Pattern Development and Henvey Inlet First Nation Start Construction of Largest First Nation Wind Project in Canada

Pattern Development

January 12, 2018

Pattern Energy Group LP announced the completion of a C$1 billion financing for the 300 megawatt (MW) Henvey Inlet Wind project located on Henvey Inlet First Nation Reserve No. 2 on the northeast shore of the Georgian Bay in Ontario. Pattern Development and Nigig Power Corporation, a wholly-owned subsidiary of Henvey Inlet First Nation, are joint venture partners in the project.

“This landmark project is a first on many fronts: largest wind project in Ontario, largest on-reserve wind installation in Canada, highest hub heights in North America, and the first to develop a First Nation Environmental Stewardship Regime under the First Nations Lands Management Act,” said Mike Garland, CEO of Pattern Development. “We are proud to be partners with Henvey Inlet First Nation. Together we’re excited to kick off construction on this historic project that will harness the strong and steady winds blowing across the Georgian Bay to create hundreds of local jobs and provide a significant new source of revenue for Henvey Inlet First Nation.”

“This will be the first wind power project on First Nation land, representing an economic turning point in which we are creating a prosperous future,” said Chief Wayne McQuabbie of Henvey Inlet First Nation. “This project’s watershed permitting and real estate regime sets an example for responsible economic development that protects and preserves First Nation land while also generating revenue for future generations. The project also benefits Magnetawan and Shawanaga First Nations with income and employment opportunities.”

“We aren’t just building a wind farm, we’re building an economy,” said Ken Noble, President and CEO, Nigig Power Corporation. “The net proceeds over the next two decades of operations will provide the financial resources to transform the local economy, expand all community services, relieve poverty, and create employment.” 

Henvey Inlet Wind will utilize 87 Vestas 3.45 MW turbines with a 136-meter rotor diameter and 132-meter hub height. The project has a 20-year Power Purchase Agreement with the Independent Electricity System Operator (IESO) for 100% of its production.

The project will create up to 500 jobs during construction. Once operational the project will employ approximately 15 permanent full-time workers and also create the need for more than 100 ongoing indirect jobs.

Once operational in the first half of 2019, Henvey Inlet Wind will generate clean power for approximately 100,000 Ontario homes each year. It is expected to generate lease royalties of more than C$8 million annually for the Henvey Inlet First Nation, in addition to significant income from project distributions.  

Henvey Inlet Wind is being jointly developed and will continue to be jointly owned and operated by Pattern Development and Henvey Inlet First Nation. Pattern Development owns a 50% interest in the project, and Nigig Power Corporation owns the other 50% of the project.

Related Articles


Latest Articles

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    February 6, 2026 The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual Read More…

  • 3D Printing: Inside Lighting’s Next Revolution

    February 5, 2026 While 3D printing in mass production was once a dream, advancements in the technology have moved it more into the mainstream. The technique, which is also referred to as additive manufacturing, has rapidly evolved from a niche prototyping tool into a transformative production method for many sectors, including the lighting industry. As Read More…

  • Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    February 5, 2026 In an era of extreme weather, aging infrastructure, and ever‑rising energy demands, many facility managers are rethinking their relationship with the grid. Microgrids offer a way to take control and operate autonomously when necessary. A microgrid is more than just backup, when designed properly, it becomes a platform for resiliency, efficiency, and Read More…

  • ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    February 5, 2026 Understanding NEMA Ratings for Electrical Enclosures NEMA Ratings are an essential classification system used across North America to define the environmental and mechanical protection provided by electrical enclosures. Developed by the National Electrical Manufacturers Association (NEMA), these ratings help engineers, installers, and specifiers identify the appropriate enclosure type for industrial, commercial, and outdoor Read More…


Changing Scene

  • Lighting What’s Next: Stanpro Celebrates 65 Years

    Lighting What’s Next: Stanpro Celebrates 65 Years

    February 6, 2026 “We didn’t get here by standing still. For 65 years, we’ve shaped how we think, how we design, and what responsibility means,” the company said in a LinkedIn post. “Today, that thinking takes a new form. Not to change who we are, but to express our evolution more clearly. This is Stanpro, Read More…

  • Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    February 6, 2026 Efforts to support the creation of new affordable housing and reduce chronic homelessness are on track, but there is still lots of work to do, according to David Hickey, the minister responsible for the New Brunswick Housing Corporation. New data indicates progress has been made on three key government priorities related to Read More…

  • BJ Electric is now Bernie’s Electric Supplies Ltd

    BJ Electric is now Bernie’s Electric Supplies Ltd

    February 6, 2026 BJ Electric has announced the company has rebranded as Bernie’s Electric Supplies Ltd, a nod to their founder. “BJ Electric Supplies is now Bernie’s Electric Supplies—in honor of our founder, Bernard Joseph Thompson, and the values that have guided the company for nearly 50 years. As we grow and evolve, this name Read More…

  • The Government of Canada Introduces the Build Canada Homes Act

    The Government of Canada Introduces the Build Canada Homes Act

    February 6, 2026 The Government of Canada has introduced the Build Canada Homes Act, legislation that will establish Build Canada Homes as a Crown corporation whose mandate will be dedicated to building affordable housing in communities across the country. As Canada’s affordable housing builder, this legislation will equip Build Canada Homes with the necessary tools to Read More…