Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • ABB Among TIME’s World’s Most Sustainable Companies

    ABB Among TIME’s World’s Most Sustainable Companies

    June 30, 2025 ABB has been ranked 14th in TIME’s “World’s Most Sustainable Companies 2025” and third in Switzerland across all industries. TIME and Statista assessed over 5,000 of the world’s largest and most influential companies, considering factors such as revenue, market capitalization, and public prominence. The top 500 companies from 35 countries and 21 industries were… Read More…

  • New Partnership to Deliver 1,000 Affordable Housing Units Across Quebec

    New Partnership to Deliver 1,000 Affordable Housing Units Across Quebec

    June 25, 2025 The governments of Canada and Quebec, together with Desjardins, have announced the construction of 1,000 new affordable housing units over the next three years. These housing units will be created as part of the Desjardins Affordable Housing Initiative, a partnership launched in 2022 that will now enable the delivery of over 3,000 affordable housing units… Read More…

  • CIB Closes $50M Loan with Dream Industrial REIT to Fund Large-Scale Commercial Building Upgrades

    CIB Closes $50M Loan with Dream Industrial REIT to Fund Large-Scale Commercial Building Upgrades

    June 30, 2025 The Canada Infrastructure Bank (CIB) and Dream Industrial Real Estate Investment Trust have finalized a $50 million loan to fund commercial property retrofits related to energy efficiency savings and emissions reductions at 34 warehouses in Alberta, Ontario and Quebec. With buildings currently accounting for 18% of Canada’s total emissions, investments from the… Read More…

  • Province, BC Hydro Launch Pilot Program to Cut Energy Costs, Support Housing Density

    Province, BC Hydro Launch Pilot Program to Cut Energy Costs, Support Housing Density

    June 25, 2025 In a Canadian first, the Province and BC Hydro have launched a pioneering pilot project in Vancouver that has the potential to set new standards for supporting growing housing priorities and densification in Canada. Designed to support the transition from single-family homes to multi-unit residences, the initiative is exploring how full electrification –… Read More…