Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • Saskatchewan and Ontario Breaking Down Trade Barriers

    June 9, 2025 Saskatchewan Premier Scott Moe and Ontario Premier Doug Ford signed a Memorandum of Understanding (MOU) to collaborate on the removal of trade barriers across the two jurisdictions. “Now is the time to take strong action to strengthen trade across Canada,” Moe said. “Our province remains committed to removing restrictive barriers that limit… Read More…

  • Aberta and PEI Sign Free Trade Agreements with Ontario

    June 9, 2025 Premier Doug Ford was joined by Alberta Premier Danielle Smith and Prince Edward Island Premier Rob Lantz to sign Memorandums of Understanding (MOUs) that will help grow all three provincial economies by advancing efforts to knock down barriers to trade across Canada. “With President Trump threatening our economy, there’s never been a… Read More…

  • Ontario Rewards Toronto With $67.2 Million Through the Building Faster Fund

    Ontario Rewards Toronto With $67.2 Million Through the Building Faster Fund

    June 9, 2025 As part of its record-breaking investments in housing-enabling infrastructure, the Ontario government is awarding $67,199,200 to the City of Toronto through the second round of the Building Faster Fund, which provides funding to municipalities that achieve at least 80 per cent of their provincially designated housing targets. Toronto broke ground on 20,999… Read More…

  • LEDVANCE Expands Ontario Presence with New Specification Agent

    LEDVANCE Expands Ontario Presence with New Specification Agent

    June 9, 2025 LEDVANCE Ltd. is pleased to announce the appointment of Sterling Architectural Products Ltd. (Sterling Lights) as our new specification agent in Ontario. This partnership strengthens our presence in the region and reinforces our commitment to serving the professional lighting design and specification community with innovative, reliable lighting solutions. “We are very excited… Read More…