Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles


Changing Scene

  • BC Hydro Making it Easier and More Affordable to Connect New Homes

    BC Hydro Making it Easier and More Affordable to Connect New Homes

    July 24, 2025 BC Hydro is supporting the construction of new housing developments in growing communities by advancing changes to streamline upgrades and reducing the cost of new customer connections to BC Hydro’s electricity grid. “As communities across B.C. grow, so does the need for essential housing. We are committed to ensuring we’re ready to… Read More…

  • Mitrex Sets Record with Largest BIPV Solar Panel Mural at SunRise Residential in Edmonton

    Mitrex Sets Record with Largest BIPV Solar Panel Mural at SunRise Residential in Edmonton

    July 22, 2025 Building-Integrated Photovoltaics (BIPV) manufacturer, Mitrex proudly announces that its transformative SunRise Residential project in Edmonton, Alberta, has earned the Guinness World Record for the largest solar panel mural globally. This landmark project showcases Mitrex’s innovative BIPV solar panels, blending cutting-edge solar technology with vibrant cultural artistry to redefine sustainable architecture. Sustainable Architecture with BIPV Spanning over 30,000 square feet, the Mitrex eFacade PRO plus… Read More…

  • Nexans Unveils a Cable Made with 100% Recycled Materials

    Nexans Unveils a Cable Made with 100% Recycled Materials

    July 24, 2025 Nexans has reached a major milestone in its sustainability journey by developing a prototype cable made entirely from recycled materials — a first in the company’s history. This innovation combines technical performance, industrial feasibility, and a drastically reduced environmental footprint, marking a decisive step forward in circular economy. A cross-continental success story… Read More…

  • EFC Welcomes New Manufacturer Member: MGM Transformers

    EFC Welcomes New Manufacturer Member: MGM Transformers

    July 24, 2025 Since 1974, MGM Transformers has produced tough and trusted transformers designed to get the job done right. As a leading manufacturer, the company employs a highly experienced and dedicated engineering team that excels in custom designs. MGM Transformers is committed to excellent quality and service, offering industry-leading lead times and exceptional customer service. MGM Transformers specializes… Read More…