Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • Mac’s II Agencies Re-Envisions EV Charging Solutions with Two Leading Brands

    Mac’s II Agencies Re-Envisions EV Charging Solutions with Two Leading Brands

    April 9, 2026 Mac’s II Agencies has announced a strategic revision of its electric vehicle charging portfolio with the addition of Wallbox, and an expanded partnership with RVE. These partnerships position Mac’s II Agencies to deliver end-to-end EV charging solutions for residential developments and commercial applications throughout British Columbia and Yukon in a whole new way. Since Read More…

  • EB Horsman Introduces New Lower Mainland District Manager

    EB Horsman Introduces New Lower Mainland District Manager

    April 9, 2026 EB Horsman is pleased to announce the appointment of Shane Smith as Lower Mainland District Manager, effective April 1, 2026. With nearly two decades of experience at EB Horsman & Son, Shane has built a strong foundation across multiple areas of the business. Since joining the company in 2007, he has progressed Read More…

  • Nominations are Open for NETCO 2026 Leadership Excellence Award

    Nominations are Open for NETCO 2026 Leadership Excellence Award

    April 9, 2026 NETCO is pleased to announce that nominations are now open for the 2026 Leadership Excellence Award. Established in 2016, this national award recognizes an individual who has made outstanding contributions to apprenticeship training and continuing electrical training across Canada. The recipient is honoured annually at the NETCO National Training Conference. NETCO are seeking nominations for Read More…

  • Bartle & Gibson Announces New Partnership with Eaton

    Bartle & Gibson Announces New Partnership with Eaton

    April 9, 2026 Bartle & Gibson Co. Ltd., an Alberta-based premier distributor of plumbing, heating, and electrical products, and Eaton Industries (Canada) Company have announced a new regional partnership that expands access to Eaton’s electrical solutions across Western Canada. This agreement enables customers throughout the Western provinces to procure a broad range of Eaton products, Read More…