OPG Celebrates the Early Completion of Darlington Unit 3

July 18, 2023

The second of four OPG refurbished reactors now re-connected to Ontario’s electricity grid

Ontario Power Generation (OPG) has achieved a major milestone by successfully connecting Darlington Nuclear Generating Station’s Unit 3 to Ontario’s electricity grid, 169 days ahead of schedule. This world-class project performance demonstrates OPG’s expertise and commitment to completing the station’s four-unit refurbishment safely, with quality and on budget, by the end of 2026.

Unit 3 is now the second Darlington unit to undergo complete refurbishment and is operating at 100 percent capacity, providing clean, reliable energy for Ontarians during these peak summer months. The early return of Unit 3 will produce an extra 3 terawatt-hours of energy, enough to power 350,000 homes for an entire year. It will also reduce up to 1 megatonne of greenhouse gas emissions, or the equivalent of taking 300,000 cars off the road for an entire year.

Unit 2 was completed in early June 2020. Thanks to the quality of refurbishment work, in the three years since its return to service, Unit 2 has experienced a record 529-day continuous run. This is industry-leading performance for a CANDU reactor post-refurbishment. Overall generation was also 10 plus percent better than target.

Unit 1 refurbishment, expected to be completed mid-2025, is approximately 60 percent complete and is currently in the reassembly phase. Unit 4, the last of Darlington’s four reactors, will come offline shortly to begin its refurbishment.

Once complete, a refurbished Darlington Nuclear Generating Station will provide more than 30 years of carbon-free power. The Refurbishment project, together with the station’s extended operation, will generate approximately $90 billion in economic benefits for Ontario and create an average of 14,200 jobs annually across the province.

Quick Facts

Quotes

“Through this project, OPG is demonstrating that with detailed planning and preparation, large nuclear projects can be completed not only on-time, but ahead of time and with great quality,” said Ken Hartwick, OPG’s President and CEO. “This would not be possible without the performance, expertise, and commitment from our refurbishment project team, project partners, industry experts, energy professionals, and skilled tradespeople.”

Ken Hartwick, OPG’s President and CEO

“The successful refurbishment of Darlington’s Unit 3 ahead of schedule and on-budget will help power the next major international investment in Ontario, the new homes we are building, and industries as they grow and electrify,” said Todd Smith, Minister of Energy. “It’s also proof that this province can deliver the major energy projects we have planned to Power Ontario’s Growth on-time and on-budget, including building a total of four Small Modular Reactors at Darlington, and beginning pre-development work to site Canada’s first large-scale nuclear build in over three decades.”

Todd Smith, Minister of Energy

Source

Related Articles


Latest Articles


Changing Scene

  • SurgePure Corporation Expands into the Mid-West with New Representation Partner, Advance Electrical Agency

    SurgePure Corporation Expands into the Mid-West with New Representation Partner, Advance Electrical Agency

    August 1, 2025 SurgePure Corporation is proud to announce its new partnership with Advance Electrical Agency, who will represent the company across Saskatchewan, Manitoba, and Western Ontario. Led by principals Darren Churchwell and Bob Fiesel , the Advance team is part of a well-established agency known for representing some of the most respected manufacturers in… Read More…

  • Munden Partners with Valid Manufacturing in Atlantic Canada

    Munden Partners with Valid Manufacturing in Atlantic Canada

    August 1, 2025 Munden Enterprises has announced that they are back in the custom enclosure business through a new partnership with Valid Manufacturing Ltd. Expect Canadian-made, engineered solutions for industrial, utility, transportation, wastewater, renewables, and beyond. Whether you need a bare enclosure or a fully assembled panel, Munden is here to help. Reach out to… Read More…

  • JEHS Joins Forces with NOARK to Deliver Smarter Electrical Solutions in Ontario

    JEHS Joins Forces with NOARK to Deliver Smarter Electrical Solutions in Ontario

    August 1, 2025 NOARK Electric is pleased to announce a new partnership with Cambridge, Ontario based manufacturing representitive, JEHS. This strategic collaboration will expand NOARK’s reach and customer support across Ontario and beyond, bringing reliable and innovative electrical solutions to a wider audience. With over 50 years of combined sales experience, JEHS brings a strong… Read More…

  • BC Hydro Making it Easier and More Affordable to Connect New Homes

    BC Hydro Making it Easier and More Affordable to Connect New Homes

    July 24, 2025 BC Hydro is supporting the construction of new housing developments in growing communities by advancing changes to streamline upgrades and reducing the cost of new customer connections to BC Hydro’s electricity grid. “As communities across B.C. grow, so does the need for essential housing. We are committed to ensuring we’re ready to… Read More…