Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

April 7, 2025

by William (Bill) Burr[i]

Section 32 – Fire Alarm Systems, Fire Pumps, and Carbon Monoxide Alarms.

The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the Code.

32

Section 32, as outlined in rule 32 -000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection, of fire alarm systems, fire pumps and smoke and carbon monoxide alarms required by the National Building Code of Canada as referenced in Appendix G. For further information, reference should also be made to Canadian Standard CAN/ULC – S524 Standard for the Installation of Fire Alarm Systems published by ULC Canada. Appendix B contains important additional helpful notes, and the CEC Handbook also contains helpful information.

Rule 32-100 specifies the requirements for conductors in fire alarm systems which include copper material, ampacity, use of optical fiber cables, use of stranded conductors, insulation rated at 300 volts, determining wire size for raceways or integral assemblies, and selection in accordance with rules 4-008(1) or 4-020(1).

Rule 32-102 outlines wiring methods for installation of conductors either in metal, non-metallic raceway, or having metal armour or sheath.  Where installed in buildings of combustible construction conductors may be installed in accordance with Section 12.  Conductors need to be installed independent of any other wiring except for point of supply, signal, ancillary device or communication circuits and must be insulated for the highest voltage rated conductor. Communication circuits must conform to Section 60.

Rule 32-104 requires that all exposed non-current-carrying parts of electrical equipment be bonded to ground in accordance with Section 10.  In addition, non-metallic fire alarm wiring systems must incorporate a bonding conductor.

Rule 32-106 denotes that for electrical supervision, each circuit conductor terminal shall be independentlyterminated. 

Rule 32-108 specifies that the fire alarm system power supply, except for included additional control units or transponders, be on a separate circuit and that the overcurrent devices and disconnecting means be permanently identified as a fire alarm system, be coloured red, and lockable in the on position.

Rule 32-110 provides installation requirements for permanently connected smoke alarms and carbon monoxide alarms in dwelling unitsthat are required by the National Building Code of Canada (see Appendix G).  The rule requires that smoke and carbon monoxide alarms be supplied from a circuit that will provide an indication, if shut off, for instance with a lighting or mixed lighting and receptacle circuit with no disconnect, including a GFCI or AFCI device, between the alarms and the branch circuit overcurrent device.  Interconnection of alarms may use a class 2 power supply in accordance with Rules 12-506 to 12-524.

Rule 32-200 requires that conductors for the supply of a fire pump supplied from the emergency power source have an ampacity not less than 125% of the full load current rating of the motor or sum of multiple motors and auxiliary motors and be protected from fire exposure to provide continuing operation during a fire as required by the National Building Code of Canada (see Appendix G)

Rule 32-202 outlines the requirements for wiring methods of fire pumps to be installed in metal raceways, in armour or metal sheathed cable, selected in accordance with Rule 4-888(1), in rigid non-metallic conduit imbedded in concrete, or electrical non-metallic tubing imbedded in concrete.

Rule 32-204 provides that a separate service box for a fire pump and equipment may be installed in conformance with Rule 32-206 below and, notwithstanding Rule 6-102(2), may be located remote from other service boxes.

Rule 32-206 requires that no disconnecting means, overcurrent protection or device capable of interrupting the fire pump circuit may be placed between the service box and the fire pump transfer switch or controller, except a circuit breaker that is permanently labeled identifying it as a fire pump disconnect. In addition, the circuit breaker must be lockable in the closed position and may be in the separate service box as in Rule 32-204 above. In the case where this circuit breaker is installed in an emergency power supply circuit between the emergency power source and the fire pump transfer switch the rating of the circuit breaker shall be as per Rule 28-200. Where it is installed in a normal supply circuit the rating should be not less than the overcurrent protection of the fire pump controller.

Rule 32-208 requires that where an on-site electrical transfer switch is used to provide emergency power supply to a fire pump, it must be provided solely for the fire pump, located in a barriered or separate compartment or enclosure, permanently labeled as the fire pump power transfer switch, and approved for fire pump service. Where more than one fire pump is provided, a transfer switch is required for each fire pump.

Rule 32-208 provides that overload and overheating protection for branch circuit, control, or equipment conductors shall not be required but shall be protected by the motor branch circuit overcurrent device.

Rule 32-210 specifies that ground fault protection shall not be installed in a fire pump circuit.

In the next installment, we will be discussing Section 34 – Signs and Outline Lighting.


[i] Source: CSA C22.1:24, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. © 2021 Canadian Standards Association. Please visit Store – CSA Group or call 1-800-463-6727. With the permission of CSA Group, the material is reproduced from CSA Group standard CSA C22.1:21, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. This material is not the complete and official position of CSA Group on the referenced subject, which is represented solely by the Standard in its entirety. While use of the material has been authorized, CSA Group is not responsible for the manner in which the data are presented, nor for any representations and interpretations. No further reproduction is permitted. For more information or to purchase standard(s) from CSA Group, please visit Store – CSA Group or call 1-800-463-6727.

[i] William (Bill) Burr is an associate member of the Canadian Electrical Code, Part 1, Technical Committee and formerly Chair of the Canadian Advisory Council on Electrical Safety (CACES), Chief Electrical and Elevator Inspector for the Province of BC & the Northwest Territories, Director of Electrical and Gas Standards Development and Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com..

Related Articles


Latest Articles

  • Hydro-Québec Announces New Grant to Accelerate Solar Self-Generation

    Hydro-Québec Announces New Grant to Accelerate Solar Self-Generation

    April 7, 2026 Hydro-Québec is launching a new grant for residential and business customers who want to install solar panels. The grant will provide for $1,000 per kW installed and covers up to 40% of eligible project costs, which can average between $5,000 and $6,000 for residential customers and approximately $45,000 for a business. The Read More…

  • Wesco’s Industrial Playbook Brings Application-Based Thinking to Canadian Industry

    Wesco’s Industrial Playbook Brings Application-Based Thinking to Canadian Industry

    April 6, 2026 Wesco has introduced its Industrial Playbook 2025, a Canadian-focused guide designed to help industrial customers, specifiers, and channel partners navigate a broad range of products, services, and application-specific solutions. Rather than functioning as a conventional line card or product catalogue, the playbook is structured as a practical resource built around real operating Read More…

  • ESA Provides an Update on its New Self-Serve Licensing Platform

    ESA Provides an Update on its New Self-Serve Licensing Platform

    March 27, 2026 In October 2025 Electrical Safety Authority (ESA) officially launched its new self-serve licensing platform, a modern system designed to transform how Master Electricians (MEs) and Licensed Electrical Contractors (LECs) manage their licensing needs. The platform replaces paper-based processes and provides a centralized, web-based experience for renewing and applying for licences, paying fees Read More…

  • BC Updates to Solar and Battery Rebate Program Come into Effect April/June 2026

    BC Updates to Solar and Battery Rebate Program Come into Effect April/June 2026

    March 27, 2026 Starting April 1, 2026, our battery rebate offer is changing. The offer will include: Applications submitted before April 1, 2026, will be reviewed under the current rebate amounts. New requirement for working with contractors Beginning June 1, 2026, solar and battery installations must be completed by a Home Performance Contractor Network (HPCN) member to Read More…


Changing Scene

  • Skills Ontario Supports Critical Skilled Trades Investment in the 2026 Ontario Budget

    Skills Ontario Supports Critical Skilled Trades Investment in the 2026 Ontario Budget

    March 27, 2026 — Skills Ontario welcomes the 2026 Ontario Budget: A Plan to Protect Ontario, released today by the Ontario Government and Minister of Finance Peter Bethlenfalvy, and applauds the continued commitment to investing in skilled trades, technologies, and workforce development. Skills Ontario was pleased to see the government maintain and strengthen its support Read More…

  • Toronto Hydro Launches New Pilot Program to Help Multiplex Builders Energize

    Toronto Hydro Launches New Pilot Program to Help Multiplex Builders Energize

    April 27, 2026 Toronto Hydro is launching a trailblazing customer pilot project designed to help local builders electrify multiplex housing without complex service upgrades. Through Toronto Hydro’s Multiplex PowerPlay, up to six multiplex projects can qualify to receive funding toward a smart energy load management system. Smart load management systems continuously monitor total building energy Read More…

  • Gescan and George Gordon Developments Strengthen Community Impact in Saskatchewan

    Gescan and George Gordon Developments Strengthen Community Impact in Saskatchewan

    March 25, 2026 Gescan, a Sonepar Company, is proud to highlight its continued commitment to supporting communities across Saskatchewan through their meaningful alliance with George Gordon Developments Ltd. (GGDL). With a strong focus on community development, workforce participation and inclusive growth, Gescan is working closely with GGDL to create training, employment and business opportunities for Saskatchewan residents. These efforts are particularly focused on supporting individuals Read More…

  • Electric Avenue Launches Incentive Program for EV Charging Installers

    Electric Avenue Launches Incentive Program for EV Charging Installers

    March 23, 2026 Halifax-based EV charging solutions provider Electric Avenue has announced the official launch of its new Contractor Incentive Program, a first-of-its-kind initiative in the EV charging industry, built exclusively for contractors who have completed the company’s Installer Certification course. The program rewards certified installers for every verified and networked installation they complete, offering cash Read More…