Wiring MethodsWilliam (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.In this article: Section 12 — Wiring Methods.

It should be noted that while many other sections of the code are commonly used by designers, installers and regulators, Section 12 is mostly used byelectricians, who must clearly understand all aspects of wiring, and by electrical inspectors, who audit compliance of the wiring methods with the code requirements. Electrical inspection authorities must always be consulted on specific issues related to wiring methods.

Section 12 is a general section and applies to all wiring installations except for
•    Class 2 circuits
•    community antenna distribution and radio and television circuits
•    opticalfibre cables
•    communication circuit conductors
•    conductors integral to factory-built equipment

That is, unless specified in the respective code sections covering those type of installations. We will discuss this later when dealing with Sections 16, 54, 56, and 60in future instalments.

The rules of this section may also be modified by the provisions of Section 32 — Fire alarm systems, Section 36 — High voltage installations or Section 45 — Emergency power supply, unit equipment exit signs and life safety systems.

Section 12 of the Code is divided into six parts:
•    General Requirements
•    Conductors
•    Raceways
•    Cablebus
•    Manufactured wiring systems
•    Installation of boxes, cabinets, outlets and terminal fittings

Generally the definitions in Section 0 apply throughout, but there are some special terminology definitions in the sub-section rules covering flat conductor cable type FCC.

In the General Requirements part, rules 12-010 to 12-020 apply specifically to locations where fire, mechanical, moisture or other environmental issues must be considered or locations where wiring may be prohibited, such as ducts and plenum chambers, underground installations, hoistways, lightning down conductors, entry of raceways and cables into buildings, and wiring under raised floors for data processing.

The Conductors part includes the rules applying to the installation of all types of conductors.It is divided into a general subdivision and individual subdivisions for each type of conductor.

In the General subdivision of Conductors,Rule 12-100 establishes that types of conductors must be chosen for their location with respect to moisture, corrosive action, temperature, degree of enclosure and mechanical protection as set out in Table 19. The Appendix B notes offer additional specifications on choosing the appropriate type of conductor.

Rules 12-102 to 12-120 provide general considerations for the installation of all conductors, such as:
•    the treatment of insulated conductors
•    flame test coverings
•    multi- and single-conductor cables
•    conductors in parallel
•    radii of bends in conductors
•    conductor joints and splices
•    treatment of the ends of insulated conductors
•    termination of conductors
•    termination and splicing of aluminum conductors
•    supporting of conductors

You will find, again, that extensive notes in Appendix B provide additional helpful information, including a diagram outlining configurations for installing parallel conductors.

The rest of the Conductor subdivision deals with the rules for specific types of conductors:
•    open wiring Rules 12-200 to 12-224 apply to single conductors run as open wiring (colloquially referred to as “knob and tube wiring”)
•    exposed wiring on exteriors of buildings and between buildings on the same premises —Rules 12-302 to 12-318
•    barebusbars and risers —Rules 12-400
•    non-metallic-sheathed-cable: Rules 12-500 to 12-526 (NMSC)
•    armoured cable —Rules 12-600 to 12-618
•    mineral-insulated cable, aluminum-sheathed cable, and copper-sheathed cable —Rules 12-700 to 12-716
•    flat conductor cable Type FCC —Rules 12-800 to 12-824

The third part, Raceways, includes the rules applying to the installation of all types of raceways.It is divided into a general subdivision and subdivisions for each type of raceway.

The General subdivision,Rules 12-902 to 12-944, governs the installation of all
•    raceways and conductors run in raceways
•    types of conductors and cable suitable for use in raceways as per Table 19
•    conductors in raceways
•    protection of conductors at the ends of raceways
•    inserting conductors in raceways
•    conductors, in conduit and tubing
•    joints or splices within raceways
•    stranding of conductors, electrical continuity of raceways
•    mechanical continuity of raceways
•    junction of open wiring and raceways
•    entry of underground conduits into buildings
•    raceways installed underground or where moisture may accumulate
•    metal raceways in plaster
•    protection for raceways installed in concrete, cinder concrete, and cinder fill
•    raceways completely installed before conductors are installed
•    capping of unused raceways
•    maximum number of bends in raceways
•    metal raceways embedded in slabs, pavement or roadbeds

The rest of the Raceways part documents the rules for specific types of raceways:
•    rigid and flexible metal conduit:Rules 12-1000 to 12-1014
•    rigid PVC conduit: Rules 12-1100 to 12-1124
•    rigid types EB1 and DB2/ES2 PVC conduit: Rules 12-1150 to 12-1166
•    rigid RTRC conduit: Rules 12-1200 to 12-1220
•    liquid-tight flexible conduit: Rules 12-1300 to 12-1308
•    electrical metallic tubing: Rules 12-1400 to 12-1414
•    electrical non-metallic tubing: Rules 12-1500 to 12-1514
•    surface raceways: Rules 12-1600 to 12-1614
•    underfloor raceways: Rules 12-1700 to 12-1718
•    cellular floors: Rules 12-1800 to 12-1820
•    auxiliary gutters: Rules 12-1900 to 12-1904
•    busways and splitters: Rules 12-2000 to 12-2020
•    wireways: Rules 12-2100 to 12-2112
•    cable trays: Rules 12-2200 to 12-2210

The fourth part, Cablebus, includes the rules applying to the installation of cablebus as a complete system.Rules 12-2252 to 12-2260 include:
•    the use of Cablebus
•    methods of installation
•    connection to other wiring methods
•    provisions for bonding
•    ampacities of conductors in cablebus

The fifth part, Manufactured wiring systems, includes Rules 12-2500 and 12-2502 specifying the uses permitted, and Installation of Manufactured wiring systems

The sixth sub-section, Installations of boxes, cabinets, outlets, and terminals, includes Rules 12-3000 to 12-3036 that cover
•    outlet boxes
•    outlet box covers
•    terminal fittings
•    terminal fittings behind switchboards
•    boxes in concrete construction
•    outlet box supports, boxes, cabinets and fitting supports
•    accessibility of junction boxes, outlet boxes, cabinets and fittings
•    outlet boxes attached to existing plaster work
•    outlet boxes, etc., in damp places
•    entrance of conductors into boxes, cabinets and fittings
•    unused openings in boxes, cabinets, and fittings
•    extensions from existing outlets
•    multi-outlet assemblies
•    conductors in boxes, cabinets or fittings
•    wiring space in enclosures
•    maximum number of conductors in a box,
•    pull box or junction box sizes

 In the next installment we will be discussing Section 14 — Protection and control.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 - Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 - Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Contractors! You Deserve Better.

You Deserve BetterContractors! You Deserve Better | Win $2,000 Grand Prize from LEDVANCE, THE WORLD'S LEADING VERTICALLY INTEGRATED LIGHTING COMPANY

OFFERING SYLVANIA AND LEDVANCE BRANDED LIGHTING PRODUCTS IN CANADA


You deserve better and LEDVANCE wants to make sure you know it. Enter for a chance to be one of over 190 winners with the grand prize including $2000 and a SYLVANIA Work Light!

Read More


Changing Scene

  • Prev
E.B. Horsman & Son (EBH) has announced their Victoria branch has moved to a new location as ...
Canada’s Building Trades Unions has been selected as an intermediary for the Apprenticeship Service ...
More skilled trades workers can seek certification in Nova Scotia with changes the Province is ...
Procore Technologies, Inc. has announced it is working with Amazon Web Services (AWS) to ...
The federal governemnt has officially launched a call for proposals (CFP) for the  ...
The Electrical Contractors Association of BC (ECABC) has announced the impending departure of ...
The Minister of Employment, Workforce Development and Disability Inclusion, Carla Qualtrough was at ...
The launch of the Apprenticeship Service stands to help overcome financial barriers employers face ...
The National Electrical Trade Council (NETCO) is pleased to announce that they will be rolling out ...
43 years ago, Steve Silverstein bought a table saw and a delivery van and began a revolution in the ...


Government of CanadaThe federal governemnt has officially launched a call for proposals (CFP) for the Zero-Emission Vehicle Awareness Initiative (ZEVAI). The initiative’s 2022 CFP will help fund new and innovative projects that aim to increase awareness and knowledge of ZEVs and charging and refueling infrastructure thereby increasing public confidence in these vehicles and their economic and environmental benefits.


Natural Resources Canada will provide funding through non-repayable contributions of between 50 and 75 percent of the total eligible project costs, with a maximum funding of up to $300,000 per project. The CFP will close on August 18, 2022.

Read more


 

Omnicable joins ETIMETIM North America announced that OmniCable has joined the product classification standards organization. Headquartered in West Chester, PA, OmniCable has 24 locations throughout North America, and also owns Houston Wire & Cable (HWC). The company partners with many electrical manufacturers and only sells to distributors.

According to John Dean, Director of Marketing & E-Commerce, OmniCable/HWC, “The wire and cable industry is often called commodities, but there are very distinct features and attributes for the different products our manufacturers produce. 

Read More

 


 

Atkore United Poly SystemsAtkore Inc. announced that it has acquired United Poly Systems, a manufacturer of High Density Polyethylene (HDPE) pressure pipe and conduit, primarily serving telecom, water infrastructure, renewables, and energy markets.

“We are pleased to complete the acquisition of United Poly Systems, which strengthens Atkore’s product portfolio, expands our manufacturing capacity and further enables us to meet HDPE customers’ needs,” stated John Pregenzer, President of Atkore’s Electrical business. “HDPE pipe and conduit is a growing market that is expected to benefit from U.S. infrastructure legislation, and United Poly Systems is a great addition to Atkore. We welcome these employees and look forward to working together to continue to serve and support our customers.”

Read More


 

Canadian Electrical Contractor Discussion Group: Can You Count the Deficiencies?

EIN CECD 400Have you ever been called to fix the work of a 'handyman'?

"Was supposedly done by a"certified ' electrician....told the homeowner that he got a $266 permit....no record at TSBC. Can you count the deficiencies?"

"There is a second panel change in the triplex also.......even more deficiencies. Think the guy was a glorified handyman. Ones not obvious: 240 BB heat hooked up 120....drier on 2p20....range on 2p50....water heater fed with 2c14 Bx on 2p15."

Go HERE to join the discussion

 


 

Grimard is more competitive and produces estimates 3X faster with Procore

Procore

When the pandemic lockdowns started in March of 2020, Grimard (an electrical contractor) had to decide whether to shut down its operations entirely or implement a new platform with people who were now freely available for work. Once they implemented Procore, they found a way to efficiently communicate with stakeholders and offer full transparency in terms of project costs and planning. It also allowed Grimard to utilize historical data to make project estimates more accurate. Grimard was able to streamline its bidding process, which made it more attractive to potential clients and helped the business grow.

Read More


 



 

Iron+EarthThe RenuWell Project partners are excited to announce the groundbreaking of two pilot sites located near Taber, Alberta. These pilot sites are the first of their kind to repurpose inactive oil and gas infrastructure as a foundation for renewable energy development and job creation.

When operating, the solar projects will generate 2,030 MWh annually – enough electricity to power 280 average Alberta households or irrigate 11,700 acres of farmland for an average year. This is roughly equivalent to $200,000 in electricity sales per year with 1,100  tCO2e savings in GHG emissions. Over a 25-year lifespan, the projects will generate 50,750 MWh, with GHG emission savings of 28,420 tCO2e.

Read More


 

David O'ReillyBy Elle Bremmer

Recently, I had the pleasure of sitting down with David O’Reilly, Vice President Home & Distribution and Secure Power Divisions with Schneider Electric Canada for a discussion regarding the Wiser EnergyTM smart home solution, the Wiser Approved training program, and his thoughts on several different subjects, including sustainability and future technologies currently in the works at Schneider Electric. David has been with the company for five and a half years in his role.

We recently published a study (version en français ICI) from Schneider Electric showing a strong interest from Canadians in smart home technology. 

Read More


 

Product News

  • Prev
Ericson has launched upgraded versions of their line of Harsh and Hazardous Lighting Solutions. ...
Designed for quick and easy installation, this strong and durable baseboard is easily recognizable ...
The Lithonia Lighting® ESXF LED Floodlight is an all-in-one flood that gives ultimate versatility ...
STARFISH WiFi enabled mobile app controlled. Customize and save various light scenes or utilize the ...
The 8540 Pro profile is designed to disappear into the structure, merging the light source with the ...
Keystone’s DirectDrive DX2 is a UL Type B line voltage tube offering single- or double-ended wiring ...
This voluminous Hubbell® Gangable Device Box offers smooth flat external sides and flush ears that ...
The EarthTronics LED Adjustable Wall Packs has a slim profile design. They can be locked into any ...
Klein Tools introduces new phone Thermal Imagers, one for Android® Devices and one for iOS Devices, ...
The tri-power countertop pop-up receptacle from Hubbell Wiring Device - Kellems® provides power ...


Ericson String LightsEricson announces upgraded versions of their extremely capable line of Industrial String Lights and SL, LED Stringlights. These new and updated products have several key features important when safe, code compliant lighting for industrial workspace is necessary.

Infinitely capable, these ruggedly built products have several industry leading & exclusive features including:

Industrial String Lights:

  • A United States Navy Specification since before WWII, they’re time and application tested...

 

Read More


 

 

Intermatic Pool and Spa SolutionIntermatic Incorporated announced its new P40000 Series Load Centers, a set of next-generation panels for pool-only applications, as well as its new PE24GVA 24-Volt Valve Actuator, an easy-to-install valve actuator that allows for tool-free cam adjustments. Both solutions remove obstacles for pool service professionals while delivering lasting performance.

“Intermatic load centers and valve actuators have been the preferred choice of pool professionals for more than 30 years,” says Brian Lamberty, product marketing manager at Intermatic. “The PE24GVA and P40000 Series build on that tradition, helping pool professionals streamline service calls while setting the standard for quality and performance.”

Read More


 

 

Klein Tools Zipper BagsKlein Tools introduces new Stand-up Zipper Bags, in a 2-Pack with 7-Inch and 14-Inch sizes, both designed to handle tough jobsite conditions and stand up so tools and small parts can be easily accessed when working.

Stand-up Zipper Bags, 7-Inch and 14-Inch, 2-Pack (Cat. No. 55559)

  • Perfect for storing pliers, wrenches, screwdrivers, drill bits and other small tools and parts
  • 4 1/2’’ tall zipper bags come in two sizes:
    • 14’’ (36.6 cm) dark gray
    • 7’’ (17.8 cm) royal blue


Read More


 

Emerson HV SafetyThe Occupational Safety and Health Administration (OSHA) estimates 350 employees are killed annually in electrocution accidents, which roughly equals one fatality per day. In the face of these dangers, OSHA officials and industry safety consultants alike recommend eliminating potential hazards on work sites, rather than simply relying on contractors or employees to follow safety guidelines.

To help safeguard employees from electrocution, Emerson has launched its Appleton™ Powertite™ Lock Collar, a device that fastens over plug and connector connections and is secured with a padlock, preventing unauthorized personal from disconnecting the cable connection once in place. 

Read More


 

Peers & Profiles

  • Prev
Watt’s the Word is a recently launched Electrical Industry Podcast hosted by Zack Hartle and ...
Allana Kellett-Jamieson loves working in the electrical sector and is proud of the great focus ...
As the head of ABB Canada's electrification business unit, Éric Deschênes is no newcomer to the ...
Karen Pullen knows what it’s like to be the only woman on a construction site, and as a proud ...
As of February 2021, Martin Stephenson is the new President and CEO of Signify Canada.   ...
This past July, Kerith Richards, who has worked for Service Wire Company for the last seven years, ...
EngWorks was formed in 2004 as an electrical engineering and consulting firm by Allan Bozek, “After ...
Headquartered in Concord, Ontario, Mercury Lighting services national retail, ...
Among the recipients of the 2021 Clean50 Awards announced last month is Carolina Gallo, Vice ...
Sarah Silverstein is a principal with Liteline along side her two brothers Mark and Daniel. ...

Copper $US Dollar price per pound

Kerrwil Publications Great Place to Work. Certified December 2019 - December 2020

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2022 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil