures reflect long standing priorities advanced by employers and partners across the country. The Canadian Apprenticeship Forum (CAF-FCA) welcomes the Government of Canada’s renewed Read More…

  • ECABC Announces 2026 Hall of Fame Inductees

    ECABC Announces 2026 Hall of Fame Inductees

    April 30, 2026 ECABC is proud to announce that Bill Strain and Rob Tate will be inducted into the ECABC Electrical Hall of Fame this June. Bill and Rob have devoted their careers to the electrical contracting industry in British Columbia. Induction into the Electrical Hall of Fame is the highest honour the Association can Read More…

  • Nexans Initiates Copper Mark Recertification for Montreal Site

    Nexans Initiates Copper Mark Recertification for Montreal Site

    April 27, 2026 Nexans Canada Inc. has initiated the Copper Mark recertification process for its site located at 460 Durocher Avenue in Montreal. As part of this process, an independent external assessment of the site is scheduled for April 22–24, 2026. Copper Mark is an independent assurance framework designed to assess the responsible practices of industrial sites against recognized Read More…

  • Fort Frances Memorial Sports Centre Adding Solar as Part of GICB Program

    Fort Frances Memorial Sports Centre Adding Solar as Part of GICB Program

    April 27, 2026 The Fort Frances Memorial Sports Centre will generate solar energy following an investment of $589,762 from the federal government through the Green and Inclusive Community Buildings (GICB) program. This funding will reduce greenhouse gas emissions and annual electricity costs for the facility. A rooftop solar generation system will convert solar energy into Read More…