EIN Bill Burr Code 400Section 36 – High Voltage Installations applies to installations operating above 750 volts, which require special rules and conditions because high voltage arcs can travel through free air and along the surface of some materials. In addition, non-current-carrying metal parts can carry dangerous voltages along their surfaces in a ground-fault situation without effective bonding to ground.

General requirements

Rule 36-000 Scope — this is a supplementary or amendatory section of the code and applies to all electrical installations operating above 750 volts. Note that the rules of the code for installations operating at 750 volts or less also apply. The Scope also mandates that the supply authority and the inspection department be consulted before commencing any installation covered by this section. Also noted is that the rules of this section do not affect factory assembled equipment approved under the Canadian Electrical Code, Part II standards. Refer to Appendix B and the CEC Handbook for additional information.

Rule 36-002 denotes some special terminology that applies to this section — Boundary fence, Ground grid conductor, Maximum ground fault current, Potential rise of ground grid, Station, Step voltage, and Touch voltage. The CEC Handbook contains an explanation of touch and step voltages with good diagrams. In addition, see Table 52.

Rule 36-004 Guarding — requires that the live parts of high-voltage electrical equipment shall only be accessible to authorized persons.

Rule 36-006 Warning Notices — specifies the required wording, specifications and various locations where warning notices and signs are required.

Wiring methods

Rule 36-100 Conductors — stipulates that bare or insulated conductors not enclosed in grounded metal must be used only

• outdoors

• in electric equipment vaults in accordance with Rules 26- 350 to 26-356

• in cable trays in accordance with Rule 12- 2202, or

• in service rooms accessible only to authorized persons

That insulated conductors or cables used indoors or attached to buildings outdoors shall be

• installed in metal conduit

• installed in electrical metallic tubing

• installed as metal-enclosed busways

• cables with a continuous metal sheath, steel wire armour, or of the interlocking armour type, or

• Type TC tray cable installed in cable tray in accordance with Rule 12- 2202

High-voltage TC cables installed in the same tray with low-voltage conductors must have

• a metal barrier not less than 1.34 mm thick separating them

• permanent marking of the location of conductors imbedded in concrete or masonry

• conductive coverings stripped back from terminals to prevent current leakage

• a minimum mechanical strength of #6 AWG for service conductors

Rule 36-102 Radii of Bends — notes that the minimum bending radii for cables must conform to Table 15.

Rule 36-104 Shielding of Thermoset Insulated Conductors — high-voltage cables with thermoset insulation operating at more than 2000 volts must have a metallic shield layer over the insulation, bonded to ground in accordance with Rule 10-304 to equalize the dielectric stress on the insulation layer, except where the conductors meet the conditions outlined in sub rules (2), (3), and (4). Appendix B provides additional information.

Rule 36-106 Supporting of Exposed Conductors — conductors not enclosed in grounded metal must be sufficiently insulated from their supports to withstand any stresses imposed by a possible short circuit in the supply system.

Rule 36-108 Spacing of Exposed Conductors — conductors and other bare live parts must conform to the spacing outlined in Tables 30 and 31. Where the conductors are connected to terminals with less spacing, they are required to meet the required spacing at the first support point.

Rule 36-110 Guarding of Live Parts and Exposed Conductors — conductors not in contact with grounded metal and bare live parts must be accessible only to authorized persons, and isolated by elevation or barriers in accordance with Tables 32, 33, and 34. For voltages more than these tables and for conductors crossing highways, railways and communication lines, use the requirements in CAN/CSA-C22.3 No.1. Where a span following Table 34 exceeds 50 meters, increase the clearance by 1% of the excess.

Rule 36-112 Terminating Facilities — where cables are terminated they must be protected from moisture or mechanical damage.

Rule 36-114 Joints in Sheathed Cables — where sheathed cables are spliced or tapped, the covering insulation and shielding must be electrically and mechanically equivalent to that on the conductors or cables. In addition, the continuity of any bonded metal or conducting sheath must be maintained or the joint must be made in a suitable splicing box that maintains the bonding path continuity.

Rule 36-116 Elevator Shafts — high-voltage insulated conductors or cables are not permitted in elevator shafts unless installed in conduit imbedded in and surrounded by not less than 50mm of masonry or concrete.

Rule 36-118 Conductors over Buildings — states that high voltage conductors shall not be installed over buildings.

Control and protective equipment

Rule 36-200 Service Equipment Location — as per Rule 6-206, service equipment must comply with the location requirements of the supply authority and be at the service entrance point either inside the building or in an outdoor fenced switch yard.

Rule 36-202 Rating and Capacity — it is important that the type and ratings of circuit breakers, fuses and switches are sufficient to provide protection and current-limiting from the high levels of energy during a short circuit. Compliance with Rule 14-012, the requirements of the supply authority, and the rules for other electrical equipment is required.

Rule 36-204 Overcurrent Protection — all ungrounded conductors must have overcurrent protection by a circuit breaker or fuse having adequate rating and interrupting capacity. Fuses must be accessible to authorized persons only and be preceded by a group-operated visible break load-interrupting device or visible break air-break device that may be closed, with safety to the operator, with a fault on the system.

Rule 36-206 Indoor installation of Circuit Breakers, Switches, and Fuses — these must be totally enclosed or installed in an area with non-combustible construction, and for dielectric liquid-filled equipment must conform to Rule 26-012.

Rule 36-208 Interlocking of Fuse Compartments — to prevent access to energized fuses, the cover or door of the fuse compartment must be interlocked with the isolating means so that there is

• no access to the fuses unless the isolating or disconnecting means immediately ahead of the fuses is in the de-energized position

• no access to the fuses where the fuses may be energized from either side, unless the isolating or disconnecting means on both sides of the fuses are in the de-energized position

• no possibility to place the switch into the closed position until the fuse compartment has been closed and the interlock re-engaged

Rule 36-210 Protection and Control of Instrument Transformers — in addition to complying with Rule 26-262, instrument voltage transformers must have a disconnecting means on the supply side of the fuses.

Rule 36-212 Outdoor Installations — field assembled high-voltage switches and fuses must conform to the spacing outlined in Table 35. Horn-gap switches must be mounted horizontally and be capable of being locked in the open position.

Rule 36-214 Disconnecting Means — a load breaking device is required wherever high-voltage insulated conductors or cables fed from a station enter a building.

• It must be located either

- at the entry of the insulated conductors or cable into the building, or

- at the supply station, and

- be capable of being operated from within the building.

• Except where the load breaking device is the draw-out type, the contacts must be visible for inspection in the open position.

• It must also be provided with a group-operating isolating switch on the supply side that provides

- visible inspection of the contacts in the open and closed position

- interlocking to prevent operation under load

- positive indicators of position

• Where there is more than one source of voltage or possibility of feedback in a station, the visibility of contacts, as above, must be provided in all circuits where a feedback could occur. The Appendix B note provides a further explanation in understanding this concept.

Grounding and bonding

Rule 36-300 Material and Minimum Size of Grounding Conductors and Ground Grid Conductors and Connections – conductors ideally should be copper and sized per Rules 36-302 to 36-310 and Table 51. Materials other than copper can be used if

• the current carrying capacity is equal or greater than that specified for copper conductors

• consideration is given to galvanic action when buried in ground or in contact with dissimilar metals

• methods of connecting maintains the required current-carrying capacity of the connection for the life of the electrode design

Reference should also be made to IEEE 80, IEEE 837 and CSA C22.2 No. 41 for additional information.

Rule 36-302 Station Ground Electrode — provides the specifications for constructing a station ground electrode either outdoors or indoors to meet the requirements of Rule 36-304.

Rule 36-304 Station Ground Resistance — outlines the specifications necessary to provide the maximum permissible resistance of the station ground electrode, to limit the potential rise of all parts of the station ground grid to 5000 volts and to the tolerable step and touch voltages specified in Table 52. In special circumstances, in accordance with Rule 2-030, higher voltage rise may be permitted up to the insulation level of communication equipment.

Rule 36-306 Station Exemption — provides exemption from conducting soil resistivity, analysis of touch and step voltages or measurement of resistance of the station ground electrode or touch voltage near the ground electrode where the phase-to-phase voltage is less than 7500 volts, the ground surface covering meets Rule 36-304(5), and the ground potential rise (GPR) will not exceed touch and step voltages in Table 52.

Rule 36- 308 Connections to the Station Ground Electrode — requires that all non-current carrying metal equipment and structures forming part of the station must be grounded to the station ground electrode, and provides the sizes of grounding conductor and methods of connection of various items.

36-310 Gang-operated Switch Handle Grounds — provides methods for grounding of switches to the ground electrode and requirements for a metallic gradient control mat to maintain the touch voltage to Table 52 tolerances.

36-312 Grounding of Metallic Fence Enclosures of outdoor stations — specifies the location of the fence and the various points and methods of connection of parts of it to the station ground electrode, and requires that:

• touch voltages within 1 meter of a boundary fence, located close to the station fence, must not exceed the tolerable values of Table 52 (the CEC Handbook provides several good diagrams showing effective connections to the station ground electrode)

• the station ground electrode must be connected to the fence by a tap conductor at

- each end post

- corner post

- gate post

- at intermediate posts at intervals not exceeding 12 m

by a conductor of not less than No. 2/0 AWG copper

• the tap conductor at each hinge gate post must be clamped or bonded to the gate frame by a copper braid or a flexible copper conductor of at least No. 2/0 AWG

• the tap conductor must be connected to

- the fence post

- the bottom tension wire

- the fence fabric (where the conductor may be woven in at least two places)

- the top rail

- each strand of barbed wire

with the connection to the bottom tension wire, the fence fabric, and barbed wire strands made with bolted or equivalent connectors, and with the top rail connections bonded at every joint by a jumper equivalent to No. 2/0 AWG copper. When there is a metal boundary fence in proximity to the station fence, the touch voltages within 1 m of all parts of the boundary fence shall not exceed the tolerable values specified in Table 52.

In the next installment, we will be discussing Section 38 – Elevators, Dumbwaiters, Material Lifts, Escalators, Moving walks, Lifts for Persons with Physical Disabilities, and Similar Equipment.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

* Source: CSA C22.1:21, Canadian Electrical Code, Part 1 - Safety Standard for Electrical Installations. © 2021 Canadian Standards Association. Please visit store.csagroup.org. With the permission of CSA Group, material is reproduced from CSA Group standard CSA C22.1:21, Canadian Electrical Code, Part 1 - Safety Standard for Electrical Installations. This material is not the complete and official position of CSA Group on the referenced subject, which is represented solely by the Standard in its entirety. While use of the material has been authorized, CSA Group is not responsible for the manner in which the data are presented, nor for any representations and interpretations. No further reproduction is permitted. For more information or to purchase standard(s) from CSA Group, please visit store.csagroup.org or call 1-800-463-6727.

It should be noted that the CEC Technical Committee has recently discussed and imminently approved an amendment to the definition of voltage in line with the IEC:

Extra-low voltage:

• for ac circuits, any voltage not exceeding 30 V ac

• for dc circuits, any voltage not exceeding 60 V dc

Low voltage:

• for ac circuits, any voltage exceeding 30 V but not exceeding 1000 V ac,

• for dc circuits, any voltage exceeding 60 V dc but not exceeding 1500 V dc.

High voltage:

• for ac circuits, any voltage exceeding 1000 V ac,

• for dc circuits, any voltage exceeding 1500 V dc.

This amendment will not be published until the 26th edition of the Code in 2024, hence one should confirm with the local Authority Having Jurisdiction whether these increased voltage levels should be observed in the meantime.

Five Tips to Find Time for Field Service Marketing

SimProTime is a precious resource that we all want more of. And if you own a field service business or work for one, you undoubtedly know how hard it is to find time for everything you need to accomplish in a workday, let alone a week, a quarter, or a year.

Like many of us, you do your best to check every item off of the to-do list during working hours while inevitably pushing lower priority items off to another day. And often, marketing your field service business is one of those things that easily falls to the wayside after being pushed back for more urgent matters.

Read More


Changing Scene

  • Prev
The federal governemnt has officially launched a call for proposals (CFP) for the  ...
The Electrical Contractors Association of BC (ECABC) has announced the impending departure of ...
The Minister of Employment, Workforce Development and Disability Inclusion, Carla Qualtrough was at ...
The launch of the Apprenticeship Service stands to help overcome financial barriers employers face ...
The National Electrical Trade Council (NETCO) is pleased to announce that they will be rolling out ...
43 years ago, Steve Silverstein bought a table saw and a delivery van and began a revolution in the ...
E.B. Horsman & Son (EBH) has announced their Victoria location will be officially moving to a ...
 The Maritime’s largest Mechanical and Electrical event took place last Wednesday and ...
IDEAL INDUSTRIES, INC. is calling all professional and student-apprentice electricians to come out ...
Vivi White has been appointed to the Board of Directors of the Electrical Safety Authority ...

Become a Wiser Approved Installer

Wiser Approved Installer

Get access to exclusive benefits, product discounts and resources that will help you drive more business, and lower energy bills for your clients.

 

 

 

Read More


 



Government of CanadaThe federal governemnt has officially launched a call for proposals (CFP) for the Zero-Emission Vehicle Awareness Initiative (ZEVAI). The initiative’s 2022 CFP will help fund new and innovative projects that aim to increase awareness and knowledge of ZEVs and charging and refueling infrastructure thereby increasing public confidence in these vehicles and their economic and environmental benefits.


Natural Resources Canada will provide funding through non-repayable contributions of between 50 and 75 percent of the total eligible project costs, with a maximum funding of up to $300,000 per project. The CFP will close on August 18, 2022.

Read more


 

Omnicable joins ETIMETIM North America announced that OmniCable has joined the product classification standards organization. Headquartered in West Chester, PA, OmniCable has 24 locations throughout North America, and also owns Houston Wire & Cable (HWC). The company partners with many electrical manufacturers and only sells to distributors.

According to John Dean, Director of Marketing & E-Commerce, OmniCable/HWC, “The wire and cable industry is often called commodities, but there are very distinct features and attributes for the different products our manufacturers produce. 

Read More

 


 

Atkore United Poly SystemsAtkore Inc. announced that it has acquired United Poly Systems, a manufacturer of High Density Polyethylene (HDPE) pressure pipe and conduit, primarily serving telecom, water infrastructure, renewables, and energy markets.

“We are pleased to complete the acquisition of United Poly Systems, which strengthens Atkore’s product portfolio, expands our manufacturing capacity and further enables us to meet HDPE customers’ needs,” stated John Pregenzer, President of Atkore’s Electrical business. “HDPE pipe and conduit is a growing market that is expected to benefit from U.S. infrastructure legislation, and United Poly Systems is a great addition to Atkore. We welcome these employees and look forward to working together to continue to serve and support our customers.”

Read More


 

Canadian Electrical Contractor Discussion Group: Can You Count the Deficiencies?

EIN CECD 400Have you ever been called to fix the work of a 'handyman'?

"Was supposedly done by a"certified ' electrician....told the homeowner that he got a $266 permit....no record at TSBC. Can you count the deficiencies?"

"There is a second panel change in the triplex also.......even more deficiencies. Think the guy was a glorified handyman. Ones not obvious: 240 BB heat hooked up 120....drier on 2p20....range on 2p50....water heater fed with 2c14 Bx on 2p15."

Go HERE to join the discussion

 


 

The Canadian Electrical Code for safer electrical installations

Canadian Standards Association

For over 90 years, the Canadian Electrical Code, Part I (CSA C22.1:21), has helped ensure the safety of electrical installations and protection of electrical workers. Its 2021 edition brought 200+ additions and updates that address energy storage systems, climate change adaptation, hazardous locations, and other important topics. To help users better understand and apply the Code, CSA Group developed additional resources and training.

Learn more about available Code packages and resources

 


 



 

Iron+EarthThe RenuWell Project partners are excited to announce the groundbreaking of two pilot sites located near Taber, Alberta. These pilot sites are the first of their kind to repurpose inactive oil and gas infrastructure as a foundation for renewable energy development and job creation.

When operating, the solar projects will generate 2,030 MWh annually – enough electricity to power 280 average Alberta households or irrigate 11,700 acres of farmland for an average year. This is roughly equivalent to $200,000 in electricity sales per year with 1,100  tCO2e savings in GHG emissions. Over a 25-year lifespan, the projects will generate 50,750 MWh, with GHG emission savings of 28,420 tCO2e.

Read More


 

David O'ReillyBy Elle Bremmer

Recently, I had the pleasure of sitting down with David O’Reilly, Vice President Home & Distribution and Secure Power Divisions with Schneider Electric Canada for a discussion regarding the Wiser EnergyTM smart home solution, the Wiser Approved training program, and his thoughts on several different subjects, including sustainability and future technologies currently in the works at Schneider Electric. David has been with the company for five and a half years in his role.

We recently published a study (version en français ICI) from Schneider Electric showing a strong interest from Canadians in smart home technology. 

Read More


 

SimplySnap: It Just Works.

SynapseSmart technology is only smart if it works, and SimplySnap? It just works.
Scalable, field-proven, DLC NLC 5.0 qualified, and easy-to-install wireless network
lighting controls are in-stock. Explore energy code compliant SimplySnap
technology here.

Read More

 


 

Product News

  • Prev
Alligator® water pump pliers from KNIPEX provide good access to the workpiece due to slim size of ...
The MX FUEL™ ROCKET™ Tower Light/Charger provides up to 27,000 lumens of task and area lighting and ...
Automate electrical system labelling and electrical panel directory creation (ditch the manual ...
The Ferret Plus brings you the ultimate innovation in inspection technology. Includes built-in (on ...
IDEAL® Pro Series Camo Zipper Pouches are a convenient storage solution for electrical tools, ...
The new WhisperAir Repair™ from Panasonic is a compact ceiling-mount air purifier that is effective ...
By pairing the sturdiness and performance of the Green Cable Concrete and the simplicity ...
Offering a wide range of high-quality industrial plugs and sockets complying with IEC 60309-1 and ...
Stanpro’s L1RHT is a high temperature, high lumen output, high impact resistant LED high bay rated ...
The nPODA Key is a low voltage, single gang, nLight decorator switch that offers additional ...


Ericson String LightsEricson announces upgraded versions of their extremely capable line of Industrial String Lights and SL, LED Stringlights. These new and updated products have several key features important when safe, code compliant lighting for industrial workspace is necessary.

Infinitely capable, these ruggedly built products have several industry leading & exclusive features including:

Industrial String Lights:

  • A United States Navy Specification since before WWII, they’re time and application tested...

 

Read More


 

 

Intermatic Pool and Spa SolutionIntermatic Incorporated announced its new P40000 Series Load Centers, a set of next-generation panels for pool-only applications, as well as its new PE24GVA 24-Volt Valve Actuator, an easy-to-install valve actuator that allows for tool-free cam adjustments. Both solutions remove obstacles for pool service professionals while delivering lasting performance.

“Intermatic load centers and valve actuators have been the preferred choice of pool professionals for more than 30 years,” says Brian Lamberty, product marketing manager at Intermatic. “The PE24GVA and P40000 Series build on that tradition, helping pool professionals streamline service calls while setting the standard for quality and performance.”

Read More


 

 

Klein Tools Zipper BagsKlein Tools introduces new Stand-up Zipper Bags, in a 2-Pack with 7-Inch and 14-Inch sizes, both designed to handle tough jobsite conditions and stand up so tools and small parts can be easily accessed when working.

Stand-up Zipper Bags, 7-Inch and 14-Inch, 2-Pack (Cat. No. 55559)

  • Perfect for storing pliers, wrenches, screwdrivers, drill bits and other small tools and parts
  • 4 1/2’’ tall zipper bags come in two sizes:
    • 14’’ (36.6 cm) dark gray
    • 7’’ (17.8 cm) royal blue


Read More


 

Emerson HV SafetyThe Occupational Safety and Health Administration (OSHA) estimates 350 employees are killed annually in electrocution accidents, which roughly equals one fatality per day. In the face of these dangers, OSHA officials and industry safety consultants alike recommend eliminating potential hazards on work sites, rather than simply relying on contractors or employees to follow safety guidelines.

To help safeguard employees from electrocution, Emerson has launched its Appleton™ Powertite™ Lock Collar, a device that fastens over plug and connector connections and is secured with a padlock, preventing unauthorized personal from disconnecting the cable connection once in place. 

Read More


 

Peers & Profiles

  • Prev
Watt’s the Word is a recently launched Electrical Industry Podcast hosted by Zack Hartle and ...
Allana Kellett-Jamieson loves working in the electrical sector and is proud of the great focus ...
As the head of ABB Canada's electrification business unit, Éric Deschênes is no newcomer to the ...
Karen Pullen knows what it’s like to be the only woman on a construction site, and as a proud ...
As of February 2021, Martin Stephenson is the new President and CEO of Signify Canada.   ...
This past July, Kerith Richards, who has worked for Service Wire Company for the last seven years, ...
EngWorks was formed in 2004 as an electrical engineering and consulting firm by Allan Bozek, “After ...
Headquartered in Concord, Ontario, Mercury Lighting services national retail, ...
Among the recipients of the 2021 Clean50 Awards announced last month is Carolina Gallo, Vice ...
Sarah Silverstein is a principal with Liteline along side her two brothers Mark and Daniel. ...

Copper $US Dollar price per pound

Kerrwil Publications Great Place to Work. Certified December 2019 - December 2020

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2022 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil