Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • Thermon Expands Electric Heater Offering Through Aquisition of F.A.T.I.

    Thermon Expands Electric Heater Offering Through Aquisition of F.A.T.I.

    October 25, 2024 Thermon has announced the acquisition of Fabbrica Apparecchiature Termoelettriche Industriali S.r.L. (F.A.T.I.), a manufacturer of electric heaters for industrial applications, based in Milan, Italy. F.A.T.I. is a leading designer and manufacturer of electrical heaters and heating systems for a broad range of industrial end markets, including oil & gas, pharmaceutical, renewables, nuclear… Read More…

  • CDM2 Partners with ELEC-TECH Sales to Expand Emergency Lighting Solutions Across BC

    CDM2 Partners with ELEC-TECH Sales to Expand Emergency Lighting Solutions Across BC

    October 25, 2024 CDm2 LIGHTWORKS is pleased to announce a strategic partnership with Elec-Tech Sales to bring ABB LUMACELL emergency lighting products and systems into their diverse application-driven solutions. “This partnership with Elec-Tech Sales strengthens our ability to deliver a robust portfolio of integrated lighting, controls, and electrical solutions,” noted Darren Luce, President + Principal of CDm2 LIGHTWORKS. “Together,… Read More…

  • Manitoba Government Introduces Legislation to Help Build New Housing Faster

    Manitoba Government Introduces Legislation to Help Build New Housing Faster

    October 25, 2024 The Manitoba government has introduced amendments to the Planning Act and the City of Winnipeg Charter Act that would change the appeals process for zoning changes by removing a requirement that made it difficult for municipalities to change local zoning bylaws and allowing faster new housing construction, Municipal and Northern Relations Minister… Read More…

  • Piloting New Ways to Make Homes More Energy-Efficient and Affordable

    Piloting New Ways to Make Homes More Energy-Efficient and Affordable

    October 22, 2024  Canada’s buildings sector is the third-largest contributor to greenhouse gas emissions across the country.  We must increase the scale and pace of retrofitting buildings across the country to make them more energy-efficient, increasing savings and reducing emissions. A federal investment totalling $4.3 million has been announced for five projects funded under the Greener Neighbourhoods Pilot Program (GNPP)… Read More…