The CE Code is a comprehensive document. Sometimes it can seem daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 6. The article is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 6 – Services and service equipment

This section of the code outlines the rules applicable to the electrical installation of service equipment, including the consumer's service and the supply service. As per the definitions in Section 0, a consumer's service includes all that portion of the consumer's installation from the service box or equivalent, up to the point where the supply authority or local utility makes connection.

Note that “supply authority” can include public utilities as well as private electrical power networks that are deemed to be supply authorities by the regulatory authority having jurisdiction. Also, according to the scope outlined in Section 0,equipment and work employed by the supply authority, in its function as a utility, are not covered by this code.

However, this section does have rules only for the attachment point of the supply service. The rest is deemed to be outside the scope of the code since it is installed by the utility.

As noted above, this section deals with all electrical services. However, services and service equipment over 750 volts may be modified by rules in Section 36 - High-voltage installations.We will discuss these modifications when we get to Section 36, but if you are intending to install a high-voltage service be aware there may be rating, capacity and overcurrent protection modifications for high-voltage service equipment rules.

Other Section 0 definitions that relate to Section 6 are a supply service — the supply conductors as mentioned above, and a service box — an assembly containing an enclosure that can be locked or sealed and containing a switch or breaker that can be opened when the box is closed.There is also one special terminology definition applicable to this section: a transformer rated meter mounting device, a meter mounting device with current transformers that may have test switches mounted in the same enclosure.

The General part of Section 6 deals with the number, arrangement and location of electrical services.

Normally, according to Rule 6-102, only one service is run to a building, however, more than one supply service could be permitted to run to any building provided that each supply service is supplying:
• fire pumps, in acccordance with Section 32
• an industrial establishment, or
• completely self contained row type occupancies, with separate entrances to ground level

The service boxes for such supply services associated with multiple supply services must be grouped, where practicable.Where this is not possible, a permanent diagram must be affixed beside each supply service box indicating where the other service boxes are located. In any case the Appendix B note to this section advises that it is prudent to consult with the supply authority on the number and location of supply services.

Rule 6-104 further provides for a maximum of four consumer's services of the same voltage and characteristics (normally number of phases) run to any one supply service. The following Rules 6-104 to 6-110 discuss rules regarding service supply from more than one system, from an electric railway, and requirements for a 3-wire system where more than two 120 volt circuits are installed.Rules 6-112 to 6-116 outline the requirement for support, clearance, and termination of consumer's service conductors and location of a consumer's service head. The Appendix B notes for this section are very helpful in designing and installing a consumer's service.

The Control and Protective Equipment part of this section specifies how services are controlled, as well as measures for the protection of persons and property.Rules6-200 to 6-204 delineate the need for and for the arrangement of service boxes. Rules 6-206 to 6-214 discuss the location of consumer's service equipment and conductors, the use of oil switches and oil circuit breakers as service switches, wiring space in enclosures, and marking of service switches. Again, note that Appendix B suggests that the local regulatory authority be consulted regarding the locking of service boxes in the 'on' position and regarding the location of service boxes and meter mounting devices, as the supply authority requires access to this service equipment.

The Wiring Methods part of Section 6 has guidelines for the selection, minimum size and installation of consumer's service conductors. Rules6-300 to 6-304 address the installation of underground consumer's service conductors,the installation of overhead consumer's service conductors and the use of mineral insulated and aluminum sheathed cables. Rule6-306specifies that consumer's service raceways must contain only consumer's service conductors, be protected from mechanical damage, and have a minimal cross section size of 21mm. Rules 6-308 to 6-312 treat the use of bare neutral conductors, the use of joints in neutral conductors and the draining of condensation in consumer's service raceways.

The Metering Equipment part gives us the guidelines for selection, arrangement and installation of meters and metering equipment. Metering equipment includes current and potential transformers and associated measuring equipment. Rules 6-402 to 6-410 outline the location and method of installing meter loops, selection and installation of instrument transformer enclosures, disconnecting means for meters,location of meters and the space required for meters.Finally, Rule 6-412 has specifications for metering impedence grounded systems.

These are the specific rules that apply to all services. However, the rules of the other general sections also may apply to services and service equipment selection and installation.

In the next installment:Section 8 – Circuit loading and demand factors.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 - Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 - Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Changing Scene

  • Prev
During the recently held IMARK Canada 2019 meeting in Niagara Falls, executives from 14 of the ...
Valard has been selected by Wataynikaneyap Power LPto provide engineering, procurement ...
The Canadian Apprenticeship Forum-Forum Canadien sur l’Apprentissage (CAF-FCA) has announced ...
Electricity Human Resources Canada has announced this year's keynote speakers for Agents of Change ...
Kiashke Zaaging Anishinaabek (KZA)/Gull Bay First Nation (GBFN) and Ontario Power Generation (OPG) ...
The BCEA's Woman's Network THRIVE Summit is taking place on October 4th at the Executive Inn ...
NSI Industries has announced the acquisition of electrical products manufacturer Bridgeport ...
The National Electrical Trade Council (NETCO)—jointly sponsored by International Brotherhood ...
IDEAL Electrical has launched its fourth annual national competition to find the best ...
IDEAL Industries Canada has announced the appointment of Sean Bernard as Regional Sales Manager to ...

Electrician Forum Brought to you by Schneider Electric

As industry experts you know the products you use everyday better than anyone and should have input on what information you receive about products and what could improve them.

Therefore, we want your insight on the biggest challenges or issues you face when installing loadcentres, breakers (CAFI, GFI's…) and other surge protection devices. We ask that you do not provide product specific details but rather your general issues and concerns or any questions that have come to mind while working with these product types. Provide us with your valued expert insight into the issues you have faced so manufacturers can better inform you about the installation and use of these products. Lets generate some discussion that will help guide the Industry.

Make your comments  HERE

 

SoneparSonepar Canada has announced the launch of new mobile applications for Gescan Vallen, Sesco and Lumen.

The mobile apps were officially released as of June of this year and features barcode scanning, access to pricing, product availability, store locator and much more – 24 hours a day, 7 days a week.

The new mobile app is changing the way customers can interact with the Operating Companies within Sonepar Canada. The barcode scanning functionality is a popular feature amongst customers allowing them to scan an item easily and add it to their cart.

 

Read More

 

 

 

Fredericton Transmission LineNB Power recenly announced it will seek approval to build a new transmission line in the Fredericton area, which will improve the reliability of the power grid in the region for approximately 25, 000 customers.

The new proposed 15-kilometre transmission line will run from the Rainsford Substation, in Fredericton, to the Mactaquac Terminal.

“NB Power strives to offer its customer a reliable power grid that meets or exceeds all utility standards,” said NB Power’s President and CEO, Gaëtan Thomas. “This will increase transmission reliability for customers in the Fredericton region with fewer interruptions that can be restored within minutes rather than hours or days.”

Read More

 

 

Codes and Regulations Brought to You by the CSA Group

  • Prev
The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the ...
The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the ...
In this article: Tables — Part B. This section of the Code contains 99 tables of essential ...
In this article: Section 58 — Passenger Ropeways and Similar Equipment. Rule 58-000 ...
  Unauthorized CSA Group certification marks have been found on wiring by Triumph Cable ...
In this article: Section 52 — Diagnostic imaging installations. The CE code is a ...
In this article: Section 46 — Emergency Power Supply, Unit Equipment, Exit Signs, and ...
  In this article: Section 44 — Theatre Installations. The CE Code is a ...
CSA has published C22.2 No. 60947-7-3, the harmonized standard for low-voltage switchgear and ...
  Electric welders. The CE Code is a comprehensive document. Sometimes it can seem ...

 

Emergency Lighting PrinciplesBy Kevin Smee, Vice President Sales at AimLite

Most of us take light for granted. It has become so ubiquitous and cheap to use that we don’t really stop to think about emergencies. Thankfully most buildings are required by law since 1974 to be equipped with emergency lighting that automatically activates during power failures to facilitate our exit.

Emergency lighting is only one component of a building’s life safety systems, but perhaps one of the most important. 

 

 

Read More  

 

Open Office DesignOpen office design has exploded in popularity over the last 20 years. In fact, the New Yorker magazine claims that approximately 70% of all offices now have an open floor plan.[1]

How did we get here?

Although open offices have been around since the mid-1700s, the cubicle culture developed by Hermann Miller in 1964 became very popular in the 1980s and 1990s. By the early 2000s, open office design started to re-emerge in an effort to encourage more collaboration and Silicon Valley was among the first to embrace sleek, open office workspaces as the norm.

Read More

 

 

Tools for the Trade

  • Prev
  IDEAL Industries has introduced Combination Drill Taps to its tool lineup. Combining the ...
  Stripping and crimping device, 100 - 240 V input voltage, for insulated ferrules with a ...
Professional all-in-one cutter/stripper for coaxial and twisted pair cables     ...
  Klein Tools' Coax Explorrer 2 tests coaxial cable and maps up to 4 locations   ...
  Ideal Industries' T-14 wire stripper s are ideal for all professionals working within the ...
  The ATS850 conveyor eliminates all types of electro static discharge requirements. ...
  Lorik Tool & Automation has the experience and ability to manufacture a variety of ...
  Ideal Industries' 26 piece insulated Journeyman kit is ideal for new electricians or for ...
  Klein Tools Deluxe Fish Rod Set comes in 19 pieces that when assembled can fish wire and ...
  BendWorks Software was designed to help electrical contractors adopt this new process ...

Product News

  • Prev
Standard Stanpro’s LED Tapes work on direct line voltage 120V and can easily be installed ...
Standard Stanpro’s FLUO LED is designed for 120 V applications and is easy and quick to ...
The LCAN series is an indoor and outdoor surface mount with V-type light distribution.   ...
HPS Sentinel G ventilated stand-up distribution transformers meet the latest federally mandated ...
Advanced Performance in a Classic Form Factor The UFIT LED Low Bay is the perfect combination of a ...
The clean and elegant design of EG series 1X4FT led flat panel light provides a modern alternative ...
Signify has announced new smart light products, including an upgraded Hue Go, the Smart button and ...
HomeWorks by Lutron is a lighting and shading control solution for luxury homes.   ...
Signify unveiled its brand-new Philips Hue Filament collection, perfect for those who want to bring ...
These LED lamps are designed to meet or exceed the standards set out in the California Energy ...

 

EikoThese LED lamps are designed to meet or exceed the standards set out in the California Energy Commission’s Title 20 and Title 24 (JA8) Appliance Efficiency Regulations.

FEATURES

  • MR16 GU5.3 and GU10 base; B11 Decorative E12 and E26 base
  • 80% more efficient and 30x longer life than standard incandescent
  • Shatter-resistant plastic housing for reduced risk of injury and breakage
  • Compatible with a wide array of dimmers
  • ANSI construction compliant

Read More

 

 

Peers & Profiles

  • Prev
Ali Heighton is the Program Coordinator for IBEW Local 37 who has found success as a young ...
Flextherm was founded in 1991 by current company President, Philippe Charron. For more than 25 ...
Ouellet Electric Heating began humbly in 1960 with Charles-Emile Ouellet, who started manufacturing ...
Justin Harris is a Programmer/Electrician for COREngineering, a New Brunswick based mechanical ...
Bill Maki is an Electrical Engineer from Thunder Bay, Ontario working as a Control Systems ...
Benedict Electrical Contracting Limited is a locally owned and operated family business in Owen ...
Spark Power Corp. is one of North America’s leading independent providers of integrated ...
Marcia Ranger is a master construction and maintenance electrician, as well as a college professor ...
Con’s Electric Company Limited was established in 1985. Based in Timmins Ontario, only 700 ...
Mark Unsworth is an electrical engineer with over 35 years of experience in project management, ...

Copper $US Dollar price per pound

Kerrwil Publications

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2019 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil