OPG Celebrates the Early Completion of Darlington Unit 3

July 18, 2023

The second of four OPG refurbished reactors now re-connected to Ontario’s electricity grid

Ontario Power Generation (OPG) has achieved a major milestone by successfully connecting Darlington Nuclear Generating Station’s Unit 3 to Ontario’s electricity grid, 169 days ahead of schedule. This world-class project performance demonstrates OPG’s expertise and commitment to completing the station’s four-unit refurbishment safely, with quality and on budget, by the end of 2026.

Unit 3 is now the second Darlington unit to undergo complete refurbishment and is operating at 100 percent capacity, providing clean, reliable energy for Ontarians during these peak summer months. The early return of Unit 3 will produce an extra 3 terawatt-hours of energy, enough to power 350,000 homes for an entire year. It will also reduce up to 1 megatonne of greenhouse gas emissions, or the equivalent of taking 300,000 cars off the road for an entire year.

Unit 2 was completed in early June 2020. Thanks to the quality of refurbishment work, in the three years since its return to service, Unit 2 has experienced a record 529-day continuous run. This is industry-leading performance for a CANDU reactor post-refurbishment. Overall generation was also 10 plus percent better than target.

Unit 1 refurbishment, expected to be completed mid-2025, is approximately 60 percent complete and is currently in the reassembly phase. Unit 4, the last of Darlington’s four reactors, will come offline shortly to begin its refurbishment.

Once complete, a refurbished Darlington Nuclear Generating Station will provide more than 30 years of carbon-free power. The Refurbishment project, together with the station’s extended operation, will generate approximately $90 billion in economic benefits for Ontario and create an average of 14,200 jobs annually across the province.

Quick Facts

Quotes

“Through this project, OPG is demonstrating that with detailed planning and preparation, large nuclear projects can be completed not only on-time, but ahead of time and with great quality,” said Ken Hartwick, OPG’s President and CEO. “This would not be possible without the performance, expertise, and commitment from our refurbishment project team, project partners, industry experts, energy professionals, and skilled tradespeople.”

Ken Hartwick, OPG’s President and CEO

“The successful refurbishment of Darlington’s Unit 3 ahead of schedule and on-budget will help power the next major international investment in Ontario, the new homes we are building, and industries as they grow and electrify,” said Todd Smith, Minister of Energy. “It’s also proof that this province can deliver the major energy projects we have planned to Power Ontario’s Growth on-time and on-budget, including building a total of four Small Modular Reactors at Darlington, and beginning pre-development work to site Canada’s first large-scale nuclear build in over three decades.”

Todd Smith, Minister of Energy

Source

Related Articles


Latest Articles

  • Driivz: 2025 State of EV Charging Network Operators Report

    Driivz: 2025 State of EV Charging Network Operators Report

    May 19, 2025 As the EV charging industry is poised for profitability, network operators still face many challenges. But what are their biggest challenges, are they ready to scale up to support their business growth, and how will they provide drivers with a better charging experience in 2025. This report answers these questions and more,… Read More…

  • Electri International: Understanding, Identifying, and Measuring Rework

    Electri International: Understanding, Identifying, and Measuring Rework

    May 19, 2025 ELECTRI has sponsored a research project to create a playbook for electrical contractors that will help you: Unpaid rework refers to activities in the field (including prefabrication) that have to be done more than once, or activities that remove work previously installed as part of the project, where no change order has… Read More…

  • Intermatic Acquired by MPE Partners

    Intermatic Acquired by MPE Partners

    May 19, 2025 By David Gordon, Channel Marketing Group, President The Intermatic deal is done. It has been rumored for months that Intermatic was being sold. Strategic buyers and private equity firms were mentioned as expressing interest and reviewing “the book” throughout the fall (and some mentioned even last summer.) According to sources, it was a “challenge” for… Read More…

  • 6 Things Contractors Need To Know About the Security Kit for Wire Mesh Tray

    6 Things Contractors Need To Know About the Security Kit for Wire Mesh Tray

    May 19, 2025 The rapid expansion of data centers has brought about significant challenges in maintaining data security standards. According to Statistics Canada, recovery costs from cyber security incidents in 2023 were $2.1 billion, up from $600 million in 2021. This critical situation requires a more robust cable management design to protect data from being… Read More…


Changing Scene

  • Schneider Electric Canada Named One of Canada’s Greenest Employers for 2025

    Schneider Electric Canada Named One of Canada’s Greenest Employers for 2025

    May 19, 2025 Schneider Electric Canada has been recognized as one of Canada’s Greenest Employers for 2025 by Mediacorp Canada Inc. as part of the Canada’s Top 100 Employers project, a prestigious honour celebrating organizations that lead the country in creating a culture of environmental sustainability. This recognition highlights Schneider Electric’s long-standing commitment to advancing climate action, driving… Read More…

  • NEW ECAO Website is LIVE

    NEW ECAO Website is LIVE

    May 19, 2025 ECAO are excited to officially launch the new and improved ECAO website, redesigned with you in mind. Whether you are registering for training, accessing member resources, or staying up to date on key industry developments, ECAO’s new platform makes it faster, easier, and smarter. ECAO have rebuilt the site to deliver the ultimate… Read More…

  • Catalyst Sales and Marketing Announces New Partnership with MGM Transformers

    Catalyst Sales and Marketing Announces New Partnership with MGM Transformers

    May 19, 2025 Catalyst Sales and Marketing is proud to announce a new line partnership with MGM Transformer Company, a recognized provider of dry-type and liquid-filled transformers for commercial, industrial, and infrastructure applications. With over 50 years of expertise, MGM delivers custom-engineered, reliable, and energy-efficient solutions designed to meet the demands of data centers, renewable… Read More…

  • Intermatic Acquired by MPE Partners

    Intermatic Acquired by MPE Partners

    May 19, 2025 By David Gordon, Channel Marketing Group, President The Intermatic deal is done. It has been rumored for months that Intermatic was being sold. Strategic buyers and private equity firms were mentioned as expressing interest and reviewing “the book” throughout the fall (and some mentioned even last summer.) According to sources, it was a “challenge” for… Read More…