Government of Canada Approves Manitoba-Minnesota Transmission Project subject to 28 NEB Conditions

EIN 26 CS manitoba transmission 400

June 20, 2019

Canada’s Minister of Natural Resources recently announced the Governor in Council has approved Manitoba Hydro’s $453 million Manitoba-Minnesota Transmission Project.

The proposed Manitoba–Minnesota Transmission Project will strengthen the overall reliability of Manitoba’s electricity supply, allow Manitoba Hydro to fulfill current export sales agreements, and increase access to markets in the United States, supporting the export sales that keep rates lower for Manitobans. Manitoba Hydro requires federal and provincial approval of the project.

This power project will:

  • enhance the competitiveness of Canada’s electricity market,
  • support a minimum of 20 percent of construction contracts that involve purchases from Indigenous suppliers, contracts with Indigenous subcontractors, and the employment and training of Indigenous peoples,
  • strengthen energy relationship with the United States by increasing Canada’s electricity exports, and  
  • protect the environment by supporting growth in renewables and reduce GHG emissions by more than 3 million tonnes by displacing production from coal-fired generation and other sources of electricity.

As part of today’s announcement, the government has directed the NEB to amend five project conditions in order to respond to and accommodate concerns raised by Indigenous groups during the Crown consultation process.  The modification of NEB conditions is responsive to the guidance provided by the Federal Court of Appeal decision on the Trans Mountain Expansion project.

The government also responded to three suggestions made by the NEB in its Reasons for Decision Report, including through the creation of a terrestrial and cultural studies initiative to support Indigenous-led studies on issues related to the project.

Approving good projects following thorough reviews is part of the government’s plan to create good, middle class jobs, protect the environment, and advance reconciliation with Indigenous peoples.

  • The Government’s approval of Manitoba Hydro’s $453 million project is subject to 64 Manitoba licence conditions and 28 National Energy Board (NEB) conditions to ensure the safe construction and operation of the project, environmental protections, and ongoing engagement with Indigenous groups.
  • The project will consist of the Dorsey Interprovincial Power Line (IPL) and modifications to two existing transmission lines. The Dorsey IPL is a 213 kilometer, 500 kilovolt power line that would extend from northwest of Winnipeg to the State of Minnesota, crossing the Canada-United States border near Piney, Manitoba. 

  • The NEB will now issue a Certificate of Public Convenience and Necessity.  Prior to construction, Manitoba Hydro will need to demonstrate to the NEB how it will meet the necessary pre-construction conditions for the project, including ongoing consultations with Indigenous communities.

The project includes construction of a 500-kilovolt AC transmission line in southeastern Manitoba and upgrades to associated stations at Dorsey, Riel, and Glenboro. The proposed route will:

  • originate at the Dorsey Converter Station (located near Rosser, northwest of Winnipeg);
  • travel south around Winnipeg and pass near the Riel Station (east of the city) along what is known as the Southern Loop corridor;
  • continue south to the Manitoba–Minnesota border;
  • connect to the Great Northern Transmission Line.

The Great Northern Transmission Line is to be constructed by Minnesota Power. It will terminate at Iron Range Station located northwest of Duluth, Minnesota. Subject to regulatory approvals, the projected in service date is mid-2020. The budget as of the spring of 2017 is estimated at $453 million.

Right-of-way and tower design

The right-of-way required for the transmission line will depend on the design of the tower structures. Predominantly 2 tower types will be utilized and will typically range in height from 40 to 60 metres. Spacing between towers will 400 to 500 metres apart on average.

  • Self-supporting steel lattice structures will be used in cultivated crop lands (agricultural areas), to minimize impact on agricultural operations. Right-of-way width will be 80 metres for self supporting structures.
  • Guyed steel structures will be used in non-cultivated lands. Right-of-way width will be 100 metres for guyed structures.

Station modifications

For the transmission line to be compatible with the existing system, modifications to both Riel and Dorsey converter stations will be undertaken.

Although distant from the proposed transmission line, modifications to Glenboro Station will also be required, including extending the current switch yard and installing additional equipment. Several towers on existing lines will be relocated to accommodate the station expansion.

Go HERE for more information on the project

Related Articles


Latest Articles

  • NSAA Apprenticeship Management System (AMS) is Now Available

    NSAA Apprenticeship Management System (AMS) is Now Available

    June 19, 2026 NSAA has now launched the Apprenticeship Management System (AMS) to provide a faster, easier, and more transparent way for apprentices and employers to manage apprenticeship activity. For Apprentices, Apprenticeship Management System will allow you to:  For Employers, with Apprenticeship Management System, you will be able to:  For Tradespersons Your launch of Apprenticeship… Read More…

  • IP Ratings in Lighting: What They Actually Mean in the Field

    IP Ratings in Lighting: What They Actually Mean in the Field

    By CSC LED IP ratings are among the most frequently referenced specifications in lighting, yet they are often misunderstood or oversimplified. While they may appear to be just another number on a specification sheet, IP ratings play an important role in determining where a fixture can be installed and how it will perform over time.… Read More…

  • The Role of Offshore Sourcing: An Editorial Perspective for Manufacturers, Distributors, Agents, Contractors, and Industry Stakeholders

    The Role of Offshore Sourcing: An Editorial Perspective for Manufacturers, Distributors, Agents, Contractors, and Industry Stakeholders

    The real divide is not domestic versus offshore. It is between committed, accountable partners and transactional, price‑only players. The CSA mark sits inside that story as one important signal but it is only a subset of what the market should be looking at. Read More…

  • Alberta OHS Code Review

    Alberta OHS Code Review

    June 15, 2026 Albertans are invited to provide feedback for Alberta’s ongoing review of Alberta’s OHS Code. Complete the surveys by July 8. Albertans are invited to participate in our ongoing review of the Occupational Health and Safety Code (OHS Code). This is an opportunity to improve health and safety outcomes for workers and streamline… Read More…


Changing Scene

  • AEMC® Instruments welcomes Mark Stathenas as Authorized Factory Representative for Eastern Canada

    AEMC® Instruments welcomes Mark Stathenas as Authorized Factory Representative for Eastern Canada

    June 19, 2026 AEMC® Instruments, part of the Chauvin Arnoux Group® welcomes Mark Stathenas as Authorized Factory Representative for Eastern Canada.  Mark will serve as your primary point of contact for product information, technical support, and order coordination in the Eastern Canada region. With over two decades of experience in technical sales, distribution and business development, Mark brings a… Read More…

  • BCCA Response to Investment Announcement

    BCCA Response to Investment Announcement

    June 19, 2026 Statement from BCCA: The British Columbia Construction Association (BCCA) welcomes today’s joint announcement by the federal and provincial governments to invest in housing, infrastructure, healthcare, and public transit across British Columbia, including funding to reduce Development Cost Charges (DCCs). These investments will help support the infrastructure needed to enable new housing and… Read More…

  • ECAO Recognition of Safety Achievement Award Recipients

    ECAO Recognition of Safety Achievement Award Recipients

    June 15, 2026 ECAO is proud to recognize the recipients of their Recognition of Safety Achievement Award. This award honours member companies that demonstrate exceptional commitment to workplace safety through outstanding safety performance and a strong culture of prevention. The Recognition of Safety Achievement Award celebrates organizations that maintain injury and illness statistics below the… Read More…

  • ECS Announces the Promotion of Jeff Bartlette to Branch Manager, Winnipeg

    ECS Announces the Promotion of Jeff Bartlette to Branch Manager, Winnipeg

    June 15, 2026 ECS is pleased to announce the promotion of Jeff Bartlette to Branch Manager, Winnipeg. Jeff joined ECS with a mandate to establish the company’s presence in Manitoba. Having successfully balanced both sales and leadership responsibilities, he will now focus fully on developing his team, strengthening branch capabilities, and positioning Winnipeg for continued… Read More…