Alberta Pauses Approvals for Renewable Energy Projects as of Aug 3rd

August 8, 2023

Starting Aug. 3, the Alberta Utilities Commission (AUC) will pause approvals of new renewable electricity generation projects over one megawatt until Feb. 29, 2024, and review policies and procedures for the development of renewable electricity generation.

This approach is in direct response to a letter received from the AUC and concerns raised from municipalities and landowners related to responsible land use and the rapid pace of renewables development. At the end of this process, future renewable projects will be able to move forward at a pace that is conducive to business while maintaining responsible environmental stewardship and preserving Alberta’s reliable electricity supply.

Throughout the process, Albertans will still be able to install renewable energy products in their homes and communities.

“Participants in our public hearings have increasingly raised concerns about the impacts and pace of renewable generation development. We are pleased to support the government in canvassing relevant issues for its development of policy to ensure the economic, orderly and efficient development of electricity generation in Alberta.”

Carolyn Dahl Rees, chair, Alberta Utilities Commission

“RMA is pleased by this decision to develop a provincewide plan for how the industry can grow strategically and responsibly. Rural municipalities cover roughly 85 per cent of Alberta’s land and their voices must be included in the approval process for all renewable energy projects. We look forward to working with the Government of Alberta to create an approval process that balances provincial and local perspectives and positions Alberta as a leader in responsible renewable energy development.”

Paul McLauchlin, president, Rural Municipalities of Alberta 

The AUC inquiry will include reviewing the use of agricultural land and public land for wind and solar projects, land reclamation and the role of municipal governments in land selection for project development and review.

The inquiry will inform government policy decisions around the ongoing economic, orderly and efficient development of electricity generation in Alberta and will look at issues, including:

  • Development of power plants on specific types or classes of agricultural or environmental land.
  • The impact of power plant development on Alberta’s pristine viewscapes.
  • Mandatory reclamation security requirements for power plants.
  • Development of power plants on lands held by the Crown.
  • The impact of the increasing growth of renewables on Alberta’s generation supply mix and electricity system reliability.

Quick facts

  • The AUC is an independent, quasi-judicial agency that is responsible for the approval of Alberta’s electricity generation projects.
  • The Government of Alberta does not determine when or where electrical generation facilities are to be built.
  • The AUC is currently reviewing 15 renewable, thermal and energy storage projects.
  • All utility-scale renewable generation projects in Alberta are commercially developed on private land only and can only advance with the permission of private landowners.

Source

Recommended Reading

CanREA: Alberta Market at Risk Without Swift Resolution to Moratorium

Related Articles


Latest Articles

  • ESA 2025 Annual Licence Holder Meeting

    ESA 2025 Annual Licence Holder Meeting

    December 8, 2025 This year marked ESA’s 20th Annual Licence Holder Meeting — a milestone celebrating two decades of collaboration, innovation and safety leadership made possible by Ontario’s licence holder community. The meeting was held on Wednesday, November 26, 2025 Agenda Highlights Watch a recording of the 2025 Licence Holder Meeting. Read More…

  • BC Hydro’s Updated Business Energy-Saving Incentives, Limited Time Bonus Offer

    BC Hydro’s Updated Business Energy-Saving Incentives, Limited Time Bonus Offer

    December 8, 2025 Get funding from BC Hydro for businesses upgrading eligible equipment with energy-efficient models. Funding rates vary depending on the equipment being upgraded, with past participants receiving an average of 30% for upfront costs. Incentives are available for: Bonus offer BC Hydro is currently offering a 30% bonus incentive on all business energy-saving incentives projects… Read More…

  • Mastering Advanced Bidding Strategies in Electrical Contracting

    Mastering Advanced Bidding Strategies in Electrical Contracting

    December 1, 2025 By Melvin Newman, Patabid CEO & Ian Paterson, Patabid Client Success Manager and journeyman electrician with 30+ years of experience In the competitive world of electrical contracting, knowing how to estimate electrical jobs effectively can make the difference between winning profitable projects and watching opportunities slip away. For electrical contractors, mastering advanced… Read More…

  • Why Choosing the Right USB Charger Matters

    Why Choosing the Right USB Charger Matters

    December 1, 2025 Not all USB Chargers are Created Equal As the number of devices used daily increases, so does the need for a charger that delivers safe speeds and maximum charging potential. A high-quality USB charger delivers efficient charging without risk of damage, but the sea of USB chargers and outlets available on online… Read More…


Changing Scene