PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    February 6, 2026 The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual Read More…

  • 3D Printing: Inside Lighting’s Next Revolution

    February 5, 2026 While 3D printing in mass production was once a dream, advancements in the technology have moved it more into the mainstream. The technique, which is also referred to as additive manufacturing, has rapidly evolved from a niche prototyping tool into a transformative production method for many sectors, including the lighting industry. As Read More…

  • Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    February 5, 2026 In an era of extreme weather, aging infrastructure, and ever‑rising energy demands, many facility managers are rethinking their relationship with the grid. Microgrids offer a way to take control and operate autonomously when necessary. A microgrid is more than just backup, when designed properly, it becomes a platform for resiliency, efficiency, and Read More…

  • ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    February 5, 2026 Understanding NEMA Ratings for Electrical Enclosures NEMA Ratings are an essential classification system used across North America to define the environmental and mechanical protection provided by electrical enclosures. Developed by the National Electrical Manufacturers Association (NEMA), these ratings help engineers, installers, and specifiers identify the appropriate enclosure type for industrial, commercial, and outdoor Read More…


Changing Scene

  • Lighting What’s Next: Stanpro Celebrates 65 Years

    Lighting What’s Next: Stanpro Celebrates 65 Years

    February 6, 2026 “We didn’t get here by standing still. For 65 years, we’ve shaped how we think, how we design, and what responsibility means,” the company said in a LinkedIn post. “Today, that thinking takes a new form. Not to change who we are, but to express our evolution more clearly. This is Stanpro, Read More…

  • Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    February 6, 2026 Efforts to support the creation of new affordable housing and reduce chronic homelessness are on track, but there is still lots of work to do, according to David Hickey, the minister responsible for the New Brunswick Housing Corporation. New data indicates progress has been made on three key government priorities related to Read More…

  • BJ Electric is now Bernie’s Electric Supplies Ltd

    BJ Electric is now Bernie’s Electric Supplies Ltd

    February 6, 2026 BJ Electric has announced the company has rebranded as Bernie’s Electric Supplies Ltd, a nod to their founder. “BJ Electric Supplies is now Bernie’s Electric Supplies—in honor of our founder, Bernard Joseph Thompson, and the values that have guided the company for nearly 50 years. As we grow and evolve, this name Read More…

  • The Government of Canada Introduces the Build Canada Homes Act

    The Government of Canada Introduces the Build Canada Homes Act

    February 6, 2026 The Government of Canada has introduced the Build Canada Homes Act, legislation that will establish Build Canada Homes as a Crown corporation whose mandate will be dedicated to building affordable housing in communities across the country. As Canada’s affordable housing builder, this legislation will equip Build Canada Homes with the necessary tools to Read More…