PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles


Changing Scene

  • Mattr Completes Acquisition of AmerCable, Establishing US Wire and Cable Manufacturing Footprint

    Mattr Completes Acquisition of AmerCable, Establishing US Wire and Cable Manufacturing Footprint

    January 10, 2025 Mattr Corp. has announced that it has closed its previously announced acquisition of AmerCable Incorporated [see press release], which now forms part of Mattr’s Connection Technologies reporting segment. Under the terms of the transaction, Mattr has acquired all of the outstanding shares of AmerCable from Nexans USA Inc. for a purchase price… Read More…

  • Ontario Launches New Energy Efficiency Programs

    Ontario Launches New Energy Efficiency Programs

    January 10, 2025 The Ontario government is launching new energy efficiency programs, including the new Home Renovation Savings Program. The programs are part of a new $10.9 billion, 12-year investment in energy efficiency. The new Home Renovation Savings Program will launch on January 28, 2025, and offer rebates of up to 30 per cent for home energy… Read More…

  • The Government of Yukon Pauses the Affordable Heat Pump Program Due to High Demand

    The Government of Yukon Pauses the Affordable Heat Pump Program Due to High Demand

    January 9, 2025 The Affordable Heat Pump Program (AHPP) is fully subscribed through 2025, with 84 households receiving heat pumps through the program since the program launched on December 19, 2024. The rapid uptake of the program exceeded expectations, demonstrating Yukoners’ interest in switching to more efficient electric heating sources that result in lower utility… Read More…

  • Jesse Spring of Primary Engineering and Construction Named EHRC 2024 Leader of the Year

    Jesse Spring of Primary Engineering and Construction Named EHRC 2024 Leader of the Year

    January 6, 2025 Electricity Human Resources Canada (EHRC) is thrilled to announce Jesse Spring, CEO of Primary Engineering and Construction, as the recipient of the 2024 Leader of the Year Award. EHRC proudly recognizes Jesse for his leadership, which is built on excellence and powering growth. Jesse’s journey with Primary began in 2008 as an… Read More…