Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • Four Ways Permanent Power Enahnces Outdoor Spaces

    Four Ways Permanent Power Enahnces Outdoor Spaces

    April 14, 2025 Today’s workplaces are expanding beyond the four walls of an office. As technology continues to evolve, employees are looking for new and alternative workspaces to inspire creativity and increase productivity. This includes taking their work to outdoor spaces. Bringing technology to outdoor spaces has become a challenge for facility managers and property… Read More…

  • CAF-FCA Provides Recomendations on Apprenticeship Investment

    CAF-FCA Provides Recomendations on Apprenticeship Investment

    April 13, 2025 CAF-FCA have provided an outline of actionable recommendations—developed through national consultation—to enhance accessibility, reduce financial barriers, and better align apprenticeship training with industry needs. Source Read More…

  • New Report: Preparing Alberta’s Buildings for Severe Weather

    New Report: Preparing Alberta’s Buildings for Severe Weather

    April 13, 2025 Alberta is facing more severe weather events, with rising temperatures, wildfires, and more frequent extreme storms threatening homes and businesses. Our report, Preparing Alberta’s Buildings for Severe Weather−written in partnership with the Alberta Ecotrust Retrofit Accelerator program−highlights the need for deep retrofits to ensure the province’s buildings can withstand these changing conditions. Four… Read More…

  • CCA Bulletin: Managing Tariff Risks in Construction Projects

    CCA Bulletin: Managing Tariff Risks in Construction Projects

    April 13, 2025 This bulletin was prepared by select members of the Canadian Construction Association’s (CCA) General Contractors National Advisory Council. Its purpose is to assess the potential impacts of tariffs and counter-tariffs on general contractors in Canada focusing specifically on: In both areas, the bulletin explores both upstream and downstream impacts – examining how… Read More…


Changing Scene

  • PEI’s First Net Zero Ready School Officially Opens

    PEI’s First Net Zero Ready School Officially Opens

    April 13, 2025 Island students, their families and the Sherwood school community came together today to celebrate the opening of PEI’s first net zero ready school. The new Sherwood Elementary School, built next to the former school, offers over 82,000 square feet of space with many innovative features to promote enhanced learning experiences for up… Read More…

  • Nova Scotia Invests to Connect Nova Scotians to Skilled Trades

    Nova Scotia Invests to Connect Nova Scotians to Skilled Trades

    April 13, 2025 The Province is helping more Nova Scotians explore and connect to careers in skilled trades through a $10-million investment in the construction industry. The investment will support more skilled trades training through three key initiatives: “Nova Scotia needs more skilled trades professionals to support our growing economy and to build the homes,… Read More…

  • PEI Tables Bill Aimed to Eliminate Trade and Labour Barriers

    PEI Tables Bill Aimed to Eliminate Trade and Labour Barriers

    April 13, 2025 Hon. Rob Lantz, Premier of Prince Edward Island, introduced the Interprovincial Trade & Mobility Act in the provincial legislature. This bill will allow Prince Edward Island to eliminate unnecessary barriers to trade and labour mobility with reciprocating jurisdictions.   The Bill will accept provincial inspections and standards on goods coming from a… Read More…

  • PEI Minimum Wage Set to Increase

    PEI Minimum Wage Set to Increase

    April 13, 2025 Minimum wage in Prince Edward Island will increase incrementally to $17 per hour by April 1, 2026.  The Employment Standards Board reviews minimum wage annually and provides their recommendation to government.  Go HERE for more information Source Read More…