Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • New Gender Equality Report Card Shows Most Jurisdictions are Failing

    New Gender Equality Report Card Shows Most Jurisdictions are Failing

    November 10, 2025 The Canadian Coalition of Women in Engineering, Science, Trade and Technology (CCWESTT) has just released the first Gender Equality Report Card, which provides comprehensive, evidence-based insight into the state of gender equality across Canada’s provinces and territories in science, engineering, trades and technology (SETT) workplaces. The report draws on 18 participatory research… Read More…

  • Guide to the Canadian Electrical Code, Part 1[i] 26th Edition – A Road Map: Section 46

    Guide to the Canadian Electrical Code, Part 1[i] 26th Edition – A Road Map: Section 46

    November 10, 2025 By William (Bill) Burr[i] The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendices B and… Read More…

  • Calgary Project Transforms Office Building into Energy Efficient Housing

    November 10, 2025 More than 200 Calgarians now have new homes in Downtown West as the former Dominion Centre office reopens as Dominion Civic Apartments. The former Dominion Centre has been transformed from 100,000 square feet of vacant office space to an energy efficient and climate resilient residential building with 132 modern rental suites. The… Read More…

  • Remembering Katy Shebath, A Kind And Thoughtful Leader

    Remembering Katy Shebath, A Kind And Thoughtful Leader

    November 10, 2025 By Stanpro Katy Shebath played a critical role alongside her brother, David Nathaniel, throughout the last 32 years of Standard Products journey. She remains, with David, the heart and soul of this company. A Driving Force Behind STANDARD When Katy joined STANDARD in 1986, she took on the administration of the company. At… Read More…


Changing Scene

  • A Groundbreaking Return to the Sir Robert Peel Centre for Ellis Don

    A Groundbreaking Return to the Sir Robert Peel Centre for Ellis Don

    November 10, 2025 In a full circle moment, EllisDon has broken ground on the Sir Robert Peel Centre Redevelopment Project, a facility originally constructed by EllisDon in the 1980s. Now, this milestone marks the beginning of a new chapter in Peel Region’s public safety infrastructure. The redevelopment will deliver a modern, high-performance policing hub designed… Read More…

  • BCCA Response to Federal Budget 2025

    BCCA Response to Federal Budget 2025

    November 10, 2025 The BCCA welcomes the federal government’s investments into construction and infrastructure in Budget 2025. The budget includes increasing Canada Infrastructure Bank funding by $10 billion and funding the new Major Projects Office to the tune of $213.8 million over 5 years. The BCCA also supports the government’s investment into the construction workforce,… Read More…

  • Government of Canada Releases Budget 2025

    Government of Canada Releases Budget 2025

    November 10. 2025 Canada faces a rapidly changing and increasingly uncertain world. The rules-based international order and the trading system that powered Canada’s prosperity for decades are being reshaped – hurting companies, displacing workers, causing major disruption and upheaval for Canadians. In the face of global uncertainty, Canada’s new government is focused on what we… Read More…

  • CME: Budget 2025 Delivers Key Gains for Manufacturers Facing Tariff Pressures, but Canada Still Needs Deeper Competitiveness Reforms

    CME: Budget 2025 Delivers Key Gains for Manufacturers Facing Tariff Pressures, but Canada Still Needs Deeper Competitiveness Reforms

    November 10, 2025 Canadian Manufacturers & Exporters (CME) applauds Budget 2025 for recognizing the serious challenges facing Canada’s economy amid ongoing U.S. trade actions and for introducing new incentives to spur investment. “This budget takes meaningful steps to support manufacturers under pressure and acknowledges the critical role our sector plays in Canada’s economic future,” said… Read More…