Arc Flash Incident Involving a Maintenance Switch

Maintenance Switch

 

Feb 12, 2016

This case study article examines the plans and processes reviewed and considered, the strategy deployed to manage/reduce arc flash hazards, and then lessons learned in the implementation of new systems to improve electrical workplace safety. The setting: a chemical processing facility with a robust electrical workplace safety process. The site experienced an actual arc flash event while energized work was being performed.

Photo courtesy: www.utilityproducts.com

The facility was planning energized work for an existing 480 V low voltage switchgear assembly that was an existing piece of equipment in the plant. During a process upgrade in the facility, an energized work permit was issued to remove three abandoned load conductors from an existing 480 V low voltage switchgear assembly cable compartment.

The work permit was very detailed and included tools planned for use in the project and required PPE for workers performing the task based on the incident energy defined by a recently completed arc flash hazard assessment. The defined task for the work order required the site contractor to use a nylon rope, which was typical with this type of project, disconnecting the de-energized cables and working to raise them from the top cable compartment. Figure 10 showsa layout of the low voltage assembly involved in the work.

The de-energized cables were to be removed from Cubicle 5, with still energized conductors existing in Cubical 4 at the bottom of the cable wireway. The rope used was not able to grab the conductors and would slip off of the cable, so the electrical contractor elected to employ a “come along” to assist in the removal, as the come along could apply more force. The first conductor was successfully removed with this new tool. Upon removing the second conductor, a small arc flash was observed in the lower compartment. Simultaneously, the lights to the plant went out.The contractor stopped work and waited for plant electricians to arrive, not knowing what had just occurred.

The event caused the entire plant to shut down, stopping work on the project until an analysis could be completed. It was determined that the chain of the come along had drifted below where the work was being performed and into energized Cubicle 4. Fortunately, the damage to the wall of the switchgear and come along tool was minimal, which is shown in Figure 11.

Post event analysis proved that the chain of the come along had drifted below where the work was being performed and into an energized cubicle. The chain touched an energized terminal and arced to ground, touching both phase conductor and cabinet ground metal below the non-energized cubicle where the electrician was working. After reviewing minimal damage and completing the project while de-energized, the plant switchgear was cleaned and re-energized. Fortunately, total downtime for the plant due to this event was minimal. No loss of equipment or injury to any employee occurred as a result of this event.

 

Eaton Arc Flash Safety

 

Low voltage assembly involved in planned energized work. The planned task included removing cables from de-energized Cubicle 5 while Cubical 4 in an adjacent section was still energized.

The important take-away here is that the arc flash study was completed before energized work was performed. The upstreamlow voltage power circuit breaker with a special maintenance switch setting discussed previously employed technology to clear the fault faster than the microprocessor instantaneous setting of the circuit breaker trip unit.

Calculations were previously performed that quantified a reduction in incident energy from 17.7 cal/cm2 to2.9 cal/cm2 using the special maintenance setting. Both workersand equipment were saved as a result of a total clearing time at 40 milliseconds as defined by the manufacturer’s published trip curves[8].

Lessons learned

This case study unequivocally proves that planning for the unplanned event can save lives. Some of the key lessons learned here:
• mistakes will happen on even the best planned projects. A change in tools is what led to this arc flash event
• proper planning and leveraging of all accessible resources prevented what could have been a catastrophic event
• leveraging technology can often deliver a reduction in the available energy. Using more sensitive settings can save both people and equipment should an arc flash event occur

Eaton Come Along

At left, a “come along” tool used for energized work and at right, damage to panel after phase to ground arc flash event with an upstream device with maintenance setting capabilities.

This case study is one of four published online by Eaton and has been lightly edited by EIN. See all case studies: http://www.eaton.com/ecm/groups/public/@pub/@eaton/@corp/documents/content/pct_1562591.pdf.

 

Related Articles


Latest Articles

  • Industry Optimism and Growth: Looking Back on the Hong Kong International Outdoor and Tech Light Expo

    Industry Optimism and Growth: Looking Back on the Hong Kong International Outdoor and Tech Light Expo

    December 2, 2024 By Elle Bremmer Attracting more than 50,000 buyers from around the world, the 26th Hong Kong International Lighting Fair (Autumn Edition) and the 9th Hong Kong International Outdoor and Tech Light Expo was by all definitions, a success. The twin fair events, which were organized by the Hong Kong Trade Development Council… Read More…

  • What Is Corrosion and Why Does VpCI® Help?

    What Is Corrosion and Why Does VpCI® Help?

    December 2, 2024 Rust is a familiar sight for most of us. Rusty cars, rusty nails, rusty locks, and other forms of corrosion are part of everyday life, causing assets to lose their value and functionality. But while the problem is obvious, the cause and the solution are less apparent to most. However, understanding the… Read More…

  • IHSA: Workplace Mental Health Toolkits

    IHSA: Workplace Mental Health Toolkits

    December 1, 2024 IHSA is committed to supporting employers and workers with their occupational health and safety needs. That includes psychological health and safety—a growing and critically important area for workplaces to address. In the sections below, you will find tools, resources, education, and supports from IHSA and our health and safety system partners. They… Read More…

  • New Research on Smart Home Trends & Technology Adoption

    New Research on Smart Home Trends & Technology Adoption

    December 1, 2024 Entertainment systems are becoming a common entry point for smart home technology, with 61% of adopters using smart TVs, displays, or speakers. So says a new consumer research report from the Association for Smart Homes & Buildings (ASHB) that explores the perceptions, preferences, pain points, and challenges of residential renters and owners… Read More…


Changing Scene

  • Legrand Acquires Power Bus Way, a Leading Provider of Fully Customized Power Feeder Systems for Data Center, Industrial and Large-scale Commercial Applications

    Legrand Acquires Power Bus Way, a Leading Provider of Fully Customized Power Feeder Systems for Data Center, Industrial and Large-scale Commercial Applications

    December 3, 2024 Legrand® has announced it has acquired Power Bus Way, a Toronto-based premier provider of custom-designed cable bus solutions for data centers, industrial facilities and commercial projects. Due to increasing demand for more digital infrastructure, Legrand estimates the North American data center market will continue to grow. This accelerated growth is further bolstered by… Read More…

  • Procore Drives Connected Construction Innovation at Groundbreak 2024

    Procore Drives Connected Construction Innovation at Groundbreak 2024

    December 2, 2024 Procore Technologies wrapped up Groundbreak 2024 last month. Procore is unveiled Resource Management, the industry’s first all-in-one solution for comprehensive labor, equipment and materials tracking and planning, along with new AI-powered Scheduling and Safety tools that enhance efficiency and streamline safety management. “Construction is one of the most complex industries in the world,… Read More…

  • Applications Now Open for Next Round of Onatario Skills Development Fund

    Applications Now Open for Next Round of Onatario Skills Development Fund

    December 1, 2024 The Ontario government has launched the second round of its Skills Development Fund (SDF) Capital Stream, with over $74 million in available funding to build, expand and retrofit training facilities for workers in the trades, including construction, manufacturing, technology and health care. Since the province launched the Skills Development Fund in 2021, Ontario is… Read More…

  • New Alberta Industry Skills Grant

    New Alberta Industry Skills Grant

    December 1, 2024 Alberta’s government continues to find creative ways to help employers find the qualified workers they need, especially in industries experiencing labour shortages. The new Alberta Industry Skills Grant will fund industry-led training in high-demand sectors like aviation, aerospace, construction and tech. Alberta’s government is making $5 million available through a pilot program… Read More…