Guide to the Canadian Electrical Code, Part I – Instalment 3

Electrical Conductors

William (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 4. It is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 4 – Conductors

The definition of conductor, from Section 0, is a wire or cable, or other form of metal, installed for the purpose of conveying electric current from one piece of electrical equipment to another or to ground.

Section 4 deals with the selection of type, ampacity and installation conditions of insulated conductors. It is a general section and therefore it applies to all conductors supplying lighting, appliances and power circuits. The selection of other conductors, such as for control, grounding, emergency, safety, fire alarms, airport installations, renewable energy, communications, cathodic protection, and others, will be governed by individual sections covering these situations. Individual sections may also apply as general sections, or may have rules that reference or amend Section 4.

For example, Sections

• 6 — Services and service equipment
• 8 — Circuit loading and demand factors
• 10 — Grounding and bonding
• 12 — Wiring methods
• 14 — Protection and control
• 16 — Class I and Class II circuits
• 26 — Installation of electrical equipment

For this reason it is important to compare the rules in Section 4 with the rules governing conductors in the section dealing with your particular installation. For instance, Rule 4-002 requires that the minimum size for all copper conductors, except for flexible cord, equipment wire, or control circuit wire, and cable (which are specifically covered by other sections) is No.14 AWG and No. 12 AWG if aluminum. However, in Section 6, Rule 6-302 Installation of overhead consumer’s service conductors requires that the minimum size for overhead consumer’s service conductors is No.10 AWG copper or No. 8 AWG aluminum. Even though there are amendatory sections and rules later in the code, it is still important that you refer to Section 4 first when selecting and installing any conductor.

Conductor selection factors

When selecting a conductor there are a number of factors to be considered. Because of the complexity of conditions, you need to have a process to determine the correct type and size for your application. The first consideration is to choose the size of conductor you need based on the

• current it will be required to carry
• conditions under which it will be installed
• type of conductor or cable to be used

Rule 4-004 Ampacity of wires and cables contains 7 items each in subrules (1) and (2) covering scenario options each for copper and aluminum that need to be studied and chosen. In addition, there are 21 other factors in the subsequent subrules to be considered.

Although this may seem daunting at first, it is simply a matter of going through the list of options and conditions and choosing the ones that apply to your situation. Rule 4-004 will then direct you to the correct table and correction factor for your situation.In some cases you will be directed to use the IEEE 385 calculation method or the tabulated information tables in Appendix D. The IEEE 385 Standard Power Cable Ampacity Tables contains all pertinent equations and has the electrical/thermal analog circuit and calculation examples in the annex.

Once the right ampacity has been chosen or calculated, the next factor to consider, according to Rule 4-006, is the temperature limitations on the conductor ampacity you have chosen. Where the maximum conductor termination temperature is marked on the equipment, you will have already chosen the minimum size of conductor based on the correct temperature column of tables 1, 2, 3 or 4. Where the maximum conductor termination temperature is not marked on the equipment, the temperature to be used is: 600 C for equipment rated 100 A or less or marked for use with No.1 AWG or smaller conductors, or 750 C for equipment rated more than 100 A or marked for use with conductors larger than No. 1 AWG.

These conditions apply only to the first 1.2 meters of conductor length measured from the termination point of the equipment.One other condition to note when using a single conductor cable with a metal sheath or armour: induced voltages may cause the conductor insulation temperature to exceed its rating. In this case,Rule 4-010 Induced voltages and currents in metal armour or sheaths of single-conductor cables requires you to derate the conductor along with some other procedures to mitigate this situation.

The next important consideration outlined in Rules 4-008, 4-012, 4-014, 4-016, 4-018, 4-020, 4-040 and 4-042 is the selection of the type of insulated conductor, flexible cord, equipment wire or portable power cable. In some cases these rules will specify minimum sizes and ampacities for the various types.

Finally we go back to Rules 4-022, 4-024, 4-026, 4-028, 4-030, 4-032, 4-034, and 4-036, which provide for the use of a common neutral, installation, identification and use of neutral and identified conductors. Rule 4-038 Colour of conductorscovers the colouring of insulated grounding and bonding conductors, and where colour-coded circuits are required.

You will note that Section 4 does not apply to non-insulated grounding or bonding conductors. The use, size and ampacity of these conductors are covered by Section 10, which we will deal with in subsequent instalments.

In the next installment we will explore Section 6 — Services and service equipment.

Read the rest of the instalments in the series:

Part 1: Guide to the CE Code, Part I — A Roadmap (Instalment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I — Instalment 2
Part 3: Guide to the Canadian Electrical Code, Part I — Instalment 3
Part 4: A Road Map to the CE Code, Part 1 — Instalment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Instalment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Instalment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Instalment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Instalment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 — Instalment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 — Instalment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Code Question on Section 24 – Patient Care Areas

    Code Question on Section 24 – Patient Care Areas

    July 14, 2025 The rules for the installation of panelboards, circuits, and bonding in Patient Care Area depends on whether the area is designated as either, Basic Care, Intermediate Care or Critical Care. How are these areas defined? Read more on Section 24 — Health care areas Read More…

  • Ontario’s Institutional Component Drives Non-Residential Construction Intentions in May 2025

    Ontario’s Institutional Component Drives Non-Residential Construction Intentions in May 2025

    July 14, 2025 In May, the total value of building permits issued in Canada rose by $1.4 billion (+12.0%) to reach $13.1 billion. The increase in construction intentions was driven by Ontario’s institutional component (+$1.3 billion). On a constant dollar basis (2023=100), the total value of building permits issued in May increased 11.8% from the previous month and was… Read More…

  • Plan Group Partners in Construction of UHN Surgical Tower at Toronto Western Hospital

    Plan Group Partners in Construction of UHN Surgical Tower at Toronto Western Hospital

    July 14, 2025 Plan Group is proud to be a partner in the construction of the UHN Surgical Tower at Toronto Western Hospital. Plan Group will provide work on the project in: Mechanical: Plumbing, HVAC, Controls, Medical GasElectrical: Lighting & Controls, Power Distribution, Emergency Generators, UPSTechnology: Structured Cabling, AV Systems including Digital Signage and IPTV UHN’s 15-storey Surgical… Read More…

  • How Canada Can Equip Workers for a Low-Carbon Future

    How Canada Can Equip Workers for a Low-Carbon Future

    July 14, 2025 The Canadian economy is shifting towards low-carbon industries, and the workforce is shifting with it. New roles are emerging, traditional ones are evolving and the demand for skilled workers is growing fast — particularly in light of the ambitious nation-building agenda the federal government has set out. In the federal Speech from… Read More…


Changing Scene

  • OEL Apprentice Success Project Available Until March 2026

    OEL Apprentice Success Project Available Until March 2026

    July 14, 2025 With renewed funding by Ontario’s Skills Development Fund, the OEL Apprentice Success Project is now available for another year until March 2026. The project is part of OEL’s Employer Engagement Program (EEP) consisting of wage, training, and equipment subsidies for apprentices. These funding opportunities are available to OEL Members and non-Members. For… Read More…

  • EB Horsman Unveils New Mural at Campbell River Branch

    EB Horsman Unveils New Mural at Campbell River Branch

    July 14, 2025 EB Horsman & Son are thrilled to unveil a new mural at their Campbell River branch, painted by the talented Kwakwaka’wakw artist, Adam Lewis. “This stunning piece celebrates Indigenous heritage and our community spirit,” said EB Horsman on LinkedIn. “As we mark 125 years of serving Western Canada and 55 years in… Read More…

  • Glenco Electric Celebrate New Red Seal Team Members

    Glenco Electric Celebrate New Red Seal Team Members

    July 14, 2025 “The Red Seal Journeyman designation is the highest recognition in the trades, and we’re proud to have seen so many of our team members earn it under our watch,” said Glenco Electric on LinkedIn. “At Glenco, we’re big on mentorship and promoting from within. When you combine that with driven, hard-working professionals,… Read More…

  • Canada and Ontario Investing to Improve Energy Efficiency in Province’s Agri-Food Industry

    Canada and Ontario Investing to Improve Energy Efficiency in Province’s Agri-Food Industry

    July 14, 2025 The governments of Canada and Ontario are investing up to $3 million and launching the third intake of the Agricultural Stewardship Initiative (ASI) to help farmers implement projects to improve the energy efficiency of their farming operations. To support the province’s plan to protect Ontario, this funding will help local agriculture, agri-food… Read More…