Wiring MethodsWilliam (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.In this article: Section 12 — Wiring Methods.

It should be noted that while many other sections of the code are commonly used by designers, installers and regulators, Section 12 is mostly used byelectricians, who must clearly understand all aspects of wiring, and by electrical inspectors, who audit compliance of the wiring methods with the code requirements. Electrical inspection authorities must always be consulted on specific issues related to wiring methods.

Section 12 is a general section and applies to all wiring installations except for
•    Class 2 circuits
•    community antenna distribution and radio and television circuits
•    opticalfibre cables
•    communication circuit conductors
•    conductors integral to factory-built equipment

That is, unless specified in the respective code sections covering those type of installations. We will discuss this later when dealing with Sections 16, 54, 56, and 60in future instalments.

The rules of this section may also be modified by the provisions of Section 32 — Fire alarm systems, Section 36 — High voltage installations or Section 45 — Emergency power supply, unit equipment exit signs and life safety systems.

Section 12 of the Code is divided into six parts:
•    General Requirements
•    Conductors
•    Raceways
•    Cablebus
•    Manufactured wiring systems
•    Installation of boxes, cabinets, outlets and terminal fittings

Generally the definitions in Section 0 apply throughout, but there are some special terminology definitions in the sub-section rules covering flat conductor cable type FCC.

In the General Requirements part, rules 12-010 to 12-020 apply specifically to locations where fire, mechanical, moisture or other environmental issues must be considered or locations where wiring may be prohibited, such as ducts and plenum chambers, underground installations, hoistways, lightning down conductors, entry of raceways and cables into buildings, and wiring under raised floors for data processing.

The Conductors part includes the rules applying to the installation of all types of conductors.It is divided into a general subdivision and individual subdivisions for each type of conductor.

In the General subdivision of Conductors,Rule 12-100 establishes that types of conductors must be chosen for their location with respect to moisture, corrosive action, temperature, degree of enclosure and mechanical protection as set out in Table 19. The Appendix B notes offer additional specifications on choosing the appropriate type of conductor.

Rules 12-102 to 12-120 provide general considerations for the installation of all conductors, such as:
•    the treatment of insulated conductors
•    flame test coverings
•    multi- and single-conductor cables
•    conductors in parallel
•    radii of bends in conductors
•    conductor joints and splices
•    treatment of the ends of insulated conductors
•    termination of conductors
•    termination and splicing of aluminum conductors
•    supporting of conductors

You will find, again, that extensive notes in Appendix B provide additional helpful information, including a diagram outlining configurations for installing parallel conductors.

The rest of the Conductor subdivision deals with the rules for specific types of conductors:
•    open wiring Rules 12-200 to 12-224 apply to single conductors run as open wiring (colloquially referred to as “knob and tube wiring”)
•    exposed wiring on exteriors of buildings and between buildings on the same premises —Rules 12-302 to 12-318
•    barebusbars and risers —Rules 12-400
•    non-metallic-sheathed-cable: Rules 12-500 to 12-526 (NMSC)
•    armoured cable —Rules 12-600 to 12-618
•    mineral-insulated cable, aluminum-sheathed cable, and copper-sheathed cable —Rules 12-700 to 12-716
•    flat conductor cable Type FCC —Rules 12-800 to 12-824

The third part, Raceways, includes the rules applying to the installation of all types of raceways.It is divided into a general subdivision and subdivisions for each type of raceway.

The General subdivision,Rules 12-902 to 12-944, governs the installation of all
•    raceways and conductors run in raceways
•    types of conductors and cable suitable for use in raceways as per Table 19
•    conductors in raceways
•    protection of conductors at the ends of raceways
•    inserting conductors in raceways
•    conductors, in conduit and tubing
•    joints or splices within raceways
•    stranding of conductors, electrical continuity of raceways
•    mechanical continuity of raceways
•    junction of open wiring and raceways
•    entry of underground conduits into buildings
•    raceways installed underground or where moisture may accumulate
•    metal raceways in plaster
•    protection for raceways installed in concrete, cinder concrete, and cinder fill
•    raceways completely installed before conductors are installed
•    capping of unused raceways
•    maximum number of bends in raceways
•    metal raceways embedded in slabs, pavement or roadbeds

The rest of the Raceways part documents the rules for specific types of raceways:
•    rigid and flexible metal conduit:Rules 12-1000 to 12-1014
•    rigid PVC conduit: Rules 12-1100 to 12-1124
•    rigid types EB1 and DB2/ES2 PVC conduit: Rules 12-1150 to 12-1166
•    rigid RTRC conduit: Rules 12-1200 to 12-1220
•    liquid-tight flexible conduit: Rules 12-1300 to 12-1308
•    electrical metallic tubing: Rules 12-1400 to 12-1414
•    electrical non-metallic tubing: Rules 12-1500 to 12-1514
•    surface raceways: Rules 12-1600 to 12-1614
•    underfloor raceways: Rules 12-1700 to 12-1718
•    cellular floors: Rules 12-1800 to 12-1820
•    auxiliary gutters: Rules 12-1900 to 12-1904
•    busways and splitters: Rules 12-2000 to 12-2020
•    wireways: Rules 12-2100 to 12-2112
•    cable trays: Rules 12-2200 to 12-2210

The fourth part, Cablebus, includes the rules applying to the installation of cablebus as a complete system.Rules 12-2252 to 12-2260 include:
•    the use of Cablebus
•    methods of installation
•    connection to other wiring methods
•    provisions for bonding
•    ampacities of conductors in cablebus

The fifth part, Manufactured wiring systems, includes Rules 12-2500 and 12-2502 specifying the uses permitted, and Installation of Manufactured wiring systems

The sixth sub-section, Installations of boxes, cabinets, outlets, and terminals, includes Rules 12-3000 to 12-3036 that cover
•    outlet boxes
•    outlet box covers
•    terminal fittings
•    terminal fittings behind switchboards
•    boxes in concrete construction
•    outlet box supports, boxes, cabinets and fitting supports
•    accessibility of junction boxes, outlet boxes, cabinets and fittings
•    outlet boxes attached to existing plaster work
•    outlet boxes, etc., in damp places
•    entrance of conductors into boxes, cabinets and fittings
•    unused openings in boxes, cabinets, and fittings
•    extensions from existing outlets
•    multi-outlet assemblies
•    conductors in boxes, cabinets or fittings
•    wiring space in enclosures
•    maximum number of conductors in a box,
•    pull box or junction box sizes

 In the next installment we will be discussing Section 14 — Protection and control.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 - Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 - Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

 The Evolution Series. Poke-Thru Devices, Floor, Wall and Ceiling Boxes 

Legrand Wiremold EvoFrom poke-thru devices to floor, wall and ceiling boxes, the Evolution Series has continued to increase device efficiency and reliability while providing durability and quality. Customizing your space and maximizing access to all the power, A/V and communications you could ever need. Evolution Series boxes bring power, communications and A/V to walls, floors and ceilings. Evolution adds flexibility, functionality and stylish good looks to every room you create when planning office buildings, airports, schools and hospitals.

 

 

Watch the video Here

 

Changing Scene

  • Prev
Prior to joining ABB in 2017 as Executive Vice President of the Electrification business, Deschenes ...
Susan Uthayakumar, country president, Schneider Electric, has been named a Women's Executive ...
ABB presented its electrification solutions that will allow customers to take full advantage of the ...
Electricity Human Resources Canada has introduced a new Board of Directors, effective as of their ...
Jacques Fiset, the new president of the EFC Quebec section, told us in a recent interview that his ...
Organised by the Hong Kong Trade Development Council (HKTDC), the twin lighting shows - the  ...
A Friday night, the end of summer, the weather is mild, and 2,500 people — customers, ...
Eaton focuses on developing personable connections in every aspect. In September, our team will be ...
During the recently held IMARK Canada 2019 meeting in Niagara Falls, executives from 14 of the ...
Valard has been selected by Wataynikaneyap Power LPto provide engineering, procurement ...

Alta EnergyAlta Energy has completed the installation of solar power systems at 14 campuses across California’s Poway Unified School District (PUSD). Alta Energy installed a total of 632 kilowatts (kW) on 65 of PUSD’s standard 24 by 40 feet relocatable, portable classrooms. Financed through a power purchase agreement (PPA) with no out-of-pocket costs to the district, the project reduces PUSD’s electricity expenses by nearly 15 percent and will save the district $250,000 per year.

 

 

Read More

 

 

 

Connected SecurityClimate change, a dwindling supply of natural raw materials, continuous migration to the metropolises: tomorrow’s challenges can only be solved with intelligent, networked buildings, so called smart buildings.

Networking encompasses all parts of a building — from the electricity supply, taking account of regenerative energy (smart grid), via safety and security technology and operational regulation through interconnected building-automation systems, to control via mobile devices. The prerequisite for all this is systems interoperability, the only way network risks can be mastered.

Read More

 

 

Tools for the Trade

  • Prev
  IDEAL Industries has introduced Combination Drill Taps to its tool lineup. Combining the ...
  Stripping and crimping device, 100 - 240 V input voltage, for insulated ferrules with a ...
Professional all-in-one cutter/stripper for coaxial and twisted pair cables     ...
  Klein Tools' Coax Explorrer 2 tests coaxial cable and maps up to 4 locations   ...
  Ideal Industries' T-14 wire stripper s are ideal for all professionals working within the ...
  The ATS850 conveyor eliminates all types of electro static discharge requirements. ...
  Lorik Tool & Automation has the experience and ability to manufacture a variety of ...
  Ideal Industries' 26 piece insulated Journeyman kit is ideal for new electricians or for ...
  Klein Tools Deluxe Fish Rod Set comes in 19 pieces that when assembled can fish wire and ...
  BendWorks Software was designed to help electrical contractors adopt this new process ...

Product News

  • Prev
Boost your or your team’s performance with 320 x 240 resolution.      
Littelfuse power control, and sensing, announced today the expansion of its SPXI series in-line and ...
The USB Rechargeable Low-Profile Headlamp is powered by REDLITHIUM USB and delivers 600-lumens of ...
Klein Tools' new 546 Watt hour Portable Power Station give professionals a clean, quiet alternative ...
SVL Series power supplies are perfect for high volume, controlled environment applications where ...
The M18 ROCKET Dual Power Tower Light is providing more light on the job with 2,500 lumens of ...
Plants, products, and systems are becoming increasingly networked. This has resulted in a major ...
A sophisticated luminaire that delivers outstanding performance up to 19412 lumens with maximum ...
Ledalite recently intrduced the ModiFly wall mount, allowing you to achieve beautiful wall ...
The Pipeline series begins with a linear LED light, elegant in its simplicity; however what sets it ...

 

Greenlee Versi-Tugger Handheld PullerEmerson announced the addition of a handheld puller to its Greenlee pulling lineup – the new G1 Versi-Tugger. The versatile and portable G1 is designed for pulls normally done by hand and can pull up to 68-percent faster when compared to manual pulling.

“We engineered and built G1 based on honest feedback from professionals,” said Adele Hendrix, product manager for Greenlee, Emerson. “We learned being fast wasn’t only about pull speed. From setup and pulling to unspooling the line after – the entire process should be quicker than pulling by hand. Our design delivers that speed.”

 

 

Read More

 

 

SICK SIM10xxAs part of the SICK AppSpace eco-system, the programmable SIM10xx Sensor Integration Machines offer multiple sensor data acquisition and fusion processes, thereby providing space for new application solutions. The acquired data is processed and visualized for important information, for example quality control or process analysis. In addition, the IoT gateway functions enable connection from the edge to the cloud via the Internet in the context of Industry 4.0. The SIM10xx products feature a powerful processor and Ethernet interfaces for cameras and LiDAR sensors. Other sensors can be integrated via IO-Link, for instance for distance and height measuring purposes.

 

Read More

 

Peers & Profiles

  • Prev
Chad Alexander is a Branch Manager with Contact Automation, which provides automation integration ...
Rob Milner is the Canadian National Science, Automation, Optical Gas Imaging & sUAS Manager for ...
EIN sat down with WiRE President & CEO Joanna Osawe to learn more about WiRE and the ...
For the second consecutive year, Paul Hannania was among the 162 professionals and apprentices to ...
Alexander Couckuyt, Director of Operations for Southwire Canada, spent the majority of his ...
Stephanie Medeiros leads ABB Canada’s Electric Vehicle Charging Infrastructure team, as well ...
Electrical Industry Canada had the pleasure of interviewing Matt Davis of Newfoundland Power, ...
An electrician by trade, Daniel Lacovetsky is the founder and President of Powertec Electric, an ...
Mike Morneau began his professional career in graphic arts after earning a Bachelor of Technology ...
AimLite offers a vast choice of lighting lines to facilitate any lighting project’s needs. ...

 

Paul HannaniaBy Blake Marchand

Held from November 7th to 9th in Orlando, Florida, the Ideal National Championships gives electricians a chance to display their skills in a high-level competition. For the first time, the event expanded internationally — over 55,000 electricians from 5 countries attempted to qualify for a chance to compete in the championship event.

For the second consecutive year, Paul Hannania was among the 162 professionals and apprentices to compete in the National competition. 

 

Read More

 

 

Copper $US Dollar price per pound

Kerrwil Publications

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2019 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil