Nova Scotia Power to Install High Voltage Electrical Lines on New Tower Across Straight of Canso

Nova Scotia Power

December 14, 2017

Nova Scotia Power is in the final construction phase of a project that will see six new transmission towers carrying high voltage electrical lines across the Strait of Canso, which will improve service reliability by providing an important back-up power connection between Cape Breton and the mainland.

“As area residents will know, we’ve been building new transmission towers across the Strait of Canso since February, with site clearing and tower construction now complete,” said Tom Flewwelling, Senior Project Engineer with Nova Scotia Power. “One of the final pieces of work is to install high voltage electrical lines on the new towers that will create two separate circuits across the Strait. This separation will establish an alternative power connection between Cape Breton and mainland Nova Scotia, improving service reliability for our customers in the event of a significant outage.”

Installing the electrical lines on the six new transmission towers requires a significant coordinated effort by a number of personnel and different types of equipment to pull and tension the lines to the appropriate height across water, land, a railway and roadways. As always, safety is our top priority and the daily work schedule is weather dependent. Navigational lights that were on the older towers are also in the process of being moved to the new, higher towers.

In order to safely allow the electrical line installation across the Strait, marine traffic may be restricted and delays should be expected in the area of Georges Bay and the Canso Causeway locks. Vessels intending to travel through this area should contact the onsite standby vessel or the Canso Lock, and proceed with caution through the area.

“We really appreciate the community’s patience as we’ve progressed from pouring concrete pads earlier this year to the more recent and very visible tower assembly,” said Flewwelling. “Building the tallest transmission towers in Atlantic Canada is no small feat, and we are proud to be working with a number of very skilled and safety-oriented local contractors and businesses to complete this important reliability project for Nova Scotians.”

The new Strait of Canso transmission towers will also support the addition of renewable energy from Newfoundland and Labrador through the Maritime Link, which will enable Nova Scotia Power to achieve a requirement to generate electricity from 40 per cent renewable energy in 2020. In 2016, 28 per cent of Nova Scotia’s electricity came from renewable sources, including eight per cent from hydro and tidal generation.

https://www.nspower.ca/en/home/newsroom/news-releases/nova-scotia-power-set-to-install-high-voltage-elec.aspx

Related Articles


Latest Articles

  • Mastering Advanced Bidding Strategies in Electrical Contracting

    Mastering Advanced Bidding Strategies in Electrical Contracting

    December 1, 2025 By Melvin Newman, Patabid CEO & Ian Paterson, Patabid Client Success Manager and journeyman electrician with 30+ years of experience In the competitive world of electrical contracting, knowing how to estimate electrical jobs effectively can make the difference between winning profitable projects and watching opportunities slip away. For electrical contractors, mastering advanced… Read More…

  • Why Choosing the Right USB Charger Matters

    Why Choosing the Right USB Charger Matters

    December 1, 2025 Not all USB Chargers are Created Equal As the number of devices used daily increases, so does the need for a charger that delivers safe speeds and maximum charging potential. A high-quality USB charger delivers efficient charging without risk of damage, but the sea of USB chargers and outlets available on online… Read More…

  • How Homebuilding Incentives Can Pay Off for Cities, Homeowners and Local Economies: New Concordia Study

    December 1, 2025 A new study from Concordia University’s John Molson School of Business finds that improving housing affordability isn’t just a social good — it’s an economic growth opportunity. Build and Benefit: How Homebuilding Incentives Can Pay Off for Cities, Homeowners and Local Economies reframes housing policy reform as a sustainable fiscal growth strategy, demonstrating meaningful… Read More…

  • The Importance of HazLoc LED Lighting for Safe Workplaces

    The Importance of HazLoc LED Lighting for Safe Workplaces

    November 30, 2025 By CSC LED In Canada’s industrial lighting sector, one of the most critical yet often overlooked safety components is lighting designed specifically for hazardous locations, otherwise known as HazLoc (hazardous location) LED lighting. For workplaces dealing with flammable gases, vapours, combustible dust, or ignitable fibres, standard LED fixtures simply don’t cut it…. Read More…


Changing Scene

  • Skills Ontario Celebrates the Expansion of Trades & Tech Truck Program

    Skills Ontario Celebrates the Expansion of Trades & Tech Truck Program

    December 1, 2025 Skills Ontario is expanding its fleet of Trades & Tech mobile unit thanks to support from the Ontario Government. The government announced this morning it’s investment in Skills Ontario to expand experiential opportunities for Ontario’s future workforce.    “Ontario’s future relies on a strong, skilled workforce,” said David Piccini, Minister of Labour, Immigration,… Read More…

  • BC’s Canadian Mutual Recognition Agreement aims to Facilitate Interprovincial Trade

    BC’s Canadian Mutual Recognition Agreement aims to Facilitate Interprovincial Trade

    December 1, 2025 A new agreement signed by all provinces, territories, and the federal government will break down interprovincial trade barriers, making it easier for B.C. businesses to sell products across Canada, and for people to buy Canadian-made goods.   “When threats to Canada’s economic security land at our doorstep, we’re at our best when we work together as… Read More…

  • EB Horsman’s Commitment to Giving Back – A Year in Recap 2024/2025

    EB Horsman’s Commitment to Giving Back – A Year in Recap 2024/2025

    December 1, 2025 EB Horsman Cares is the company’s community engagement program that supports local children’s hospitals, communities, and non-profit initiatives with donations, fundraising, volunteering, and scholarships.  Since 1993, BC Children’s Hospital has been the primary recipient of EB Horsman & Son’s fundraising. However, as EB Horsman has continued to expand its businesses across Western… Read More…

  • Build Canada Homes Introduces Policy Framework to Guide its Investments in Affordable Housing

    Build Canada Homes Introduces Policy Framework to Guide its Investments in Affordable Housing

    December 1, 2025 Central to that work, the Government of Canada is stepping up with the recently launched Build Canada Homes, new federal agency with a mandate to scale up the supply of affordable housing across Canada. Build Canada Homes will also help fight homelessness by building transitional and supportive housing – working with provinces,… Read More…