PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • CAF-FCA Provides Recomendations on Apprenticeship Investment

    CAF-FCA Provides Recomendations on Apprenticeship Investment

    April 13, 2025 CAF-FCA have provided an outline of actionable recommendations—developed through national consultation—to enhance accessibility, reduce financial barriers, and better align apprenticeship training with industry needs. Source Read More…

  • New Report: Preparing Alberta’s Buildings for Severe Weather

    New Report: Preparing Alberta’s Buildings for Severe Weather

    April 13, 2025 Alberta is facing more severe weather events, with rising temperatures, wildfires, and more frequent extreme storms threatening homes and businesses. Our report, Preparing Alberta’s Buildings for Severe Weather−written in partnership with the Alberta Ecotrust Retrofit Accelerator program−highlights the need for deep retrofits to ensure the province’s buildings can withstand these changing conditions. Four… Read More…

  • CCA Bulletin: Managing Tariff Risks in Construction Projects

    CCA Bulletin: Managing Tariff Risks in Construction Projects

    April 13, 2025 This bulletin was prepared by select members of the Canadian Construction Association’s (CCA) General Contractors National Advisory Council. Its purpose is to assess the potential impacts of tariffs and counter-tariffs on general contractors in Canada focusing specifically on: In both areas, the bulletin explores both upstream and downstream impacts – examining how… Read More…

  • Video: ABB Installation Products Proudly Powering Canada

    Video: ABB Installation Products Proudly Powering Canada

    April 7, 2024 From coast to coast, ABB Installation Products is built by Canadians, for Canadians—delivering high-quality solutions that power industries and support communities across the country. Read More…


Changing Scene

  • PEI’s First Net Zero Ready School Officially Opens

    PEI’s First Net Zero Ready School Officially Opens

    April 13, 2025 Island students, their families and the Sherwood school community came together today to celebrate the opening of PEI’s first net zero ready school. The new Sherwood Elementary School, built next to the former school, offers over 82,000 square feet of space with many innovative features to promote enhanced learning experiences for up… Read More…

  • Nova Scotia Invests to Connect Nova Scotians to Skilled Trades

    Nova Scotia Invests to Connect Nova Scotians to Skilled Trades

    April 13, 2025 The Province is helping more Nova Scotians explore and connect to careers in skilled trades through a $10-million investment in the construction industry. The investment will support more skilled trades training through three key initiatives: “Nova Scotia needs more skilled trades professionals to support our growing economy and to build the homes,… Read More…

  • PEI Tables Bill Aimed to Eliminate Trade and Labour Barriers

    PEI Tables Bill Aimed to Eliminate Trade and Labour Barriers

    April 13, 2025 Hon. Rob Lantz, Premier of Prince Edward Island, introduced the Interprovincial Trade & Mobility Act in the provincial legislature. This bill will allow Prince Edward Island to eliminate unnecessary barriers to trade and labour mobility with reciprocating jurisdictions.   The Bill will accept provincial inspections and standards on goods coming from a… Read More…

  • PEI Minimum Wage Set to Increase

    PEI Minimum Wage Set to Increase

    April 13, 2025 Minimum wage in Prince Edward Island will increase incrementally to $17 per hour by April 1, 2026.  The Employment Standards Board reviews minimum wage annually and provides their recommendation to government.  Go HERE for more information Source Read More…