Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • EFC Supporting Industry Amongst Tariff Uncertainty

    EFC Supporting Industry Amongst Tariff Uncertainty

    As a major representative of the electrical and automation industry, Electro Federation Canada remains committed to supporting its members and the industry overall in navigating the complexities of international trade policies. Read More…

  • CanREA Launches New and Improved Go Solar Guide 2025

    CanREA Launches New and Improved Go Solar Guide 2025

    March 21, 2025 The Canadian Renewable Energy Association (CanREA) launched the 2025 edition of its annual Go Solar Guide today, encouraging Canadians to go solar. The 2025 version is new and improved: Now a web portal, it is free and accessible to everyone, anytime. “CanREA is proud to produce an annual consumer guide containing everything… Read More…

  • STANDATA Interpretation: 2024 Canadian Electrical Code, Part 1 Section 6 – Number of Supply Services Permitted

    STANDATA Interpretation: 2024 Canadian Electrical Code, Part 1 Section 6 – Number of Supply Services Permitted

    March 21, 2025 Purpose To clarify requirements for installations regarding the number of supply services permitted to be located on one unit of a building consisting of row housing for residential occupancies. Discussion There has been inconsistent application of the 2024 Canadian Electrical Code (CE Code) Part 1, Rule 6-102 regarding type and location where… Read More…

  • PEI Pauses Solar Electric Rebate Program

    PEI Pauses Solar Electric Rebate Program

    March 21, 2025 Rebate pre-approval letters for the Solar Energy Rebate program are currently on hold as the PEI government conducts a program review to ensure it continues to provide the best possible benefits to the most Islanders. We appreciate your patience. We do expect the program to be operational in the coming weeks. Check… Read More…


Changing Scene

  • Mersen Fuse Selection Guide

    Mersen Fuse Selection Guide

    March 21, 2025 Unlock Instant Access to the Mersen Fuse Selection Guide Learn how to match voltage ratings, nail amperage calculations, master interrupting ratings, and conquer temperature derating, all without breaking a sweat. Go HERE to download Read More…

  • EFC’s Business Sections Welcomes New Field Service Vice Chair

    EFC’s Business Sections Welcomes New Field Service Vice Chair

    March 21, 2025 EFC is pleased to announce Matthew De Ciantis, M&D De Ciantis Enterprises Inc., as the new Vice Chair of the Field Service Business Section. Matthew is a long-standing professional in the electrical industry who fulfilled many roles within his generational family electrical contracting company. Matthew’s experience and breadth of operational knowledge has… Read More…

  • EFC Welcomes New Manufacturer Member: NOARK Electric

    EFC Welcomes New Manufacturer Member: NOARK Electric

    March 21, 2025 NOARK Electric is a global manufacturer of low, medium and high low voltage electrical components for industrial applications. They specialize in providing electrical circuit protection and motor control solutions for OEMs, contractors, and distributors. Dedicated to quality and value, their mission is to deliver top-tier products at exceptional price, backed by world-class… Read More…

  • Mac’s II Agencies Strengthens Lighting Division

    Mac’s II Agencies Strengthens Lighting Division

    March 19, 2025 Mac’s II Agencies Announces Jamie Capell as the New Sales Manager for Lighting Specification Mac’s II Agencies is pleased to announce the expansion of its lighting division with the addition of Jamie Capell as the Sales Manager for Lighting Specification. Jamie brings 25 years of experience in the lighting and electrical industry, most notably… Read More…