The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.In this article: Section 12 — Wiring Methods.

It should be noted that while many other sections of the code are commonly used by designers, installers and regulators, Section 12 is mostly used byelectricians, who must clearly understand all aspects of wiring, and by electrical inspectors, who audit compliance of the wiring methods with the code requirements. Electrical inspection authorities must always be consulted on specific issues related to wiring methods.

Section 12 is a general section and applies to all wiring installations except for
•    Class 2 circuits
•    community antenna distribution and radio and television circuits
•    opticalfibre cables
•    communication circuit conductors
•    conductors integral to factory-built equipment

That is, unless specified in the respective code sections covering those type of installations. We will discuss this later when dealing with Sections 16, 54, 56, and 60in future instalments.

The rules of this section may also be modified by the provisions of Section 32 — Fire alarm systems, Section 36 — High voltage installations or Section 45 — Emergency power supply, unit equipment exit signs and life safety systems.

Section 12 of the Code is divided into six parts:
•    General Requirements
•    Conductors
•    Raceways
•    Cablebus
•    Manufactured wiring systems
•    Installation of boxes, cabinets, outlets and terminal fittings

Generally the definitions in Section 0 apply throughout, but there are some special terminology definitions in the sub-section rules covering flat conductor cable type FCC.

In the General Requirements part, rules 12-010 to 12-020 apply specifically to locations where fire, mechanical, moisture or other environmental issues must be considered or locations where wiring may be prohibited, such as ducts and plenum chambers, underground installations, hoistways, lightning down conductors, entry of raceways and cables into buildings, and wiring under raised floors for data processing.

The Conductors part includes the rules applying to the installation of all types of conductors.It is divided into a general subdivision and individual subdivisions for each type of conductor.

In the General subdivision of Conductors,Rule 12-100 establishes that types of conductors must be chosen for their location with respect to moisture, corrosive action, temperature, degree of enclosure and mechanical protection as set out in Table 19. The Appendix B notes offer additional specifications on choosing the appropriate type of conductor.

Rules 12-102 to 12-120 provide general considerations for the installation of all conductors, such as:
•    the treatment of insulated conductors
•    flame test coverings
•    multi- and single-conductor cables
•    conductors in parallel
•    radii of bends in conductors
•    conductor joints and splices
•    treatment of the ends of insulated conductors
•    termination of conductors
•    termination and splicing of aluminum conductors
•    supporting of conductors

You will find, again, that extensive notes in Appendix B provide additional helpful information, including a diagram outlining configurations for installing parallel conductors.

The rest of the Conductor subdivision deals with the rules for specific types of conductors:
•    open wiring Rules 12-200 to 12-224 apply to single conductors run as open wiring (colloquially referred to as “knob and tube wiring”)
•    exposed wiring on exteriors of buildings and between buildings on the same premises —Rules 12-302 to 12-318
•    barebusbars and risers —Rules 12-400
•    non-metallic-sheathed-cable: Rules 12-500 to 12-526 (NMSC)
•    armoured cable —Rules 12-600 to 12-618
•    mineral-insulated cable, aluminum-sheathed cable, and copper-sheathed cable —Rules 12-700 to 12-716
•    flat conductor cable Type FCC —Rules 12-800 to 12-824

The third part, Raceways, includes the rules applying to the installation of all types of raceways.It is divided into a general subdivision and subdivisions for each type of raceway.

The General subdivision,Rules 12-902 to 12-944, governs the installation of all
•    raceways and conductors run in raceways
•    types of conductors and cable suitable for use in raceways as per Table 19
•    conductors in raceways
•    protection of conductors at the ends of raceways
•    inserting conductors in raceways
•    conductors, in conduit and tubing
•    joints or splices within raceways
•    stranding of conductors, electrical continuity of raceways
•    mechanical continuity of raceways
•    junction of open wiring and raceways
•    entry of underground conduits into buildings
•    raceways installed underground or where moisture may accumulate
•    metal raceways in plaster
•    protection for raceways installed in concrete, cinder concrete, and cinder fill
•    raceways completely installed before conductors are installed
•    capping of unused raceways
•    maximum number of bends in raceways
•    metal raceways embedded in slabs, pavement or roadbeds

The rest of the Raceways part documents the rules for specific types of raceways:
•    rigid and flexible metal conduit:Rules 12-1000 to 12-1014
•    rigid PVC conduit: Rules 12-1100 to 12-1124
•    rigid types EB1 and DB2/ES2 PVC conduit: Rules 12-1150 to 12-1166
•    rigid RTRC conduit: Rules 12-1200 to 12-1220
•    liquid-tight flexible conduit: Rules 12-1300 to 12-1308
•    electrical metallic tubing: Rules 12-1400 to 12-1414
•    electrical non-metallic tubing: Rules 12-1500 to 12-1514
•    surface raceways: Rules 12-1600 to 12-1614
•    underfloor raceways: Rules 12-1700 to 12-1718
•    cellular floors: Rules 12-1800 to 12-1820
•    auxiliary gutters: Rules 12-1900 to 12-1904
•    busways and splitters: Rules 12-2000 to 12-2020
•    wireways: Rules 12-2100 to 12-2112
•    cable trays: Rules 12-2200 to 12-2210

The fourth part, Cablebus, includes the rules applying to the installation of cablebus as a complete system.Rules 12-2252 to 12-2260 include:
•    the use of Cablebus
•    methods of installation
•    connection to other wiring methods
•    provisions for bonding
•    ampacities of conductors in cablebus

The fifth part, Manufactured wiring systems, includes Rules 12-2500 and 12-2502 specifying the uses permitted, and Installation of Manufactured wiring systems

The sixth sub-section, Installations of boxes, cabinets, outlets, and terminals, includes Rules 12-3000 to 12-3036 that cover
•    outlet boxes
•    outlet box covers
•    terminal fittings
•    terminal fittings behind switchboards
•    boxes in concrete construction
•    outlet box supports, boxes, cabinets and fitting supports
•    accessibility of junction boxes, outlet boxes, cabinets and fittings
•    outlet boxes attached to existing plaster work
•    outlet boxes, etc., in damp places
•    entrance of conductors into boxes, cabinets and fittings
•    unused openings in boxes, cabinets, and fittings
•    extensions from existing outlets
•    multi-outlet assemblies
•    conductors in boxes, cabinets or fittings
•    wiring space in enclosures
•    maximum number of conductors in a box,
•    pull box or junction box sizes

 In the next installment we will be discussing Section 14 — Protection and control.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 - Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 - Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Changing Scene

  • Prev
This ECAA Annual Training Day & AGM hybrid event will take place May 27th – May 29th. ...
Technical Safety BC has reviewed the 2021 Canadian Electrical Code (CE Code) to assess the impacts ...
The Government of Canada is providing close to $5 million, over five years, to the National ...
Applications are now open online for the Increased Employment Incentive (IEI), which ...
As a non-profit organization, Skills Ontario relies on the support of partners to continue ...
Ideal Supply is proud to announce that as of January 1, 2021 they have appointed a new Sales ...
The energy storage ecosystem and the regulatory environment in which it operates are evolving ...
It's April, which means it's time for you to ignite your competitive spark with the a new challenge ...
MP Scott Duvall has introduced an amendment to the Income Tax Act regarding travel expenses for ...
George Brown College has partnered with Hilti (Canada) Corporation to help women build rewarding ...


 

www.liteline.com

 

 

 

 


 

Canadian Electrical Contractor Discussion Group: Can You Count the Deficiencies?

EIN CECD 400Have you ever been called to fix the work of a 'handyman'?

"Was supposedly done by a"certified ' electrician....told the homeowner that he got a $266 permit....no record at TSBC. Can you count the deficiencies?"

"There is a second panel change in the triplex also.......even more deficiencies. Think the guy was a glorified handyman. Ones not obvious: 240 BB heat hooked up 120....drier on 2p20....range on 2p50....water heater fed with 2c14 Bx on 2p15."

Go HERE to join the discussion

 


 

Ideal's Stay Wired to WinIt's April, which means it's time for you to ignite your competitive spark with the a new challenge from IDEAL Nationals Canada. This month, IDEAL is asking you to show off your electrical knowledge with the most correct answers.

Five professionals and five apprentice winners will each take home a $100 VISA gift card and forged wire stripper from IDEAL.

 

 

 

 

Read More


 



William (Bill) BurrBy William (Bill) Burr

Section 32 – Fire Alarm Systems, Smoke and Carbon Monoxide Alarms, and Fire Pumps, as outlined in Rule 32-000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection, of

• local fire alarm systems

• permanently connected smoke and carbon monoxide alarms...

Read More


 

LumenpulseBy Matthew Payette

A lighting programming and control narrative is a document that is essential to coordinate the design/construction process with a fully realized final architectural product. It defines how lighting will integrate into the space and ultimately how humans will interact with that same space.

Sometimes there is a gap between the initial visions of the designers and the final product. Other times, the final product and operation of the lighting systems is achieved but after much project management distress...

Read More


 

Product News

  • Prev
MaxLite introduces the next generation of WallMax Open Face LED Wall Packs with field-selectable ...
Gotham has released its Incito™ 4” Direct-Indirect Wall Mount Cylinder luminaire. The new cylinder ...
Arlington's low cot MC cable fittings in a variety of sizes, are super convenient and ...
The Boca Flasher’s NanoLume has a streamline profile. It is a line voltage fixture perfect for Cove ...
120V AC Model, 24V DC Model, Model LB4R, cULus Listed. Type IC Rated – Approved for Direct Contact ...
 Available in Visual Comfort or Discrete optics configurations. Lumen packages from 1,600 to ...
For direct wire applications only. Consult factory for junction box sold separately. Aluminum cast ...
INFINA® DL-AC-FLEX2 is the next generation of high lumen output, specification grade, a flexible ...
Traditional in appearance, not in innovation. From below the ceiling, the Juno Podz take ...
The SLM is an ultra-slim, modern LED panel featuring edge-lit design for impressive visual comfort ...

 

11 Piece Insulated TorqueVario-S and SlimLine Blade Set• Individually tested to 10,000 volts AC and rated to 1,000 volts AC for safety and peace of mind.

• Meets VDE testing standards for protection against arc flash explosion.

• Torque accuracy of +/- 6% for confidence in precise tolerances.

• 33% narrower blade shafts for reaching deep set terminal block fasteners.

• Direct-molded insulation for protection against electrical shock and arc flash explosion.

Read More


 

 

FLIR TZ20 Dual Thermal Camera Drone PayloadPlug-and-Play Gimbal System for the DJI Matrice 200 Series and Matrice 300 Offers High-Definition FLIR Thermal Imaging with Zoom Capabilities to Improve Situational Awareness.

The FLIR Vue® TZ20, the first high resolution, dual thermal sensor gimbal purpose-built for the DJI®Matrice 200 Series and Matrice 300 airframes is now available in Canada. Featuring both a narrow-field-of-view and a wide-field-of-view 640x512 resolution FLIR Boson®thermal camera module, the Vue TZ20 offers greater situational awareness with a 20-times digital thermal zoom capability to complete public safety and industrial inspection missions both near and far. 

Read More


 

 

Autodesk TakeoffAutodesk, Inc. has announced the worldwide availability of Autodesk Takeoff, a new product that empowers estimators to perform 2D and 3D quantification workflows from a common data environment to increase collaboration, speed and accuracy during the estimation process.

Originally announced at Autodesk University in November 2020, Autodesk Takeoff will join Autodesk Build and Autodesk BIM Collaborate as part of the Autodesk Construction Cloud unified platform. The announcement comes one month after Autodesk Build and Autodesk BIM Collaborate were made available globally for Autodesk Construction Cloud customers. 

Read More


 

Peers & Profiles

  • Prev
Kyle Manfredi is the owner of ARK Electrical alongside his wife, Shannon. Operating out of ...
Like most major events over the last year, the COVID-19 pandemic put serious restrictions on the ...
This past December Jennifer Green was honoured with Canada’s Most Powerful Women Top 100 Award for ...
“It was quite surprising,” said Stephanie Smith of being named EHRC’s Leader of the Year. ...
As an advanced networked lighting controls company serving the industrial and large commercial ...
Trilliant, an international provider of utility solutions for advanced metering and smart grid ...
For more than a century, ABB has been investing in Canadian technologies and products to support ...
Mackenzie Gillan, a bright young lady from Baysville, Ontario, tells us about how she learned ...
Energy Efficient Lighting is a LED lighting manufacturer with nearly 30 years of industry ...
Dee Durant is an industrial electrician apprentice attending Conestoga College and an Ambassador ...


EIN Green 100 400

By Blake Marchand

This past December Jennifer Green was honoured with Canada’s Most Powerful Women Top 100 Award for the Skilled Trades category by WXN (Women’s Executive Network).

“It is truly an honour to be recognized by WXN and to be among this group of amazing women,” said Green of earning the distinction. “Throughout my career, I’ve worked with many great mentors and team members – to them, I say thank you for always inspiring me. I am absolutely thrilled.” Green is an industrial mechanic millwright by trade and works with Skills Ontario as Director of Competitions and Young Women’s Initiatives. 

Read More


 

Jo Istanbul Four Seasons ABy Owen Hurst

Recently, Electrical Industry Canada has developed a relationship with Women in Renewable Energy (WiRE), a non-for-profit group developing resources and networking potential for women and all working or planning to work within the renewable energy sector. Aside from being the WiRE President & CEO, Joanna Osawe is the Global Business Development Manager of Major Projects for DMC Power Inc.

EIN sat down with Osawe to learn more about WiRE and the substantial benefits it provides. Joanna is very personable and open regarding her career and her ambition, as well as the opportunities she is developing for women nationally and globally. 

Read More


 

Copper $US Dollar price per pound

Kerrwil Publications Great Place to Work. Certified December 2019 - December 2020

538 Elizabeth Street, Midland,Ontario, Canada L4R2A3 +1 705 527 7666
©2021 All rights reserved

Use of this Site constitutes acceptance of our Privacy Policy (effective 1.1.2016)
The material on this site may not be reproduced, distributed, transmitted, cached or otherwise used, except with the prior written permission of Kerrwil