Guide to the Canadian Electrical Code, Part I — Instalment 18

November 7, 2016 

By William (Bill) Burr

In this article: Section 32 — Fire Alarm Systems, Fire Pumps, and Carbon Monoxide Alarms. The code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 32, as outlined in rule 32-000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection of fire alarm systems, fire pumps and smoke and carbon monoxide alarms required by the National Building Code of Canada as referenced in Appendix G. For further information, refer to Canadian Standard CAN/ULC – S524 Standard for the Installation of Fire Alarm Systems published by ULC Canada. Appendix B contains important additional helpful notes, and the CEC Handbook also contains helpful information.

Fire alarm systems

Rule 32-100 specifies the requirements for conductors in fire alarm systems, which include copper material, ampacity, use of optical fibre cables, use of stranded conductors, insulation rated at 300 volts, determining wire size for raceways or integral assemblies, and selection in accordance with rules 4-008(1) or 4-020(1).

Rule 32-102 outlines wiring methods for installation of conductors either in metal, non-metallic raceway, or having a metal armour or sheath. Where installed in buildings of combustible construction, conductors may be installed in accordance with Section 12. Conductors need to be installed independent of any other wiring except for point of supply, signal, ancillary device or communication circuits and must be insulated for the highest voltage rated conductor. Communication circuits must conform to Section 60.

Rule 32-104 requires that all exposed non-current-carrying parts of electrical equipment be bonded to ground in accordance with Section 10. In addition, non-metallic fire alarm wiring systems must incorporate a bonding conductor.

Rule 32-106 denotes that for electrical supervision, each circuit conductor terminal shall be independently terminated.

Rule 32-108 specifies that the fire alarm system power supply, except for included additional control units or transponders, be on a separate circuit and that the overcurrent devices and disconnecting means be permanently identified as a fire alarm system, be coloured red, and lockable in the on position.

Rule 32-110 provides installation requirements for permanently connected smoke alarms and carbon monoxide alarms in dwelling units that are required by the National Building Code of Canada (see Appendix G). The rule requires that smoke and carbon monoxide alarms be supplied from a circuit, such as a lighting only or mixed lighting and receptacle circuit, that will provide an indication if shut off. The circuit shall also have no disconnect or a GFCI or AFCI device between the alarms and the branch circuit overcurrent device. Interconnection of alarms may use a class 2 power supply in accordance with Rules 12-506 to 12-524.

Fire pumps

Rule 32-200 requires that conductors for the supply of a fire pump supplied from the emergency power source have an ampacity not less than 125% of the full load current rating of the motor or sum of multiple motors and auxiliary motors, and be protected from fire exposure to provide continuing operation during a fire as required by the National Building Code of Canada (see Appendix G).

Rule 32-202 outlines the requirements for wiring methods of fire pumps to be installed in metal raceways, in armour or metal sheathed cable, selected in accordance with Rule 4-888(1), in rigid non-metallic conduit embedded in concrete, or electrical non-metallic tubing embedded in concrete.

Rule 32-204 provides that a separate service box for a fire pump and equipment may be installed in conformance with rule 32-206 below and, notwithstanding rule 6-102(2), may be located remote from other service boxes.

Rule 32-206 requires that no disconnecting means, overcurrent protection or device capable of interrupting the fire pump circuit may be placed between the service box and the fire pump transfer switch or controller, except a circuit breaker that is permanently labelled identifying it as a fire pump disconnect. In addition, the circuit breaker must be lockable in the closed position and may be in the separate service box as in rule 32-204 above. In the case where this circuit breaker is installed in an emergency power supply circuit between the emergency power source and the fire pump transfer switch, the rating of the circuit breaker shall be as per rule 28-200. Where it is installed in a normal supply circuit the rating should be not less than the overcurrent protection of the fire pump controller.

Rule 32-208 requires that where an on-site electrical transfer switch is used to provide emergency power supply to a fire pump, it must be provided solely for the fire pump, located in a barriered or separate compartment or enclosure, permanently labelled as the fire pump power transfer switch, and approved for fire pump service. Where more than one fire pump is provided, a transfer switch is required for each fire pump.

Rule 32-208 provides that overload and overheating protection for branch circuit, control or equipment conductors shall not be required but shall be protected by the motor branch circuit overcurrent device.

Rule 32-210 specifies that ground fault protection shall not be installed in a fire pump circuit.

In the next instalment, we will be discussing Section 34 – Signs and Outline Lighting.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting, billburr@gmail.com.

Related Articles


Latest Articles

  • New STANDATA Interpretation & Variance: Use of Neutral Conductors in Consumer’s Service Reporting of Electrical Incidents

    New STANDATA Interpretation & Variance: Use of Neutral Conductors in Consumer’s Service Reporting of Electrical Incidents

    October 6, 2025 There are two new STANDATA releases for the province of Alberta: The purpose of these two releases is to clarify requirements for reporting electrical incidents in Alberta and to permit the use of underground service entrance cable (USEB) with a bare neutral conductor in underground installations at service entrance equipment. STANDATA variance… Read More…

  • BizEnergySaver Program Available in Toronto & Ottawa

    BizEnergySaver Program Available in Toronto & Ottawa

    October 6, 2025 Commercial buildings in Ottawa and Toronto’s Richview South area can receive direct installation and instant discounts on energy-saving equipment upgrades for lasting benefits. The Save on Energy BizEnergySaver program is designed to help industrial, commercial and institutional (ICI), and multi-residential building owners and operators make equipment improvements to reduce their energy consumption…. Read More…

  • Electrical Industry Day of Recognition – October 6, 2025: John’s Story

    Electrical Industry Day of Recognition – October 6, 2025: John’s Story

    October 6, 2025 The Electrical Injury Day of Recognition is sponsored by the Electrical Contractors Association of Alberta, the Canadian Electrical Contractors Association, the Electrical Contractors Association of British Columbia, and the National Electrical Trade Council. The Canadian electrical industry is calling on all tradespeople and those who benefit from them, to set aside October 6 as a day… Read More…

  • Research Report: Visible and Invisible Consequences of Electrical Injury

    Research Report: Visible and Invisible Consequences of Electrical Injury

    October 6, 2025 This report was produced by the Infrastructure Health & Safety Association (ISHA). You can find the report, as well as sources on their website. This report has been written by Dr. Manuel Gomez, director of the St. John’s Rehab Research Program at Sunnybrook Health Sciences Centre in Toronto. Electricity is an important… Read More…


Changing Scene

  • Ontario Takes Next Step in Bowmanville Hospital Expansion

    Ontario Takes Next Step in Bowmanville Hospital Expansion

    October 6, 2025 The Ontario government is marking a key milestone in delivering high-quality hospital care for families in Durham Region by issuing a Request for Proposals (RFP) to select the team that will lead the expansion and revitalization of Lakeridge Health’s Bowmanville Hospital. This project will mark one of the largest redevelopments at Lakeridge… Read More…

  • Nova Scotia Takes Further Steps to Unlock Development in Halifax

    Nova Scotia Takes Further Steps to Unlock Development in Halifax

    October 6, 2025 Nova Scotia is taking more action to support housing growth in Halifax Regional Municipality (HRM), issuing new orders and moving policies forward. The measures include Municipal Affairs Minister John Lohr designating HRM as an interim planning area. Under this order, new minimum planning requirements for HRM take effect immediately. The designation also enables… Read More…

  • E.B. Horsman & Son Announces Stephen Murray as New Calgary Branch Manager

    E.B. Horsman & Son Announces Stephen Murray as New Calgary Branch Manager

    October 6, 2025 EB Horsman & Son is pleased to announce the appointment of Stephen Murray as Branch Manager of its Calgary location, effective Tuesday, September 3, 2025. Stephen Murray brings over two decades of experience in the industrial automation sector, where he has built a strong reputation for driving growth, expanding market presence, and… Read More…

  • E.B. Horsman & Son Announces Maxim Laberge as New Process Instrumentation Manager

    E.B. Horsman & Son Announces Maxim Laberge as New Process Instrumentation Manager

    October 6, 2025 EB Horsman is excited to welcome Maxim Laberge as its new Process Instrumentation Manager. Maxim Laberge brings over 25 years of experience in electrical, instrumentation, and control systems, with a proven record in business development, client engagement, and strategic project leadership. He is known for his consultative approach, combining technical insight with… Read More…