Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • SurgePure Corporation Expands into the Mid-West with New Representation Partner, Advance Electrical Agency

    SurgePure Corporation Expands into the Mid-West with New Representation Partner, Advance Electrical Agency

    August 1, 2025 SurgePure Corporation is proud to announce its new partnership with Advance Electrical Agency, who will represent the company across Saskatchewan, Manitoba, and Western Ontario. Led by principals Darren Churchwell and Bob Fiesel , the Advance team is part of a well-established agency known for representing some of the most respected manufacturers in… Read More…

  • Munden Partners with Valid Manufacturing in Atlantic Canada

    Munden Partners with Valid Manufacturing in Atlantic Canada

    August 1, 2025 Munden Enterprises has announced that they are back in the custom enclosure business through a new partnership with Valid Manufacturing Ltd. Expect Canadian-made, engineered solutions for industrial, utility, transportation, wastewater, renewables, and beyond. Whether you need a bare enclosure or a fully assembled panel, Munden is here to help. Reach out to… Read More…

  • JEHS Joins Forces with NOARK to Deliver Smarter Electrical Solutions in Ontario

    JEHS Joins Forces with NOARK to Deliver Smarter Electrical Solutions in Ontario

    August 1, 2025 NOARK Electric is pleased to announce a new partnership with Cambridge, Ontario based manufacturing representitive, JEHS. This strategic collaboration will expand NOARK’s reach and customer support across Ontario and beyond, bringing reliable and innovative electrical solutions to a wider audience. With over 50 years of combined sales experience, JEHS brings a strong… Read More…

  • BC Hydro Making it Easier and More Affordable to Connect New Homes

    BC Hydro Making it Easier and More Affordable to Connect New Homes

    July 24, 2025 BC Hydro is supporting the construction of new housing developments in growing communities by advancing changes to streamline upgrades and reducing the cost of new customer connections to BC Hydro’s electricity grid. “As communities across B.C. grow, so does the need for essential housing. We are committed to ensuring we’re ready to… Read More…