Case Study: Guildford, BC’s Recreation Centre Aquatic Addition

December 12, 2016

The Guildford Recreation Centre Aquatic Addition expands an existing facility in Surrey, BC. The 7,000 square meter addition was designed as a destination aquatic facility for both recreation and therapeutic users, offering a 50m Federation Internationale de Natation (FINA) certified lap pool as well as a leisure pool that contains a therapeutic area, waterslide, family friendly hot tub, and children’s area.

The City of Surrey’s initial project objectives were to increase the value of the facility to the city and the community, reduce waste, and maximize efficiency. Surrey’s “Wood First Policy” was achieved in the design of the Guildford Recreation Centre Aquatic Addition, which incorporated the lighting and HVAC for the natatorium. Initially destined to be open web steel joist, the final product consists of three dimensional timber trusses. The trusses were pre-assembled offsite, which allowed for easier installation, reduced waste and cost, and saved construction time to help with the accelerated schedule. This solution became a defining feature of the Guildford Aquatic Centre.

The project earned an IES Edwin R. Guth Award for Interior Lighting Design. 

Project objectives, solutions and achievements

A primary goal of the Guildford Recreation Centre Aquatic Addition was to create a building that would provide the public of all ages with a welcoming swimming pool, where they can compete, exercise, play, and relax. The City of Surrey wanted the lap pool designed to FINA swimming pool guidelines in order to host FINA competitions within the facility, allowing both the public and competitors to enjoy their activities within the same versatile facility.

Electrical engineering design was of key importance to this project in order to meet the competition lighting levels as well as the architectural intent. Meeting the client’s objectives of an aesthetically pleasing and versatile swimming pool, while staying within the energy code requirements, and budget, required creative solutions to minimize equipment costs and maximize equipment efficiency.

AES Engineering Ltd. (AES) worked with other project team members, such as the architectural and mechanical teams, on how their system and design selections would ultimately govern the lighting design throughout the building. Working together in an integrated environment, AES proposed using indirect high efficiency lighting that would create a soft diffused light that would provide the swimming pool with a pleasant glare free light and competition lighting levels, while remaining within energy use requirements.

Light output was maximized through the use of lighting modelling software, high reflectivity paint, high efficiency luminaires, and optimal mounting angles.

Working closely with the multidisciplinary team allowed all systems within the trusses and coves to be configured such that maximum light output was achieved, resulting in a lower overall energy consumption throughout the facility. Various dimensions, angles, material types, and finishes were modelled for the coves and trusses to achieve optimum design characteristics and maximize light output. The resulting design provides the public with comfortable levels of lighting while using minimal amounts of energy.

Project management was crucial to keeping the project on schedule and on budget as the City of Surrey had set an accelerated timeline. In order to meet this, the project had to be designed in multiple packages. The foundation package was designed first, well in advance of the systems inside the building, while the second package contained the remainder of the project design. AES worked in a construction management environment, with contractors who could advise what materials would be available in time to fit the schedule. The prime consultant’s project schedule and AES’s internal deadlines allowed the project to reach substantial completion by the City of Surrey’s deadline.

Technical excellence/innovation: electrical

• Computer modelling — AES utilized various software tools to maximize the light output from both the coves and the trusses. Modelling of various lighting types at multiple angles and positions helped determine which luminaire and layout would provide the best light quality and efficiency within the trusses. To further increase the light output from the truss lighting system, high reflectivity paint was selected and specified by the architect, and the lights were mounted at optimal angles to maximize the amount of light reflected onto the pool. The resulting truss lighting system provides the swimming pool with a very pleasant and even light.

• Low voltage lighting controls — the use of low voltage (LV) lighting controls provided flexibility to the truss lighting system. Three levels of lighting have been implemented within the space to provide selection options to suit its current use. Traditionally, lights are switched in rows or groups, but the lights in the trusses have been configured to switch in an interweaving pattern so that an even light output is achieved no matter what level of light is selected. Providing an even illumination using a minimal number of lights reduces overall energy consumption without sacrificing comfort or safety. The LV system is also scheduled to sweep off all lights when not required, further reducing the carbon footprint of the facility. 

• LED lighting — another energy saving measure includes the use of LED underwater lights rather than traditional halogen lighting. The LV lighting system is also tied in to the underwater lights to provide two user selectable lighting levels.

• Occupancy sensors — working in combination with the LV lighting system, occupancy sensors within enclosed offices, meeting rooms, and washrooms, automatically turn off lights to provide maximum energy savings.

 

A sampling of project luminaires

Among the luminaires used for the project are the following:

• Bartco BFL206 Linear T5s

• Cole Lighting L500 LED Steplites

• Focal Point Avenue D MR 16

• Green Imagetech GX436 vapourproof luminaires

• Kenall Mighty Mac WCBU Series

• Lithonia Lighting AS1 LED, FEM 2s, 4s and 8s, MRP Omero LED, Saturn compact DTT fluorescent, 

• Metalumen Grande RM4DOD

• Pace Illumination Avante-Garde AGSM surface mount

• Paco Lighting Puac T5s and T8s

• Rigalite MHD2/MHDO Series

• Sistemalux Megaeos and Megabrique 

• USAI Lighting BeveLED 2.0

• Winona Winline 309W linear LEDs

 

Project members

• Electrical engineer: AES Engineering Ltd. 

• Project owner/client: City of Surrey 

• Architects: Bing Thom Architects, Shape Architecture 

• Prime consultant: Bing Thom Architects 

• Other consultants involved: The AME Consulting Group Ltd., Fast + Epp, 

• Turnbull Construction Project Managers 

• Contractors: Heatherbrae Builders 

• Photographer: Ema Peter

 

Related Articles


Latest Articles

  • Code Quiz: Section 26 – Installation of Electrical Equipment

    Code Quiz: Section 26 – Installation of Electrical Equipment

    April 7, 2025 By Bill Burr Section 26 – Installation of Electrical Equipment Receptacles Question: Rule 26-706 specifies that all receptacles of CSA configuration 5-15R and 5-20R installed in: …must have a particular feature, what is this feature? Source: CSA C22.1:24, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. © 2021 Canadian… Read More…

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

    Section 32, as outlined in rule 32 -000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection, of fire alarm systems… Read More…

  • Alberta Municipalities EV Charging Installation Rebate

    Alberta Municipalities EV Charging Installation Rebate

    April 4, 2025 Alberta Municipalities are proud to provide financial rebates for applicants to purchase and install electric vehicle charging stations in Alberta as part of the Electric Vehicle Charging Program (EVCP), funded by Natural Resources Canada (NRCan) & Alberta Municipalities.  The funding will cover up to 46% of your total project cost, which can… Read More…

  • Industry Legend Bill Smith Retires

    Industry Legend Bill Smith Retires

    April 4, 2025 By Electro-Federation Canada On March 25, Electrozad, a Sonepar Company, hosted a special retirement reception at Caesars Windsor for industry titan Bill Smith who marked an incredible 50-year career with the company.  The reception was held in the elegant Caesars Ballroom, which featured an array of food stations and elegant decor. In… Read More…


Changing Scene

  • NSAA Fee Change Effective April 1, 2025

    NSAA Fee Change Effective April 1, 2025

    As of April 1, 2025, the Nova Scotia Apprenticeship Agency’s fees have changed due to the 1% reduction in HST in Nova Scotia. NSAA noted on their website that due to the number of references across various pages, you may still come across old fee amounts as they work through updating their website. Here is… Read More…

  • Nominations Open for 2024 NETCO Leadership Excellence Award

    Nominations Open for 2024 NETCO Leadership Excellence Award

    Established in 2016, the NETCO Leadership Excellence award honours an industry training professional for his/her role for the success and their outstanding contributions to apprenticeship training and continuing electrical training. Read More…

  • Munded Partners with Kane Test Equipment in Atlantic Canada

    Munded Partners with Kane Test Equipment in Atlantic Canada

    April 4, 2025 Munden Enterprises has announced a partnership with Kane Test Equipment to bring their test and measurement solutions to Atlantic Canada. “We are now excited to announce a new and promising partnership with Kane Test Equipment. Kane Test Equipment brings innovative solutions that align with our dedication to providing the best tools for… Read More…

  • Nedco Announces Western Canadian Wire & Cable Sales Manager

    Nedco Announces Western Canadian Wire & Cable Sales Manager

    April 4, 2025 Don Blake has joined Nedco as their Western Canadian Wire & Cable Sales Manager. “With over 20 years of experience in the Wire & Cable industry, Don brings a wealth of knowledge and expertise to our Nedco West team,” said the company on LinkedIn. “His focus will be on expanding our product… Read More…