STANDATA: Rule 2-024 Use of Approved Equipment – High Voltage Termination and Splice Kits

August 9, 2024

Purpose: To address issues with approval requirements for High Voltage Termination and Splice kits (HVTS)

Discussion

Electrical contractors and electrical safety codes officers have requested a provincial variance to accept HVTS kits that meet industry recognized testing requirements outlined in various standards from both manufacturers and other global recognized certification bodies and standard development organizations. Canadian certification organizations have yet to identify a demand for developing a product certification program for HVTS more than 750V as per the Canadian Electrical Code (CE Code) Part 1, Section 36, consequently Canadian certified HVTS kits are not available.

Splices and terminations utilizing HVTS kits are installed as per manufacturer specifications which includes specialized training offered by each manufacturer specific to the kit being installed. It has been identified that many of the cases of failure are related to assembly and installation errors. As a result, this variance puts emphasis on the required training by each manufacturer to ensure persons are properly qualified when installing HVTS.

Code References

C22.1:21 – Canadian Electrical Code, Part 1

Rule 2-024 Use of approved equipment

1) Electrical equipment used in electrical installations within the jurisdiction of the inspection department shall be approved and shall be of a kind or type and rating approved for the specific purpose for which it is to be employed.

Electrical Code Regulation – Electrical systems equipment

2(1) If a code, standard or body of rules declared in force under the Act with respect to electrical systems requires approved equipment, that equipment must meet the requirements of this section.

(2) No person shall manufacture, install, sell or offer for sale any equipment related to electrical systems for use in Alberta unless the equipment has been

a) certified by a certification body in accordance with the certification body’s terms of accreditation
with the Standards Council of Canada, or

b) inspected by an inspection body in accordance with the inspection body’s terms of accreditation
with the Standards Council of Canada.

(3) Subsection (2) does not apply to electrical equipment of an electric distribution system or a transmission line as defined in the Hydro and Electric Energy Act.

(Note: “certification body” is defined as ‘an organization accredited by the Standards Council of Canada as a certification body;’ and “inspection body” is defined as ‘an organization accredited by the Standards Council of Canada as an inspection body.’)

Go HERE for more information

Related Articles


Latest Articles


Changing Scene

  • Federal Investment to Add 989 New Montreal Homes

    Federal Investment to Add 989 New Montreal Homes

    November 18, 2024 The federal government is providing nearly $364 million to help build 989 new homes in Montreal. The announcement took place at 5200 rue de la Savane, in Montreal, which received $100 million dollars through the Apartment Loan Construction Program (ACLP) to build 303 homes and will be operated by Olymbec. This rental building, named Lynk, is designed to… Read More…

  • ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    November 18, 2024 ABB completed the previously announced 50/50 joint venture with Niedax Group. The Abnex Inc. joint venture (JV) will broaden solutions and advance opportunities in the rapidly growing North American cable management market. Integrating engineering and manufacturing capabilities of ABB’s Installation Products Division with Niedax Group will enable the newly formed company to deliver a… Read More…

  • Ontario Building More Electric Vehicle Charging Stations

    Ontario Building More Electric Vehicle Charging Stations

    November 18, 2024 The Ontario government is building over 1,300 new electric vehicle (EV) charging ports in small and medium-sized communities, marking a major milestone in the province’s plan to increase access to EV chargers outside of large urban centres and support the electrification of transportation across the province. As the province continues to see… Read More…

  • Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    November 18, 2024 The Ontario government is launching the second round of its Skills Development Fund (SDF) Capital Stream starting November 29, with over $74 million in available funding to build, expand and retrofit training facilities for workers in the trades, including construction, manufacturing technology and health care. The government is also investing nearly $5 million from the first… Read More…