Case Study: Centre Block Rehabilitation

EIN Lind CS Centre Block 400

February 16, 2022

The Centre Block at Parliament Hill is an iconic national symbol of Canada and the home of Canada’s Parliament. The Centre Block Rehabilitation will modernize the century-old building for future generations while preserving its heritage as the heart of Canadian democracy.

TWZ Group is the electrical contractor responsible for the temporary lighting on this complex restoration

project. TWZ Group Inc is a consortium of three electrical contractors, Ziebarth Electric, Wired Synergy and Toban Electric.

Committed to environmental sustainability and ensuring the best value for Canadians possible, the project team adopted LED Jobsite lighting throughout the project.

When compared to traditional bulb-based temporary lighting, LED Jobsite lighting reduces energy consumption by 65%. The project team is reducing the electrical consumption even further by implementing strict timing protocols to ensure non-essential lighting is turned off overnight.

Over the service-life of the lights, the energy usage is projected to be reduced by over 5.5 million kilowatt hours, which is equal to powering more than 2,700 homes per year.

The CO2 emissions will be reduced by more than 4,000 metric tons and is equivalent to removing 1,243 cars from the road.

EIN Lind CS 1

 

LED Jobsite lights require significantly less circuits, less maintenance, and are easier to install, relocate and uninstall. During the start of the restoration, the project team appreciated being able to increase efficiency while reducing the project’s carbon footprint.

 

EIN Jobsite CS 2

ON THE JOBSITE:

WASTE DIVERTED

An added environmental benefit is the significant amount of waste diverted from landfills because LED

Jobsite lights are a reusable asset and the modular cords are field serviceable. Also, CFL bulbs contain mercury and are considered hazardous waste. When moving to LED lights harmful toxins are no longer an issue.

FLEXIBILITY AND VERSATILITY

Centre Block is one of the most important buildings in Canada and the protection of its many heritage components is a critical concern for the construction team.

With a project of such complexity and scale, using a modular daisy-chain verses traditional cumbersome stringlights provides a greater level of flexibility to light the project.

LED Jobsite lights have enabled the project to hang less temporary lights, use less installation points, less circuits and less energy, all while also illuminating more space.

 

EIN Lind Case Study

www.ledjobsite.com

Related Articles


Latest Articles

  • Declines in Ontario and Manitoba Construction Intentions Push Down the Non-Residential Sector

    Declines in Ontario and Manitoba Construction Intentions Push Down the Non-Residential Sector

    December 16, 2024 The total value of building permits issued in Canada decreased by $399.1 million (-3.1%) to $12.6 billion in October. This comes on the heels of a strong September, during which construction intentions rose by $1.3 billion to the second-highest level in the series. Despite the monthly decline in October, the total value of building permits… Read More…

  • Lighting Control Basics for Home Automation

    Lighting Control Basics for Home Automation

    By Matthew Biswas Do your eyes roll when you hear terms like Smart home technology?  Or are you a true believer?  As it turns out controlling electrical devices via low-voltage technology can be easier to implement and use than many of us thought. The Lutron Caseta system uses the internet and Radio Frequency to instantly… Read More…

  • Grounded in Ontario: The Future of Energy Storage Systems

    Grounded in Ontario: The Future of Energy Storage Systems

    December 16, 2024 Technical Advisor Trevor Tremblay explains why following best practices and relying on licensed professionals will ensure a smooth and secure transition when integrating this exciting new technology. Energy Storage Systems (ESS) are revolutionizing the way individuals and businesses manage energy, providing cost-saving opportunities, increased energy reliability, and a pathway toward sustainability. In… Read More…

  • 4 in 5 Canadians See Electrifying Public Transit as Key to Advancing Climate Action, Schneider Electric Survey Finds

    4 in 5 Canadians See Electrifying Public Transit as Key to Advancing Climate Action, Schneider Electric Survey Finds

    December 13, 2024 Schneider Electric has released new survey findings showing Canadians are increasingly concerned about the environmental impact of traditional public transit emissions. According to the survey, 83 per cent of Canadians recognize the need for electrified transit to support a sustainable future and are seeking actionable and innovative solutions to ease the nation’s… Read More…


Changing Scene