Study Says $904 Million Manitoba-Nunavut Hydro Link Is Economically Viable

Nunavut

A scoping study conducted by Montreal engineering firm BBA Inc. concludes that extending transmission lines north from Churchill, MB up the western Hudson Bay coastis economically viable, environmentally beneficial, and should proceed without delay. The $904 million project could be completed by 2025 if a feasibility study begins by early 2016, the study authors say.

Image: The transmission line route would travel over continuous permafrost, indicated by the sold purple background (Image courtesy of BBA).

The study suggests the project would pay for itself over an estimated 40-year lifetime, delivering projected savings of $40 million a year by replacing fossil fuels from dirty, expensive diesel generators with cleaner, cheaper hydroelectric power.
The study was commissioned by the Kivalliq Inuit Association on behalf of the Energy Options Working Group (EOWG), established under Hudson Bay Regional Roundtable. The roundtable is a government body that addresses issues and creates opportunities for remote communities connected to Hudson Bay.The roundtable is co-chaired by the Manitoba Minister of Aboriginal and Northern Affairs and the Nunavut Minister of Community and Government Services.

In a joint statement, EOWG co-chairs Mayor Bob Leonard of Arviat, Nunavut and Mayor Michael Spence of Churchill, Manitoba stated “We hope that this report acts as a basis for future study and action so that Nunavummiut in the Kivalliq region will have access to environmentally-friendly, sustainable, and affordable energy while making the region more attractive to increased economic development and private investment.”

Next steps include funding requests to the governments of Nunavut, Manitoba and Canada for a briefing and feasibility study.

Related Articles


Latest Articles

  • EFC Letter on China Tariffs

    EFC Letter on China Tariffs

    September 15, 2024 The Canadian federal government intends to apply a 25 per cent surtax on imports of steel and aluminum products from China, effective October 15, 2024. See announcement here. The initial list of impacted goods was released for public comment and submissions are due September 20, 2024.  The list of products is available… Read More…

  • Changing How we Build Homes: A Year of the Housing Accelerator Fund

    Changing How we Build Homes: A Year of the Housing Accelerator Fund

    September 15, 2024 The Government of Canada is highlighting key results that have come from the first Housing Accelerator Fund since the start of the Program. This week marks the closure of the application portal for the second round of the HAF. HAF was created to incentivize local governments to implement structural and lasting reforms that will increase… Read More…

  • Multi-Unit Construction Intentions Fuel Growth in the Residential Sector for July Building Permits

    Multi-Unit Construction Intentions Fuel Growth in the Residential Sector for July Building Permits

    September 15, 2024 Month over month, the total value of building permits in Canada surged 22.1% to $12.4 billion in July, rebounding from two consecutive monthly declines. Both the residential and non-residential sectors expanded in July. On a constant dollar basis (2017=100), the total value of building permits in July was up 22.9% compared with the previous month,… Read More…

  • B.C. Building Code Updated to Support More Homes

    B.C. Building Code Updated to Support More Homes

    September 15, 2024 Changes to the BC Building Code (BCBC) will allow single egress stair (SES) designs in low- and mid-rise buildings to support more multi-bedroom apartment options. The Province has updated the BCBC to remove the code requirement for a second egress, or exit, stairwell per floor in buildings up to six storeys. This change will… Read More…


Changing Scene

  • Leviton Canada Achieves Another Year of Carbon Neutrality

    Leviton Canada Achieves Another Year of Carbon Neutrality

    September 15, 2024 Leviton Canada proudly reaffirms its commitment to sustainability by achieving carbon neutrality once again in 2023. The company has significantly reduced their environmental footprint by 32% compared to 2022, with a substantial impact on transportation. Despite having energy-efficient lighting and relying on hydropower—a clean and renewable energy source—for their facility, transportation (both… Read More…

  • Grand Opening: Legrand BCS Office in Markham

    Grand Opening: Legrand BCS Office in Markham

    September 15, 2024 Legrand is thrilled to announce the grand opening of their new BCS facility in the heart of downtown Markham, ON, located at 85 Enterprise Blvd, Suite 400, which is set to take place on Thursday, September 19th, 2024. “Our facility in Vaughan will remain open to continue to stock inventory for Canada… Read More…

  • Gescan Announces Partnership with PataBid

    Gescan Announces Partnership with PataBid

    September 15, 2024 Gescan is excited to announce our partnership with PataBid Quantify. PataBid is a Canadian company, with software built for contractors which integrates live supplier pricing, manual drafting, and AI technology with human expertise to maximize take offs and bidding. Patabid’s Quantify software will allow contractors to access live pricing from Gescan’s website… Read More…

  • Electrical Safety Authority Unveils ‘A-MAZE-ing’ Interactive Experience to Keep Kids Safe from Electrical Harm

    Electrical Safety Authority Unveils ‘A-MAZE-ing’ Interactive Experience to Keep Kids Safe from Electrical Harm

    September 15, 2024 The Electrical Safety Authority (ESA) cut the ribbon on its new interactive experience, “The A-MAZE-ing Adventures of Carter Current”, located at the Peel Children’s Safety Village. The interactive space is designed to help educate and keep kids safe from electrical harm by learning about electrical hazards through play. “We are excited to partner with… Read More…