PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles


Changing Scene

  • Mac’s II Agencies Strengthens Lighting Division

    Mac’s II Agencies Strengthens Lighting Division

    March 19, 2025 Mac’s II Agencies Announces Jamie Capell as the New Sales Manager for Lighting Specification Mac’s II Agencies is pleased to announce the expansion of its lighting division with the addition of Jamie Capell as the Sales Manager for Lighting Specification. Jamie brings 25 years of experience in the lighting and electrical industry, most notably… Read More…

  • RENO Lighting Announce New Vice President of Sales

    RENO Lighting Announce New Vice President of Sales

    March 19, 2025 It is with great excitement that RENO introduce Jean-Claude Lespérance as Vice President of Sales at RENO Lighting. With over 35 years of experience in the Canadian electrical industry, Jean-Claude brings unrivalled knowledge of the market and strong relationship with key industry stakeholders, suppliers, and customers. Holding a college diploma in Electrodynamics… Read More…

  • Canada Invests in Deep Energy Retrofits for Affordable Housing in Hamilton

    Canada Invests in Deep Energy Retrofits for Affordable Housing in Hamilton

    March 13, 2025 There is a need and an opportunity for Canada to strengthen energy security and affordability for all Canadians. Canada’s buildings sector is the third-largest contributor to greenhouse gas emissions across the country. By increasing the scale and pace of building retrofits, we can make homes and buildings more energy-efficient and improve reliability in units.  The federal… Read More…

  • Tesla Products Excluded from BC Hydro Incentive Program

    Tesla Products Excluded from BC Hydro Incentive Program

    March 13, 2025 CBC has reported that BC Hydro is excluding Tesla products from their EV charger incentive program. However, products purchased prior to March 12 will still be eligible. “As of March 12, Tesla chargers, energy storage batteries and inverters are not eligible for rebates, according to B.C. Hydro. Those who have purchased or… Read More…