The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code. In this article: Section 18 Hazardous locations, Part 2.

Section 18 covers installation of electrical equipment in hazardous locations as defined in Section 0, such as areas in which there is a potential for the ignition of explosive or combustible gases, dusts, fibres or flyings due to the design, installation or use of electrical equipment. Since the information in this instalment is extensive it is presented in two parts. This Instalment is Part 2.

Explosive gas atmospheres

This part contains rules for the installation of electrical equipment in all locations where explosive gas may be present.

Installations in Zone 0 locations

Rule 18-090 — Zone O is the hazardous location where explosive gas atmospheres are present continuously or for long periods and is the most restrictive. No electrical equipment or wiring may be installed in a Zone 0 hazardous location unless it meets the requirements of subrule 18-090 (2). Also note the marking requirements for Zone 0.

Rule 18-092 — seals are required where conduit leaves a Zone 0 location, and at the first point of termination of cables after entry to the Zone 0 location. Unbroken rigid conduit passing through a Zone 0 need not be sealed if the termination points are outside Zone 0. Seals are not required to be explosion-proof or flame-proof but must be identified for minimizing the passage of fluids or dusts and be accessible.

Installations in Zone 1 locations

Rule 18-100 — electrical equipment suitable for Class I Division 1 with protection level Ga or Gb and protection levels as outlined in 18-100(c) may be installed in a Zone 1 location.

Rule 18-102 — rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands shall be used for wiring in Zone 1. In addition, threads and joints need to comply with 18-102 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-104 provides the rules for sealing conduits and cables entering enclosures in and leaving Zone 1 locations.

Rule 18-106 provides requirements for the installation of motors in Zone 1 locations. Additional guidance is given in Appendix B.

Rule 18-108 provides the rules for installation of Luminaires in Zone 1.

Rule 18-110 — flexible cords are permitted in Zone 1 where flexibility is required but must be installed in accordance with 18-110 (1) and (2).

Installations in Zone 2 locations

Rule 18-150 provides the rules for the installation of equipment in Zone 2. Note that equipment suitable for Class I Division 2 and Zone 0 and Zone 1 are permitted to be installed in Zone 2. Also note that transformers, capacitors, solenoids, and other non-arcing, non-sparking or non-heat-producing devices are permitted in Zone 2 locations.

Rule 18-152 provides rules for wiring methods in Zone 2.

Rule 18-154 provides rules for sealing conduit, cable and equipment in Zone 2.

Rule 18-156 provides rules on installation of luminaires in Zone 2.

Rule 18-158 — flexible cords are permitted in Zone 2 where flexibility is required but must be installed in accordance with 18-158 (1).

Explosive dust atmospheres

This part contains rules for the installation of electrical equipment in all locations where combustible and explosive metal dust may be present.
Installations in Zone 20 locations

Rule 18-190 — like Zone O, Zone 20 is the most restrictive hazardous location where explosive dust atmospheres are present in the form of a cloud of dust in air continuously or for long periods. No electrical equipment or wiring may be installed in a Zone 20 hazardous location unless it meets the requirements of Subrule 18-190.

Rule 18-192 provides requirements for wiring methods in Zone 20.

Rule 18-194 provides requirements for seals for a Zone 20 location.

Rule 18-196 — flexible cords are permitted in Zone 20 where flexible connections are required and shall be extra-hard-usage cord with cable glands.
Installations in Zone 21 locations

Rule 18-200 provides rules for installation of equipment in Zone 21. Equipment suitable for Class II Division 1 is permissible as well as equipment with the noted types of protection in (b) and ©.

Rule 18-202 — rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands shall be used for wiring in Zone 21. In addition, threads and joints need to comply with 18-202 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-204 provides rules for sealing raceway equipment in Zone 21.

Installations in Zone 22 locations

Rule 18-250 provides rules for installation of equipment in Zone 22. Equipment suitable for Class II Division 2 is permissible as well as equipment with the noted types of protection in (b) and (c). This rule also provides rules for installation of cranes, hoists and other material handling equipment in Zone 22 locations.

Rule 18-252 provides rules for wiring methods in Zone 22.

Rule 18-254 provides the same sealing requirements as Zone 21.

In the next instalment we will discuss Section 20 — Flammable liquid and gasoline dispensing, service stations, garages, bulk storage plants, finishing Processes and aircraft hangars.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 – Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 – Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Efficiency Nova Scotia Rebates

    Efficiency Nova Scotia Rebates

    January 24, 2025 NEW Up to 75% of product costs in rebates for energy efficient products or interest-free financing for up to 24 months. Get rebates Before You Buy, at the counter, or After You Buy with mail-in and instant rebates. Before you Buy Instant Rebates No paperwork required. Save at the counter when you… Read More…

  • The Drive Towards Energy-Efficient Data Centres

    The Drive Towards Energy-Efficient Data Centres

    Data centres are the backbone of our digital world. They serve as the foundation for various online activities like streaming, e-commerce, website/app usage, Digital transformation. Read More…

  • Multi-Unit Construction Intentions Push Down the Residential Sector for November 2024 Building Permits

    Multi-Unit Construction Intentions Push Down the Residential Sector for November 2024 Building Permits

    January 20, 2025 The total value of building permits issued in Canada decreased by $739.5 million (-5.9%) to $11.7 billion in November, a second consecutive monthly decline. The residential sector led the decrease, followed by the non-residential sector. On a constant dollar basis (2017=100), the total value of building permits issued in November declined 5.8% from the previous… Read More…

  • Ontario Save On Energy Home Renovation Savings Program

    Ontario Save On Energy Home Renovation Savings Program

    January 20, 2025 On January 7, the Government of Ontario announced 14 new and expanded energy-efficiency programs, including the Home Renovation Savings Program, as part of a new $10.9 billion investment in energy efficiency to help families and businesses save money. Save on Energy and Enbridge Gas, with endorsement from the Ontario government, have partnered to… Read More…


Changing Scene

  • Agence Ricard Welcomes New Business Development Specialist for the South Shore of Montreal 

    Agence Ricard Welcomes New Business Development Specialist for the South Shore of Montreal 

    January 24, 2025 Agence Ricard is proud to announce the arrival of Fred Dozois as new business development specialist for the South Shore of Montreal. With over 10 years of experience in the electrical industry, Fred brings an impressive wealth of knowledge and skills that will strengthen the team at Ricard.  Recognized for his expertise,… Read More…

  • Graybar Transforming Branches From Coast to Coast

    Graybar Transforming Branches From Coast to Coast

    January 24, 2025 Exciting transformations are happening at Graybar Canada. Across the nation, Graybar branches are getting a refreshed look, inside and out. These updates reflect their dedication to maintaining modern, welcoming spaces that showcase the strength of their brand and world class manufacturer partners. From sleek new shelving to vibrant wall murals, these renovations are designed… Read More…

  • New Address for Franklin Empire London, ON Branch

    New Address for Franklin Empire London, ON Branch

    January 24, 2025 Franklin Empire are pleased to announce the new address of their London, Ontario branch. Address:552 Newbold StreetLondon, Ontario N6E 2S5 Source Read More…

  • Ontario Launches Regional Economic Development Through Immigration Pilot Program 

    Ontario Launches Regional Economic Development Through Immigration Pilot Program 

    January 24, 2025  The Ontario government has launched the Regional Economic Development through Immigration (REDI) pilot program to target highly-skilled immigration for four rural and northern regions with a high demand for skilled labour: Lanark, Leeds and Grenville, Sarnia-Lambton, and Thunder Bay. REDI enables local employers in these communities to attract up to 800 additional… Read More…