Guide to the Canadian Electrical Code, Part I — Instalment 6

Electrical Grounding

 

William (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 10 — Grounding and bonding.

Section 10 — Grounding and bonding

Section 10 is a general section of the Code and applies to all installations unless amended by other Sections of the Code. It’s Scope outlines requirements for:

• grounding of electrical systems and service equipment
• bonding of non-current-carrying metal parts of equipment and conductor enclosures, together and to ground
• the use of ungrounded systems and neutral grounding devices

Special terminology used in this section and found throughout the code include bonding, bonding conductor, ground, ground fault, ground fault detection, ground fault protection, grounded, grounding, grounding conductor, grounding electrode, and grounding system.

These are all thoroughly defined in Section 0. In general terms, bonding refers to a low impedance permanent connection of all non-current-carrying metal parts together, and grounding refers to a permanent low impedance connection to the earth.

The stated object of Section 10 is to provide rules for

• bonding metal parts and systems together and to the grounded system conductor to reduce the danger of electric shock and property damage, providing a low impedance path for fault current back to the source, and establishing an equipotential plane to minimize potential difference between non-current carrying metal parts

• grounding the electrical system and bonding of non-current carrying metal parts to earth to minimize any potential difference to earth

• using an ungrounded system or a neutral grounding device in the system to provide alternates to a solidly grounded system, and minimizing any damage from a single fault by limiting the magnitude of the fault current.

System and circuit grounding rules 10-102 to 10-116 provide guidance on when and where, as well as exceptions to, grounding specific two-wire dc systems, three-wire DC systems, AC systems, electric arc furnaces, electric crane circuits, isolated circuits, circuits of less than 50V, and instrument transformer circuits.

Once you have determined your specific grounding needs, Grounding connections for systems and circuits rules 10-200 to 10-212 provide specific detailed guidance on how to ground various systems. Appendix B also contains some helpful diagrams.

Conductor enclosure bonding rules 10-300 to 10-304 are guidelines for when and where to bond metal enclosures for service conductors, underground service conductors, as well as enclosures for other than service conductors.

Equipment bonding rules 10-400 to 10-414 provide the varying requirements for when and where to bond all metal non-current carrying parts of fixed equipment general, fixed equipment, specific, non-electrical equipment, portable equipment, instrument transformer cases, cases of instruments, meters, and relays-operating voltage 750v or less, cases of instruments, meters, and relays-operating voltage over 750V, as well as non-metallic wiring systems.

The Bonding methods rules 10-600 to 10-626 will guide you through the steps needed to ensure an effective continuous, low-impedance bonding connection when Bonding service equipment, Metal armour or tape of service cable, Bonding at other than service equipment, Loosely jointed metal raceways, bonding jumpers, short sections of raceway, fixed equipment, portable equipment, pendant equipment, bonding equipment to the grounded system conductor (bonding to ground), and electrolytic-type water heaters. Helpful suggestions are also contained in the Appendix B notes.

Rule 10-700 Grounding electrodes sets out the requirements for establishing a grounding connection through the use of electrodes. There are specific rules for various grounding electrodes including manufactured grounding electrodes (both rod electrodes and plate electrodes), field-assembled ground electrodes, and in-situ grounding electrodes forming part of the existing infrastructure. Rule 10-702 sets out spacing and interconnection requirements for grounding electrodes where more than one grounding electrode exists at the building including those electrodes used for signal circuits, radio, lightning protection, communication, community antenna distribution systems, and any other purpose. Rules 10-704 and 10-706 deal with railway track electrodes and the use of lightning rod system conductors and grounding electrodes.

Rules 10-800 to 10-820 are rules governing continuity, material selection, sizing, and installation of grounding and bonding conductors. The size of a grounding conductor is determined by the type of system, either AC or DC. The size of a bonding conductor as determined by Table 16A or 16B depends on the size of the associated circuit conductor (Table 16A) or on the size of the associated bus-bar (Table 16B).

Once you have installed the correct type and size of bonding and grounding conductor, pay close attention to the connection of these conductors as specified in rules 10-900 to 10-906 Grounding and bonding conductor connections. The continuity and safety of a low-impedance path to reduce the danger of electric shock and property damage, and providing a low impedance path for fault current back to the source, depends on adequate and sound connections.

The final two subjects of Section 10 deal with grounding and bonding of lightning arresters and the installation of neutral grounding devices.

In the next installment we will be discussing Section 12 — Wiring methods.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 – Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 – Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Driivz: 2025 State of EV Charging Network Operators Report

    Driivz: 2025 State of EV Charging Network Operators Report

    May 19, 2025 As the EV charging industry is poised for profitability, network operators still face many challenges. But what are their biggest challenges, are they ready to scale up to support their business growth, and how will they provide drivers with a better charging experience in 2025. This report answers these questions and more,… Read More…

  • Electri International: Understanding, Identifying, and Measuring Rework

    Electri International: Understanding, Identifying, and Measuring Rework

    May 19, 2025 ELECTRI has sponsored a research project to create a playbook for electrical contractors that will help you: Unpaid rework refers to activities in the field (including prefabrication) that have to be done more than once, or activities that remove work previously installed as part of the project, where no change order has… Read More…

  • Intermatic Acquired by MPE Partners

    Intermatic Acquired by MPE Partners

    May 19, 2025 By David Gordon, Channel Marketing Group, President The Intermatic deal is done. It has been rumored for months that Intermatic was being sold. Strategic buyers and private equity firms were mentioned as expressing interest and reviewing “the book” throughout the fall (and some mentioned even last summer.) According to sources, it was a “challenge” for… Read More…

  • 6 Things Contractors Need To Know About the Security Kit for Wire Mesh Tray

    6 Things Contractors Need To Know About the Security Kit for Wire Mesh Tray

    May 19, 2025 The rapid expansion of data centers has brought about significant challenges in maintaining data security standards. According to Statistics Canada, recovery costs from cyber security incidents in 2023 were $2.1 billion, up from $600 million in 2021. This critical situation requires a more robust cable management design to protect data from being… Read More…


Changing Scene

  • Schneider Electric Canada Named One of Canada’s Greenest Employers for 2025

    Schneider Electric Canada Named One of Canada’s Greenest Employers for 2025

    May 19, 2025 Schneider Electric Canada has been recognized as one of Canada’s Greenest Employers for 2025 by Mediacorp Canada Inc. as part of the Canada’s Top 100 Employers project, a prestigious honour celebrating organizations that lead the country in creating a culture of environmental sustainability. This recognition highlights Schneider Electric’s long-standing commitment to advancing climate action, driving… Read More…

  • NEW ECAO Website is LIVE

    NEW ECAO Website is LIVE

    May 19, 2025 ECAO are excited to officially launch the new and improved ECAO website, redesigned with you in mind. Whether you are registering for training, accessing member resources, or staying up to date on key industry developments, ECAO’s new platform makes it faster, easier, and smarter. ECAO have rebuilt the site to deliver the ultimate… Read More…

  • Catalyst Sales and Marketing Announces New Partnership with MGM Transformers

    Catalyst Sales and Marketing Announces New Partnership with MGM Transformers

    May 19, 2025 Catalyst Sales and Marketing is proud to announce a new line partnership with MGM Transformer Company, a recognized provider of dry-type and liquid-filled transformers for commercial, industrial, and infrastructure applications. With over 50 years of expertise, MGM delivers custom-engineered, reliable, and energy-efficient solutions designed to meet the demands of data centers, renewable… Read More…

  • Intermatic Acquired by MPE Partners

    Intermatic Acquired by MPE Partners

    May 19, 2025 By David Gordon, Channel Marketing Group, President The Intermatic deal is done. It has been rumored for months that Intermatic was being sold. Strategic buyers and private equity firms were mentioned as expressing interest and reviewing “the book” throughout the fall (and some mentioned even last summer.) According to sources, it was a “challenge” for… Read More…