PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • Maximizing Excel: Practical Use Cases for Preconstruction

    Maximizing Excel: Practical Use Cases for Preconstruction

    November 8, 2024 By Melvin Newman Excel is a powerful and flexible tool that can enhance efficiency in electrical construction estimating.  Spreadsheets, like those in Excel, consist of a grid of “cells” where each cell can hold various types of data. Originating from mainframe computers in the 1960s and later developed for Apple computers in… Read More…

  • The Non-Residential Sector Declines in All Three Components Despite Sustained Industrial Permit Level

    The Non-Residential Sector Declines in All Three Components Despite Sustained Industrial Permit Level

    November 4, 2024 The total value of building permits in Canada decreased by $858.1 million (-7.0%) to $11.5 billion in August, following a strong July during which construction intentions rose sharply (+20.8%). The residential and non-residential sectors contributed to the decrease in August. On a constant dollar basis (2017=100), the total value of building permits decreased 7.6% in… Read More…

  • A Slight Decrease in Residential Building Construction for August

    A Slight Decrease in Residential Building Construction for August

    November 4, 2024 Investment in building construction edged up 0.2% to $21.0 billion in August, after a 1.6% decrease in July. The residential sector edged down (-0.1%) to $14.6 billion, while the non-residential sector was up 1.0% to $6.4 billion. Year over year, investment in building construction grew 7.2% in August. On a constant dollar basis (2017=100), investment in building construction was… Read More…

  • When a Familiar Door Closes

    When a Familiar Door Closes

    November 4, 2024 By Keith Sones, seasoned utility industry executive Most of the articles I’ve written have been based on personal experiences, many of them occurring decades ago, which eventually translate into helpful life lessons. The years allow the events to marinate in a savoury stew of time and reflection, clarity never coming immediately, or even… Read More…


Changing Scene

  • Ontario Streamlining Pathways for Veterans into Skilled Trades

    Ontario Streamlining Pathways for Veterans into Skilled Trades

    November 8, 2024 The Ontario government is making it easier for Canadian Armed Forces (CAF) members, their spouses and veterans to start careers in the skilled trades. The province is also investing $2.4 million through the Skills Development Fund (SDF) to provide free training for CAF members and veterans in tech and cybersecurity careers. These initiatives… Read More…

  • Electric Avenue Partners with Rexel Atlantic to Expand EV Charging Solutions Across the Region

    Electric Avenue Partners with Rexel Atlantic to Expand EV Charging Solutions Across the Region

    November 8, 2024 Electric Avenue Manufacturing is pleased to announce a new distribution partnership with Rexel Atlantic. This strategic alliance will bring Electric Avenue’s advanced EV charging solutions to a broader audience, delivering convenience and quality to residential, commercial, and industrial sectors throughout the Atlantic region. Through this collaboration, Rexel Atlantic will offer Electric Avenue’s full… Read More…

  • BJ Take Rebrands as BJ Take Lighting

    November 8, 2024 BJ Take is an acronym chosen by the company’s founders, so they would not lose focus of why they were starting their company. The name stands for the Buma familt name and Ed and MaryAnn Buma’s five children. Now in its second-generation of family ownership, BJ Take has rebranded to BJ Take… Read More…

  • Government of Canada Invests $10.45M to Accelerate Residential Construction in Quebec

    Government of Canada Invests $10.45M to Accelerate Residential Construction in Quebec

    November 8, 2024 To better meet the evolving needs of all regions across the country, the Government of Canada yesterday launched the Regional Homebuilding Innovation Initiative (RHII). Delivered by Canada’s regional development agencies (RDAs), the RHII supports manufacturers in the residential construction sector in order to accelerate innovation in this industry and transform how homes will be built in the future. The federal government… Read More…