Considerations for EV Charging Installation and Site Preparation

December 15, 2025

By Blake Marchand

As part of our recent discussion with LEDVANCE EVSE Product Manager, Erich Bockley, he emphasized the importance of site preparation

Site preparation can be the most complicated part of the project, Bockley emphasized, a lot needs to be considered before the installation work begins. Many public charging applications will require trenches to get the power out to where it needs to go. Concrete and landscaping work could be part of the overall project. as well as establishing a strong internet signal.

With that in mind, this article provides a brief overview of some key considerations for EV charger installations, as well as a summary of code rules and bulletins relating to EV charging.

Adequate Power

EV chargers are a continuous load, the circuit must be rated at 125% of the EV charger’s load.

For a residential installation, for example, the panel needs to have the physical space for a new double-pole breaker, as well as the ampacity to meet the total load including the charger. An EV energy management system can be utilized to account for the additional load, without having to upgrade the panel.

Level 2 chargers require a fixed station and a dedicated 208-V or 240-V branch circuit.

Level 3 chargers are 480V, and more dedicated power infrastructure like a transformer, an upgraded panel, trenching and longer conduit runs from an electrical room to the charger location.

Level 3 chargers are suitable for gas stations and rest stops, as well as fleets, but require significantly more investment. 

AWG

AWG is determined by the amperage of the charger and the distance between the panel and EV charger. A larger gauge may be required for longer distances to account for voltage drop.

Home EV chargers most commonly use 6 AWG.

Reliable Connection

An EV charging installation requires internet (ethernet or WiFi) or a 4G network to operate.

Bockley noted that LEDVANCE’s Phase EV Chargers have an ethernet port at the back, so the ethernet cable can be pulled with the rest of the wire to the charger.

“Before you even take a shovel to this, you need to be able to test using specialized 4G equipment (that’s widely available) to make sure there’s a strong 4G signal where you are going to install [the charger], and if there’s not, you have two choices. Either you install a 4G repeater to make sure you have a strong signal there, or you choose another location.”

Bockley noted that if you are relying solely on the 4G signal and you don’t have a strong and reliable 4G connection, then it will result in intermittent service, which is frustrating for EV drivers and charger operators.

Charge Point Operator, RFID

It is important for electrical contractors to work with the site owner to establish how the charger is going to be used and where it will be installed, to ensure reliability.

If the client wants a free use charger for employees or tenants, LEDVANCE’s chargers feature an RFID tap to identify the end-user. Otherwise, the charger needs to be paired with a charge point operator (CPO) to enable payment for public charging.

Bockley recommends that site owners that plan to generate revenue with the chargers get set up with the CPO ahead of the installation so that it can be ready to use once the contractor completes the installation.

“Once the site is prepared, the design of the EV Charger also has to be flexible. It should be able to accommodate the various possibilities that are demanded by the site,” Bockley noted, “the LEDVANCE Phase EV is available in multiple configurations to meet the requirements of the site.”

Mechanical Protection

EVSEs should be protected by a curb and, typically, installed at least 1m back from the front of the curb. If the charger is being used by trucks or larger vehicles, the charger may need more room to protect it from being damaged. Protected curb stops are suitable for underground locations.

For wall chargers, the bottom of the charger and electrical wiring should be at least 1m above grade, potentially higher for larger vehicles.

Also of note, if the installation is outside, the charger must be rated for outdoor use.

Summary of the Main Code Rules for EV charging:

Section 86 of the Canadian Electrical Code outlines the rules for EV charging system installation. It is important to be aware of local distinctions to the national code, some jurisdictions have bulletins or interpretations to clarify certain rules or aspects of an installation.

ESA’s Bulletin 86-1-7 clarifies installation of energy management systems and EV supply equipment (EVSE) demand factors, mechanical protection, and load sharing.

Technical Safety BC: Information Bulletin: Electric Vehicle Supply Equipment (EVSE) and Electric Vehicle Energy Management Systems (EVEMS)

This Alberta STANDATA Interpretation clarifies branch circuit conductor ampacities and overcurrent device settings for electric vehicle charging systems supplied with adjustable ampacity settings.

Rule 8-002: Calculated load – the load calculated in accordance with the rules in this section; Control of electric vehicle supply equipment loads – the process of connecting, disconnecting, increasing, or reducing electric power to electric vehicle supply equipment loads; and Electric Vehicle Energy Management System – a means of controlling electric vehicle supply equipment loads comprised of any of the following: a monitor(s), communications equipment, a controller(s), a timer(s) and other applicable device(s).

86-300 – Branch circuits: Electric vehicle charging equipment shall be supplied by a dedicated branch circuit that supplies no other loads except ventilation equipment intended for use with the EV charging equipment.

86-302 – Connected load: The total connected load of a branch circuit supplying electric vehicle charging equipment and the ventilation equipment permitted by 86-300 shall be considered continuous for the purposes of Rule 8-104.

86-304 – Disconnecting means: A separate disconnecting means shall be provided for each installation of charging equipment rated at 60 A or more or more than 150 volts-to ground. It shall be located within sight of and accessible to the charging station. It shall be capable of being locked in the open position.

14-106 and 36-208 – Protection devices: Protection devices are used to open an electrical circuit in the case of the adverse effects of overcurrents and short-circuits. Where possible, they shall be grouped together and easily accessible.

86-306 – Plugs for AC Level 1 charging: Single-phase 120-V outlets dedicated to slow charging must be CSA configuration 5-20R (20 A) even if the SAE J1772 standard allows a connection to a CSA 5-15R (15 A) outlet. If the outlet is installed outdoors, it must be protected with a Class A ground fault circuit interrupter (GFCI) or located at least 2.5 m above the ground. In cases where a GFCI is built into the charging cable, to prevent unwanted trips due to interaction between the two GFCIs, it is preferable to opt for a fixed installation.

Rule 86-404 reaffirms that electric vehicle supply equipment, located in hazardous locations or areas, conforms to the applicable requirements of Section 18 and 20.

Related Articles


Latest Articles

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    February 6, 2026 The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual Read More…

  • 3D Printing: Inside Lighting’s Next Revolution

    February 5, 2026 While 3D printing in mass production was once a dream, advancements in the technology have moved it more into the mainstream. The technique, which is also referred to as additive manufacturing, has rapidly evolved from a niche prototyping tool into a transformative production method for many sectors, including the lighting industry. As Read More…

  • Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    February 5, 2026 In an era of extreme weather, aging infrastructure, and ever‑rising energy demands, many facility managers are rethinking their relationship with the grid. Microgrids offer a way to take control and operate autonomously when necessary. A microgrid is more than just backup, when designed properly, it becomes a platform for resiliency, efficiency, and Read More…

  • ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    February 5, 2026 Understanding NEMA Ratings for Electrical Enclosures NEMA Ratings are an essential classification system used across North America to define the environmental and mechanical protection provided by electrical enclosures. Developed by the National Electrical Manufacturers Association (NEMA), these ratings help engineers, installers, and specifiers identify the appropriate enclosure type for industrial, commercial, and outdoor Read More…


Changing Scene

  • Lighting What’s Next: Stanpro Celebrates 65 Years

    Lighting What’s Next: Stanpro Celebrates 65 Years

    February 6, 2026 “We didn’t get here by standing still. For 65 years, we’ve shaped how we think, how we design, and what responsibility means,” the company said in a LinkedIn post. “Today, that thinking takes a new form. Not to change who we are, but to express our evolution more clearly. This is Stanpro, Read More…

  • Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    February 6, 2026 Efforts to support the creation of new affordable housing and reduce chronic homelessness are on track, but there is still lots of work to do, according to David Hickey, the minister responsible for the New Brunswick Housing Corporation. New data indicates progress has been made on three key government priorities related to Read More…

  • BJ Electric is now Bernie’s Electric Supplies Ltd

    BJ Electric is now Bernie’s Electric Supplies Ltd

    February 6, 2026 BJ Electric has announced the company has rebranded as Bernie’s Electric Supplies Ltd, a nod to their founder. “BJ Electric Supplies is now Bernie’s Electric Supplies—in honor of our founder, Bernard Joseph Thompson, and the values that have guided the company for nearly 50 years. As we grow and evolve, this name Read More…

  • The Government of Canada Introduces the Build Canada Homes Act

    The Government of Canada Introduces the Build Canada Homes Act

    February 6, 2026 The Government of Canada has introduced the Build Canada Homes Act, legislation that will establish Build Canada Homes as a Crown corporation whose mandate will be dedicated to building affordable housing in communities across the country. As Canada’s affordable housing builder, this legislation will equip Build Canada Homes with the necessary tools to Read More…