Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • EFC: A Captivating Quebec Economic Forecast

    EFC: A Captivating Quebec Economic Forecast

    October 7, 2024 On September 19, nearly 50 members of the Quebec section of the Canadian Electro-federation had the opportunity to attend a highly strategic evening with none other than Valérie Beaudoin, Analyst and speaker specializing in American politics to talk about the issues that the upcoming US election decisions will have on the Canadian/Québec… Read More…

  • BC Hydro: Business Energy Saving Incentives

    BC Hydro: Business Energy Saving Incentives

    October 7, 2024 Get funding for energy-efficient equipment upgrades By focusing on what uses the most energy in your business, you can make energy-efficient upgrades for the greatest impact on savings.  The offer Business customers can upgrade any of the equipment listed below with eligible, energy-efficient models and BC Hydro will provide funding to cover… Read More…

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road: Section 20

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road: Section 20

    October 7, 2024 Section 20 – Flammable liquid and gasoline dispensing, service stations, garages, bulk storage plants, finishing processes, and aircraft hangars. The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical… Read More…

  • Electric Avenue Responds to Enel X’s Exit from North American Market with a Call for Open-Source EV Charging Standards

    Electric Avenue Responds to Enel X’s Exit from North American Market with a Call for Open-Source EV Charging Standards

    October 4, 2024 Electric Avenue has issued a response to the recent announcement that Enel X, a major player in the EV charging space, will be shutting down its North American operations effective October 11, 2024. This decision leaves over 170,000 EV chargers across the U.S. and Canada without software support, rendering them largely inoperable…. Read More…


Changing Scene